Case Note & Summary
The case involves a challenge by Oil & Natural Gas Corporation Ltd. (ONGC), a public sector undertaking, against an arbitral award dated 4-2-2005 made by an arbitral tribunal in favor of Western Geco International Ltd., a company incorporated under the laws of British Virgin Islands. The dispute arose from a contract for technical upgradation of ONGC's seismic survey vessel M.V. Sagar Sandhani. ONGC floated a tender in November 1999, and Western Geco submitted a bid offering Nessie 4 streamers equipped with hydrophones. The contract was awarded to Western Geco by letter dated October 10, 2000, accepted on October 25, 2000, and formally signed on June 18, 2001. The vessel was handed over to Western Geco on April 10, 2001, and was to be returned duly upgraded by July 9, 2001. However, delays occurred, and the vessel was returned later. The arbitral tribunal found that ONGC had breached the contract by delaying payment of the mobilization advance, which caused the delay in completion. The tribunal awarded US$ 2,936,607.82 with interest to Western Geco. ONGC challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that the award was contrary to the public policy of India. The High Court of Bombay, presided over by Justice D.K. Deshmukh, dismissed the petition, holding that the award was not contrary to public policy. The court found that the arbitral tribunal had correctly interpreted the contract and that the findings of breach and computation of damages were not perverse or irrational. The court also upheld the award of interest. The judgment emphasizes the limited scope of interference with arbitral awards under Section 34, particularly on the ground of public policy.
Headnote
A) Arbitration - Challenge to Award under Section 34 - Public Policy - The court considered whether an arbitral award can be set aside on the ground that it is contrary to the public policy of India under Section 34 of the Arbitration and Conciliation Act, 1996 - The court held that the award was not contrary to public policy and dismissed the petition - (Paras 1-10) B) Contract - Breach - Mobilization Advance - The dispute arose from a contract for technical upgradation of a seismic survey vessel where ONGC delayed payment of mobilization advance, causing delay in completion - The arbitral tribunal found ONGC in breach and awarded damages - The court upheld the finding that the delay in payment of mobilization advance constituted a breach by ONGC - (Paras 2-8) C) Damages - Computation - Interest - The arbitral tribunal awarded US$ 2,936,607.82 with interest - The court found no error in the computation of damages or the rate of interest - (Paras 9-10)
Issue of Consideration
Whether the arbitral award dated 4-2-2005 directing ONGC to pay US$ 2,936,607.82 to Western Geco International Ltd. is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the ground of being contrary to the public policy of India.
Final Decision
The High Court dismissed the petition and upheld the arbitral award dated 4-2-2005, directing ONGC to pay US$ 2,936,607.82 with interest to Western Geco International Ltd.
Law Points
- Arbitration Act
- 1996
- Section 34
- Public Policy
- Interpretation of Contract
- Breach of Contract
- Damages
- Interest





