Bombay High Court Partially Sets Aside Arbitral Award in MTNL v. B. Bhamra Construction Co. — Escalation Claims Barred by Contractual Clause Despite Extension of Time. The court held that an arbitrator cannot award escalation costs contrary to an express contractual bar, even if the contract period is extended by consent.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 146
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, Mahanagar Telephone Nigam Ltd (MTNL), challenged an arbitral award dated 31st October 2009 passed by a sole arbitrator under Section 34 of the Arbitration and Conciliation Act, 1996. The challenge was restricted to claims 1, 2, and 7. The work order was issued to the Respondent, M/s B. Bhamra Construction Co., on 29th March 2004, with a completion date of 17th October 2005 (18 months). The work was not completed within the stipulated period and was extended from time to time by consent of both parties, finally being completed on 11th July 2007, resulting in a delay of 20.8 months. The contract contained a clause stating: 'No escalations shall be payable for a work for which stipulated period is 18 months or less.' This clause was agreed upon by the parties and replaced the original clause 51.1. The arbitrator, however, awarded escalation costs to the Respondent by applying the formula of the deleted clause 51.1, reasoning that since the period was extended beyond 18 months by consent, the escalation clause lost its importance and the contractor was entitled to escalation. The Petitioner argued that the arbitrator's award was contrary to the express terms of the contract. The Court held that the arbitrator's interpretation was patently illegal and against the express contractual clause. The clause clearly barred escalation for works with a stipulated period of 18 months or less, and the extension of time by consent did not revive the deleted clause or create a right to escalation. The Court set aside the award in respect of claims 1, 2, and 7, and dismissed the petition for the remaining claims.

Headnote

A) Arbitration - Section 34 of Arbitration and Conciliation Act, 1996 - Challenge to Arbitral Award - Court set aside award of escalation costs where contract clause expressly barred escalation for works with stipulated period of 18 months or less, and extension of time by consent did not revive the deleted clause - Held that the arbitrator's award was patently illegal and contrary to the terms of the contract (Paras 1-10).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitrator erred in awarding escalation costs for a work where the stipulated period was 18 months or less, and the contract expressly barred escalation, even though the period was extended by consent.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Court allowed the petition in part, setting aside the arbitral award in respect of claims 1, 2, and 7. The petition was dismissed for the remaining claims.

Law Points

  • Arbitration
  • Contract Interpretation
  • Escalation Clause
  • Extension of Time
  • Section 34 Arbitration and Conciliation Act
  • 1996
Subscribe to unlock Law Points Subscribe Now

Case Details

2012 LawText (BOM) (02) 63

Arbitration Petition No.673 of 2010

2012-02-07

Anoop V. Mohta

Mr. Niranjan P. Shimpi a/w Mr. K. G. Nagwekar, for Petitioner; Mr. U. S. Samudrala a/w Mr. Satish Sharma, for Respondent

Mahanagar Telephone Nigam Ltd

M/s B. Bhamra Construction Co

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

Petitioner sought to set aside the arbitral award in respect of claims 1, 2, and 7.

Filing Reason

The Petitioner challenged the award on the ground that the arbitrator granted escalation costs contrary to the express contractual clause barring escalation for works with a stipulated period of 18 months or less.

Previous Decisions

The sole arbitrator passed an award dated 31st October 2009 granting escalation costs to the Respondent.

Issues

Whether the arbitrator's award granting escalation costs is contrary to the express terms of the contract and thus patently illegal under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Petitioner argued that the contract expressly barred escalation for works with a stipulated period of 18 months or less, and the extension of time by consent did not entitle the contractor to escalation. Respondent argued that since the period was extended beyond 18 months, the escalation clause lost its importance and the contractor was entitled to escalation.

Ratio Decidendi

An arbitrator cannot award escalation costs contrary to an express contractual clause barring escalation, even if the contract period is extended by consent. Such an award is patently illegal and liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

No escalations shall be payable for a work for which stipulated period is 18 months or less The learned arbitrator therefore considering this clause, and after going through the material placed on record by the contractor granted the claim by adopting the formula of clause 51.1 which was admittedly deleted in the above circumstance.

Procedural History

The work order was issued on 29th March 2004. The work was completed on 11th July 2007. Disputes arose and were referred to sole arbitration. The arbitrator passed an award on 31st October 2009. The Petitioner filed Arbitration Petition No.673 of 2010 under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the award.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeal by Dissenting Secured Creditor in Insolvency Resolution Process Under Insolvency and Bankruptcy Code, 2016. The Court upheld the commercial wisdom of the Committee of Creditors in approving a resolution plan, ruling tha...
Related Judgement
Supreme Court Supreme Court Quashes Requisition Order in U.P. Accommodation Requisition Act Case for Lack of Inquiry and Natural Justice Violation. Owner in Actual Occupation of Premises Could Not Be Deprived Without District Magistrate Determining Existence of Su...