Bombay High Court Full Bench adjudicates the limitation period for recovery of electricity charges under Section 56(2) of the Electricity Act, 2003. Conflicting Division Bench decisions on whether dues beyond two years can be recovered when not continuously shown as arrears are reconciled.

High Court: Bombay High Court Bench: BOMBAY
  • 209
Judgement Image
Font size:
Print

Case Note & Summary

The case originated from a writ petition challenging an order of the Electricity Ombudsman regarding recovery of electricity dues for a period beyond two years. The distribution licensee had applied a wrong multiplier factor, leading to issuance of a differential bill for the period from September 2003 to December 2010. The Ombudsman restricted recovery to two years preceding the demand, i.e., from December 2008 onwards, relying on Section 56(2) of the Electricity Act, 2003. The licensee contended that the bar did not apply because the initial under-billing was due to an error, and relied on a Division Bench judgment in Rototex Polyester. The core issue was the interpretation of the limitation under Section 56(2) and whether it precludes recovery of dues beyond two years when the sum had not been continuously shown as arrears. A conflict existed between two Division Bench judgments of the Bombay High Court: Rototex Polyester (which held that the bar applies) and Awadhesh S. Pandey (which was interpreted differently). The licensees argued that when an error in billing is corrected, the limitation should not apply retrospectively, citing Rototex. The consumers and Ombudsman argued that the plain language of Section 56(2) restricts recovery to two years unless continuously shown as arrears, citing Pandey. The Learned Single Judge noted the conflict and observed prima facie that recovery beyond two years is barred if the amount was not continuously shown as recoverable. He referred the matter to a Full Bench to resolve the divergence. The Full Bench heard the matter on October 31, 2018, and pronounced judgment on March 12, 2019, but the text of the judgment provided ends before the final decision is revealed. Therefore, the substantive ruling of the Full Bench is not included in the excerpt.

Headnote

A) Electricity Law - Limitation for Recovery of Dues - Interpretation of Section 56(2) Electricity Act, 2003 - Whether a distribution licensee can recover electricity charges beyond two years from the date they became first due where the sum was not continuously shown as recoverable as arrears - The Division Bench in Rototex Polyester (2010 (4) BCR 456) held that the bar applies, while another Division Bench in Awadhesh S. Pandey (AIR 2007 Bombay 52) had a different view - The Full Bench was called upon to resolve the conflict (Paras 1-7)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the bar under Section 56(2) of the Electricity Act, 2003 prevents a distribution licensee from recovering electricity charges for a period beyond two years from the date they became first due, where the sum had not been continuously shown as recoverable as arrears of charges for electricity supplied

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Interpretation of Section 56(2) of the Electricity Act
  • 2003
  • limitation period for recovery of electricity dues
  • meaning of 'first due'
  • requirement of continuous demonstration as arrears
  • bar on cutting supply
Subscribe to unlock Law Points Subscribe Now

Case Details

2019 LawText (BOM) (03) 200

Writ Petition No.10764 of 2011 (with connected matters)

2019-03-12

S.C. Dharmadhikari, A.M. Badar, Smt. Bharati H. Dangre

A.A. Kumbhakoni, Rahul Sinha, S.B. Lolge, Abhay Nevagi, Sandesh Shukla, Amit Singh, Santosh Sawant, R.S. Apte, Padmanabh D. Pise, Rahul Narichania, Nidhish Mehrotra, Darshan Furia, Zoya Syed, Ashish Mehta, Neeta Masurkar, S.G. Thakur, Nieyaati Masurkar, Gautam Ankhad, Ankur Shah, Hemant Sethi, Shruti D. Vyas, Kavita Anchan, Arsh Mishra, Abhishek Khare, P. Kedia, Bindu Bhatia, Shyam Mehta, Arijit Maitra, Madhusudan G. Gawde

Maharashtra State Electricity Distribution Company Limited

The Electricity Ombudsman, Sub-Divisional Officer B.S.N.L. Deogad, and others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petitions challenging orders of the Electricity Ombudsman or directly raising issues regarding recovery of electricity dues beyond two years under Section 56(2) of the Electricity Act, 2003.

Remedy Sought

The petitioners (distribution licensees) sought recovery of differential electricity charges for past periods, while consumers/respondents resisted such recovery as barred by limitation under Section 56(2).

Filing Reason

Dispute over applicability of the two-year limitation for recovery of electricity charges where the correct multiplying factor was not applied initially, leading to differential amounts being demanded for periods exceeding two years.

Previous Decisions

The Electricity Ombudsman had passed orders limiting recovery to two years prior to the demand. In WP 10764/2011, the Learned Single Judge observed prima facie that Section 56(2) barred recovery beyond two years, but noted a conflict between two Division Bench judgments of the Bombay High Court on the point, and referred the matter to a Full Bench.

Issues

Whether Section 56(2) of the Electricity Act, 2003 bars recovery of electricity charges for a period beyond two years from the date they became first due, unless the sum was continuously shown as recoverable as arrears, in a case where the initial billing was based on an erroneous multiplier factor.

Submissions/Arguments

The petitioner licensees contended that the bar under Section 56(2) does not apply where the original billing was erroneous, relying on Rototex Polyester. The respondents and the Electricity Ombudsman argued that Section 56(2) restricts recovery to two years unless continuously shown as arrears, relying on Awadhesh S. Pandey.

Judgment Excerpts

no sum due from any consumer, under this section shall be recoverable after the period of two years from the date when such sum became first due unless such sum has been shown continuously as recoverable as arrear of charges for electricity supplied and the licensee shall not cut off the supply of the electricity. there is a clear conflict between two Judgments of this Court. On the interpretation of Section 56(2) of the Indian Electricity Act, 2003. the impugned bill seeking difference of electricity charges levied on the basis of multiplying factor one instead of multiplying factor of 2 was issued in the month of December 2010 for the period of September, 2003 to December, 2010.

Procedural History

The writ petition was placed before a Learned Single Judge who on 24-1-2012 noted a conflict between two Division Bench judgments on interpretation of Section 56(2) of the Electricity Act, 2003, and referred the matter to a Full Bench. The Full Bench heard the matter on 31-10-2018 and pronounced judgment on 12-3-2019.

Acts & Sections

  • Electricity Act, 2003: 56(2), 42(5), 42(6)
  • Maharashtra Apartments Ownership Flats Act, 1971: 2
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Madras High Court Dismisses Writ Petition Challenging Rejection of Scheduled Tribe Community Certificate. Court Upholds Rejection Order Due to Petitioner's Failure to Produce Documentary Evidence and Existence of Contradictory Most Backward Class Cer...
Related Judgement
High Court Bombay High Court Allows Appeal in Workmen's Compensation Case — Cause of Action for Personal Injury Does Not Survive to Heirs Under Section 306 of Indian Succession Act. The court held that the maxim actio personalis moritur cum persona applies to...