Case Note & Summary
The dispute arose out of a contract for improvement of riding quality of NH-4A in Goa awarded by the State of Goa to P.B. Ibrahim, a Class I PWD Contractor. The plaintiff filed Civil Suit No.72/2005 seeking recovery of amounts for work done, including escalation claims for delay caused by the defendants. The Trial Court decreed the suit in part, awarding certain amounts but denying interest from the date of suit till realization and rejecting escalation claims. Both parties appealed: the contractor (First Appeal No.60/2011) sought interest and escalation, while the State (First Appeal No.33/2017) challenged the maintainability of the suit due to an arbitration clause. The High Court held that the civil suit was maintainable as the defendants did not invoke Section 8 of the Arbitration and Conciliation Act, 1996. On interest, the Court held that under Section 34 of the Code of Civil Procedure, 1908, the court has discretion to award interest at a reasonable rate, and the Trial Court erred in denying interest entirely; the Court awarded interest at 6% per annum from the date of suit till realization. On escalation claims, the Court found that the plaintiff had not pleaded any escalation clause or basis in the plaint, and therefore such claims could not be granted. The appeals were disposed of accordingly, with the contractor's appeal partly allowed and the State's appeal dismissed.
Headnote
A) Civil Procedure - Interest under Section 34 CPC - Discretionary Power - The court has discretion to award interest at different rates for pre-reference and post-decree periods, and the rate of 6% per annum from date of suit till realization is reasonable - Held that the Trial Court's denial of interest was not justified (Paras 10-15). B) Contract Law - Escalation Claims - Not Pleaded - The plaintiff did not plead or prove any escalation clause in the contract, and the claim for escalation was not part of the suit - Held that such claims cannot be awarded (Paras 16-18). C) Arbitration and Conciliation Act, 1996 - Section 8 - Bar to Civil Suit - The contract contained an arbitration clause, but the defendants did not apply under Section 8 to refer the dispute to arbitration - Held that the civil suit was maintainable (Paras 5-6).
Issue of Consideration
Whether the Trial Court erred in denying interest on the decretal amount from the date of suit till realization and in not awarding escalation claims for work done beyond stipulated time.
Final Decision
First Appeal No.60/2011 is partly allowed; the impugned judgment is modified to award interest at 6% per annum on the decretal amount from the date of suit till realization. First Appeal No.33/2017 is dismissed. No order as to costs.
Law Points
- Interest under Section 34 CPC is discretionary
- Court can award different rate for pre-reference and post-decree periods
- Escalation claims not pleaded cannot be awarded
- Arbitration clause does not bar civil suit if no arbitration agreement
- Court can grant interest on decretal amount from date of suit till realization





