Case Note & Summary
The plaintiff, A.P. Thomas, filed two suits (Suit No. 349 of 1993 and Suit No. 2092 of 1993) against the defendants, Messrs Monarch Machinery Tools Pvt. Ltd. (defendant no.1) and Mrs. N. Kohli (defendant no.2), for recovery of sums of money allegedly due for work done by the plaintiff for defendant no.1. The plaintiff claimed that he had submitted bills for the work, and the balance remained unpaid. The plaintiff sought recovery of the principal amounts as per Exhibits 'I' and 'G' in the respective suits, along with interest at 18% per annum from the date of filing of the suit till realization. The defendants denied the claim, but the court found that the plaintiff had proved the work done and the bills submitted. The defendants failed to produce any evidence of payment or settlement of the accounts. The court held that the plaintiff was entitled to the principal sums claimed. Regarding interest, the court noted that under Section 34 of the Code of Civil Procedure, 1908, the court has discretion to award interest at a reasonable rate. Considering the facts, the court awarded interest at 6% per annum from the date of filing of the suit till realization, instead of the claimed 18%. The court decreed the suits in favor of the plaintiff with costs.
Headnote
A) Civil Procedure - Recovery Suit - Interest - Section 34 Code of Civil Procedure, 1908 - Plaintiff claimed balance for work done under bills; defendant failed to produce evidence of payment or settlement - Court held that plaintiff proved the work and bills, and defendant's denial was not supported by evidence - Interest awarded at 6% per annum from date of suit till realization, not 18% as claimed, as court has discretion under Section 34 CPC (Paras 1-10).
Issue of Consideration
Whether the plaintiff is entitled to recover the balance amount for work done for defendant no.1, and whether the plaintiff is entitled to interest at 18% per annum from the date of filing of the suit till realization.
Final Decision
Suits decreed in favor of the plaintiff with costs. Plaintiff entitled to principal sums as per Exhibits 'I' and 'G' with interest at 6% per annum from date of filing of suit till realization.
Law Points
- Contractual obligation to pay for work done
- Interest rate discretion under Section 34 CPC
- Burden of proof on defendant to challenge bills
- No evidence of payment or settlement