Case Note & Summary
The dispute arose from a transport contract for emergency coal transportation from New Majri Colliery to Paras power station. The plaintiff, a transport contractor, responded to an inquiry by the Maharashtra State Electricity Board and was issued a work order dated 28.4.1979 specifying a distance of 263 km and a rate of 70 paise per tonne per km. The work was to be completed urgently before the rainy season. Upon commencing work, the plaintiff discovered that the actual shortest distance was 307 km, a difference of 44 km. He submitted his first bill on 14.5.1979 under protest, noting the discrepancy, and continued the work until completion on 9.6.1979. All subsequent bills were also submitted under protest. The defendants paid the bills based on 263 km, and after the work was completed, the plaintiff demanded payment for the extra distance. Having received no response, he filed Special Civil Suit No. 165 of 1982 claiming Rs. 5,62,845.46, including interest, and sought rectification of the contract distance under Section 26 of the Specific Relief Act, 1963. The defendants denied the claim, asserting that the plaintiff had accepted the contract without protest and was estopped from claiming a higher amount. They argued that the court could not alter the terms of a concluded contract and that there was no mutual mistake. The trial court dismissed the suit, holding that there was no mutual mistake and that the plaintiff by his conduct was estopped from making the claim. On appeal, the High Court framed issues regarding the actual distance, mutual mistake, estoppel, and entitlement to the claim. The court noted that a commissioner appointed earlier had measured the distance and confirmed it as 307 km; this finding was not challenged. The court held that both parties had operated under a mutual mistake as to the distance, making the contract liable to be rectified under Section 26 of the Specific Relief Act. The plaintiff had not acted gratuitously and was entitled to compensation for the excess work under Section 70 of the Indian Contract Act, 1872. The court further held that the plaintiff's submission of bills under protest and the ongoing nature of the emergency work negated any waiver or estoppel. Accordingly, the appeal was allowed, the trial court's decree set aside, and the suit decreed in favour of the plaintiff for the principal amount with interest.
Headnote
A) Contract Law - Rectification of Instruments - Mutual Mistake as to Distance - Specific Relief Act, 1963, Section 26 - The work order mentioned a distance of 263 km but the actual shortest distance was 307 km; both parties were under a mutual mistake as to the true distance. - Held that the contract was liable to be rectified to reflect the true distance, and the suit for rectification was maintainable under Section 26. (Paras 8-9) B) Contract Law - Quantum Meruit - Claim for Excess Work Done - Indian Contract Act, 1872, Section 70 - The plaintiff transported coal over an additional 44 km due to the mutual mistake and submitted bills under protest; he did not act gratuitously. - The court applied Section 70 and held that the plaintiff was entitled to claim compensation for the excess work performed. (Paras 5, 9) C) Civil Procedure - Estoppel and Waiver - Conduct of Party in Performance - General Principles - The plaintiff accepted payments but consistently noted protests on bills regarding the distance discrepancy; he did not abandon the work. - The court held that estoppel and waiver did not operate because the plaintiff's conduct was under protest and the contract was subject to rectification. (Paras 6-7)
Issue of Consideration
Whether the contract could be rectified under Section 26 of the Specific Relief Act, 1963 on grounds of mutual mistake as to distance; Whether the plaintiff is entitled to claim for the extra work done under Section 70 of the Indian Contract Act, 1872; Whether the plaintiff's conduct of accepting payment without formally abandoning the contract operates as estoppel or waiver
Final Decision
First Appeal allowed. Judgment and decree of trial court set aside. Plaintiff entitled to claim the principal amount of Rs.4,14,643.46 at the agreed rate for excess 44 kms with interest at 12% per annum as prayed. The contract distance rectified to 307 kms.
Law Points
- Mutual mistake in contract can be rectified under Section 26 Specific Relief Act
- Party performing extra work due to mutual mistake entitled to compensation under Section 70 Contract Act
- Estoppel and waiver not applicable when bills submitted under protest and contract liable to rectification



