Case Note & Summary
The Petitioner, Mahanagar Telephone Nigam Ltd (MTNL), challenged an arbitral award dated 31st October 2009 passed by a sole arbitrator under Section 34 of the Arbitration and Conciliation Act, 1996. The challenge was restricted to claims 1, 2, and 7. The work order was issued to the Respondent, M/s B. Bhamra Construction Co., on 29th March 2004, with a completion date of 17th October 2005 (18 months). The work was not completed within the stipulated period and was extended from time to time by consent of both parties, finally being completed on 11th July 2007, resulting in a delay of 20.8 months. The contract contained a clause stating: 'No escalations shall be payable for a work for which stipulated period is 18 months or less.' This clause was agreed upon by the parties and replaced the original clause 51.1. The arbitrator, however, awarded escalation costs to the Respondent by applying the formula of the deleted clause 51.1, reasoning that since the period was extended beyond 18 months by consent, the escalation clause lost its importance and the contractor was entitled to escalation. The Petitioner argued that the arbitrator's award was contrary to the express terms of the contract. The Court held that the arbitrator's interpretation was patently illegal and against the express contractual clause. The clause clearly barred escalation for works with a stipulated period of 18 months or less, and the extension of time by consent did not revive the deleted clause or create a right to escalation. The Court set aside the award in respect of claims 1, 2, and 7, and dismissed the petition for the remaining claims.
Headnote
A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Court set aside award of escalation costs where contract clause expressly barred escalation for works with stipulated period of 18 months or less, and extension of time by consent did not revive the deleted clause - Held that the arbitrator's award was patently illegal and contrary to the terms of the contract (Paras 1-10).
Issue of Consideration
Whether the arbitrator erred in awarding escalation costs for a work where the stipulated period was 18 months or less, and the contract expressly barred escalation, even though the period was extended by consent.
Final Decision
The Court allowed the petition in part, setting aside the arbitral award in respect of claims 1, 2, and 7. The petition was dismissed for the remaining claims.
Law Points
- Arbitration
- Contract Interpretation
- Escalation Clause
- Extension of Time
- Section 34 Arbitration and Conciliation Act
- 1996


