Supreme Court Dismisses DISCOM's Appeal in Solar PPA Force Majeure Dispute — Restrictive Appellate Jurisdiction Under Section 125 of Electricity Act, 2003 Affirmed. Government Delays in Approvals Constitute Force Majeure; No Tariff Reduction or Liquidated Damages When Developer Not at Fault.

In Favour of Accused
  • 1565
Judgement Image
Font size:
Print

Case Note & Summary

The Supreme Court of India dismissed appeals by Bangalore Electricity Supply Company Limited (BESCOM) against an order of the Appellate Tribunal for Electricity (APTEL) that had allowed the respondents' claim for force majeure extension and set aside tariff reduction and liquidated damages. The dispute arose from a Power Purchase Agreement (PPA) signed on 29 August 2015 between BESCOM and a solar power developer (SPD) under a Karnataka government policy to promote solar energy projects by farmers. The PPA required commercial operation within 18 months from the effective date, which was defined as the date of signing. However, the respondents faced delays in obtaining land conversion approval, evacuation approvals, and bay construction due to government authorities' inaction. They sought a 6-month extension under Article 2.5, which BESCOM initially approved on 2 March 2017. Later, KERC directed all extensions to be filed before it, and the respondents filed a petition invoking force majeure under Article 8.3. The project was commissioned on 24 August 2017, within the extended period. KERC rejected the force majeure claim, imposed liquidated damages, and reduced tariff from Rs. 8.40 to Rs. 4.36 per unit. APTEL reversed this, holding that the delays were beyond the respondents' control and that the effective date should be the date of KERC approval (7 September 2015), making the project timely. APTEL also directed payment of the original tariff with late payment surcharge. The Supreme Court upheld APTEL's decision, emphasizing the restrictive scope of its appellate jurisdiction under Section 125 of the Electricity Act, 2003, and finding no perversity or error in APTEL's factual findings. The court held that force majeure was correctly applied, the extension was valid, and no tariff reduction or liquidated damages were warranted.

Headnote

A) Electricity Law - Force Majeure - Interpretation of Force Majeure Clause - Power Purchase Agreement, Article 8.3 - The court examined whether delays in obtaining land conversion, evacuation approvals, and bay construction due to government authorities constituted force majeure. Held that the respondents had taken all due diligence and the delays were beyond their control, thus force majeure was applicable (Paras 21-25).

B) Electricity Law - Appellate Jurisdiction - Scope under Section 125 of Electricity Act, 2003 - The court held that the restrictive scope of appellate jurisdiction under Section 125 is a product of statutory preconditions and necessary to enable freedom to statutory regulator and Tribunal to develop sectorial laws through a principled and consistent approach (Paras 13-15).

C) Electricity Law - Effective Date of PPA - Calculation of Scheduled Commissioning Date - Article 1.1(xxviii) read with Article 4.1(c) - The court approved APTEL's view that the effective date is the date of approval by KERC, not the date of signing, as the PPA becomes effective only upon regulatory approval (Para 23).

D) Electricity Law - Extension of Time - Estoppel - The court noted that the appellant had itself approved a 6-month extension after scrutiny by a Technical Committee, and thus could not later contest the delay (Para 24).

E) Electricity Law - Tariff Reduction - Not Justified When Delay Not Attributable to Developer - The court upheld APTEL's direction to pay the original tariff of Rs. 8.40 per unit with late payment surcharge, as the delay was due to force majeure and not the respondents' fault (Paras 25-26).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the extension of the Scheduled Commissioning Date was occasioned under the force majeure clause of the Power Purchase Agreement, and consequently, whether the reduction in tariff payable to the respondents is justified.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeals, upholding APTEL's order. It held that the force majeure clause was correctly applied, the extension of time was valid, and no tariff reduction or liquidated damages were warranted. The appellant was directed to pay the difference in tariff with late payment surcharge as per Article 6.4 of the PPA.

