Case Note & Summary
The Petitioner, Rashtriya Chemicals & Fertilizers Ltd. (RCF), a public sector company, entered into an Agreement of Affreightment with the Respondent, J.S. Ocean Liner Pte. Ltd. (JSOL), on 6 November 2006. Under the agreement, JSOL was to provide vessels to carry rock phosphate from Aqaba, Jordan to Mumbai from November 2006 to December 2007. RCF had a purchase order from JPMC of Jordan for a minimum of 2.25 lakh MTs of rock phosphate. JSOL only shipped 1,63,255 MTs across 13 voyages, falling short of the minimum contracted quantity. RCF had to purchase the deficit material at higher prices and higher freight, and also borrowed some material locally. Additionally, part of the cargo was received in damaged condition, and JSOL agreed to compensate but did not. RCF stopped paying the balance 10% freight and sought to adjust it against losses. JSOL filed a claim for the balance freight of USD 293,584.78, and RCF filed a counterclaim for losses due to short shipment and damaged cargo. The Arbitrator passed an interlocutory award on 2 September 2010 holding JSOL liable for breach, and a final award on 17 February 2011 quantifying damages. RCF challenged both awards under Section 34 of the Arbitration and Conciliation Act, 1996. The Court dismissed both petitions, holding that the Arbitrator's findings were based on evidence and not perverse, and that the scope of interference under Section 34 is limited. The Court noted that the Arbitrator had considered the terms of the contract, the correspondence between parties, and the evidence on record. The Court also held that the interlocutory award was permissible and that the challenge to it was without merit. The petitions were dismissed with no order as to costs.
Headnote
A) Arbitration Law - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Interlocutory and Final Awards - The Petitioner challenged an interlocutory award dated 2 September 2010 and a final award dated 17 February 2011 passed by the same Arbitrator. The Court held that the scope of interference under Section 34 is limited and the Arbitrator's findings on breach of contract and quantification of damages were based on evidence and not perverse. (Paras 1-10) B) Contract Law - Breach of Contract - Damages - The Agreement of Affreightment required the Respondent to ship minimum 2.25 lakh MTs of rock phosphate. The Respondent shipped only 1,63,255 MTs. The Arbitrator found the Respondent in breach and awarded damages for the deficit quantity. The Court upheld the award, noting that the Petitioner had to purchase deficit material at higher prices and freight. (Paras 2-5) C) Arbitration Law - Interlocutory Award - The Arbitrator passed an interlocutory award on liability. The Court held that such an award is permissible under the Act and the challenge to it was without merit. (Paras 1, 6-8)
Issue of Consideration
Whether the impugned interlocutory and final awards passed by the learned Arbitrator are liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on the grounds of being contrary to the terms of the contract, perverse, or in conflict with the public policy of India.
Final Decision
Both Arbitration Petitions are dismissed. No order as to costs.
Law Points
- Section 34 of Arbitration and Conciliation Act
- 1996
- Public Policy
- Breach of Contract
- Damages
- Interlocutory Award
- Final Award



