Case Note & Summary
The State of Maharashtra filed a petition under Section 11 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator to resolve disputes arising from a development agreement with Kalyan Sangam Infratech Ltd. The agreement pertained to a slum rehabilitation project. The State terminated the agreement due to alleged breaches by the respondent. The arbitration clause in the agreement provided for resolution of disputes through arbitration. The State issued a notice to the respondent to appoint an arbitrator, but the respondent failed to do so. Consequently, the State approached the High Court. The respondent opposed the petition, primarily on the ground of limitation, arguing that the petition was filed beyond the prescribed period. The court examined the terms of the agreement and the correspondence between the parties. It held that the arbitration clause was valid and binding. Regarding limitation, the court observed that the dispute arose from the termination of the agreement and the petition was filed within a reasonable time. The court rejected the limitation objection. It allowed the petition and appointed a sole arbitrator to adjudicate the disputes. The court directed the arbitrator to proceed with the arbitration in accordance with the Act.
Headnote
A) Arbitration Law - Appointment of Arbitrator - Section 11 of the Arbitration and Conciliation Act, 1996 - Existence of Arbitration Clause - The State of Maharashtra filed a petition under Section 11 for appointment of an arbitrator after termination of a development agreement with Kalyan Sangam Infratech Ltd. for a slum rehabilitation project. The court found that the agreement contained an arbitration clause and the respondent failed to appoint an arbitrator despite notice. Held that the petitioner is entitled to appointment of an arbitrator by the court. (Paras 1-10) B) Arbitration Law - Limitation - Section 11 of the Arbitration and Conciliation Act, 1996 - The respondent raised an objection that the petition was barred by limitation. The court rejected this objection, noting that the dispute arose from termination of the agreement and the petition was filed within a reasonable time. Held that the petition is not barred by limitation. (Paras 11-15)
Issue of Consideration
Whether an arbitrator should be appointed under Section 11 of the Arbitration and Conciliation Act, 1996, given the existence of an arbitration clause in the development agreement and the respondent's failure to appoint an arbitrator despite notice.
Final Decision
The court allowed the petition and appointed a sole arbitrator to adjudicate the disputes between the parties. The arbitrator was directed to proceed in accordance with the Arbitration and Conciliation Act, 1996.
Law Points
- Arbitration and Conciliation Act
- 1996
- Section 11
- Appointment of Arbitrator
- Existence of Arbitration Clause
- Failure to Appoint Arbitrator
- Slum Rehabilitation Agreement
- Government Contract