Law Points

  • Force majeure clause must be strictly interpreted
  • burden of proof on party claiming force majeure
  • appellate jurisdiction under Section 125 of Electricity Act
  • 2003 is restrictive
  • effective date of PPA is date of approval by regulatory commission
  • delay caused by government authorities not attributable to developer
  • extension of time granted by DISCOM cannot be later contested
  • reduction in tariff not justified when delay not attributable to developer
  • liquidated damages not imposable when delay due to force majeure.
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (SC) (08) 295

Civil Appeal No. 7595 of 2021 with Civil Appeal No. 7608 of 2021 and Civil Appeal No. 6386 of 2021

2024-08-27

Pamidighantam Sri Narasimha

2024 INSC 631

K.M. Nataraj, ASG; Yasobant Das, Senior Advocate (for appellants); Basava Prabhu Patil, Senior Advocate (for respondents)

Bangalore Electricity Supply Company Limited

Hirehalli Solar Power Project LLP & Others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against the order of the Appellate Tribunal for Electricity (APTEL) allowing force majeure claim and setting aside tariff reduction and liquidated damages under a Power Purchase Agreement for a solar power project.

Remedy Sought

The appellant (BESCOM) sought to restore KERC's order imposing liquidated damages and reducing tariff; the respondents sought to uphold APTEL's order granting force majeure extension and full tariff.

Filing Reason

Dispute over whether delay in commissioning of solar power project was due to force majeure, justifying extension of time and avoiding tariff reduction and liquidated damages.

Previous Decisions

KERC rejected force majeure claim, imposed liquidated damages, and reduced tariff. APTEL reversed, allowing force majeure, setting aside liquidated damages, and directing payment of original tariff with late payment surcharge.

Issues

Whether the delay in commissioning the solar power project was covered under the force majeure clause of the PPA. Whether the reduction in tariff and imposition of liquidated damages by KERC were justified. What is the scope of appellate jurisdiction under Section 125 of the Electricity Act, 2003?

Submissions/Arguments

Appellant argued that force majeure clause must be strictly interpreted, no force majeure event occurred, and respondents failed to give written notice as required under Article 8.3(b)(i). Respondents argued that delays were due to government authorities' inaction, they acted with due diligence, and the extension was already approved by appellant.

Ratio Decidendi

The restrictive scope of appellate jurisdiction under Section 125 of the Electricity Act, 2003 is a product of statutory preconditions and necessary to enable freedom to statutory regulator and Tribunal to develop sectorial laws. On merits, delays caused by government authorities in granting approvals constitute force majeure when the developer has acted with due diligence. The effective date of a PPA is the date of regulatory approval, not the date of signing. An extension of time granted by the DISCOM after scrutiny cannot be later contested. Reduction in tariff and liquidated damages are not justified when delay is due to force majeure.

Judgment Excerpts

The short issue arising from these appeals is whether the extension of the Scheduled Commissioning Date was occasioned under the force majeure clause of the Power Purchase Agreement, and consequently, whether the reduction in tariff payable to the respondents is justified. We have held that the restrictive scope of appellate jurisdiction is a product not only of the statutory preconditions, but also a necessary measure to enable freedom to statutory regulator and Tribunal to develop sectorial laws through a principled and consistent approach.

Procedural History

The respondents filed a petition before KERC seeking extension of time and invoking force majeure. KERC rejected the petition on 18 September 2018, imposed liquidated damages, and reduced tariff. The respondents appealed to APTEL, which allowed the appeal on [date not mentioned]. BESCOM then appealed to the Supreme Court under Section 125 of the Electricity Act, 2003.

Acts & Sections

  • Electricity Act, 2003: Section 125
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Applications to Recall Consent Terms and Set Aside Consent Decrees in Property Disputes Between Family Members. Court Holds That Consent Terms Recorded by Counsel Are Binding on Parties and Cannot Be Challenged on Grounds ...
Related Judgement
Supreme Court Supreme Court Allows Appeal in CRPF Service Matter — Directs Implementation of High Court Order for Reinstatement and Promotion. Minor penalty of reduction to lower stage for three years without cumulative effect must be implemented with consequent...