Bombay High Court Upholds Appeal by Purchasers in Specific Performance Suit Against Builder; Grants Temporary Injunction Restraining Creation of Third Party Interest. Builder’s Demand for Full Payment Before Possession Ready Held Unjustified Under Agreement, Balancing Amount Deposited by Purchasers in Court.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

This appeal arose from an order of the trial court rejecting an application for temporary injunction in a suit for specific performance. The plaintiffs-appellants had entered into an agreement dated 30 August 2006 with defendant no.1, a builder, to purchase a flat for Rs.7,20,000/-. The agreement stipulated that Rs.5,00,000/- of the balance consideration was to be paid at the time of handing over possession, and Rs.1,50,000/- on completion of exterior painting and waterproofing. The plaintiffs also entered into a loan arrangement with defendant no.2 bank. When the bank failed to provide the loan, the builder insisted on full payment and threatened to dispose of the flat. The plaintiffs then filed a suit for specific performance against the builder and the bank, and sought temporary injunction to restrain the builder from creating third party interests. The trial court rejected the application, holding that the plaintiffs had failed to comply with paragraph 7 of the agreement, which set a timeline for completing terms within one month of registration. On appeal, the High Court held that the trial court misconstrued the contract. Reading paragraphs 5 and 7 together, the obligation to pay the balance became due only when the builder was ready to deliver possession. Since construction was only 80% complete and possession could not be handed over, the builder could not demand payment. The plaintiffs had also deposited the entire balance amount of Rs.6,50,000/- in court. The High Court further observed that the bank was a necessary party in such a suit. Accordingly, the appeal was allowed, the impugned order was set aside, and the builder was restrained from creating any third party interest or parting with possession of the flat pending the suit. The Civil Application was disposed of as the appeal itself was finally decided.

Headnote

A) Contract Law - Specific Performance - Interpretation of Payment Clause - Sale of Immovable Property - Payment Schedule Dependent on Possession - The balance consideration of Rs.5,00,000/- was payable at the time of handing over possession and Rs.1,50,000/- on completion of exterior painting and waterproofing - Builder not yet ready with possession - Held that builder cannot demand payment before completion and delivery of possession - Trial court erroneously relied on para 7 ignoring para 5 - Plaintiffs entitled to temporary injunction (Paras 5-7).

B) Civil Procedure - Joinder of Parties - Necessary Party - Specific Performance Suit - Bank Providing Housing Loan - In a suit for specific performance of flat sale agreement, the bank providing finance is a necessary party, even if there is a grievance against the bank (Para 5).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the trial court erred in rejecting the application for temporary injunction on the ground that the plaintiff had failed to comply with the terms of the contract, and whether the plaintiff was entitled to injunction restraining the builder from creating third party interests.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Appeal allowed. Impugned order set aside. Defendant No.1 restrained from creating any third party interest and/or parting with possession of flat No.11 pending the suit. Rule made absolute. Civil Application disposed of accordingly.

Law Points

  • Interpretation of contract: payment obligation becomes due only when seller is ready to deliver possession
  • temporary injunction can be granted to protect subject matter of specific performance suit
  • bank providing finance is necessary party in specific performance suit
Subscribe to unlock Law Points Subscribe Now

Case Details

2011 LawText (BOM) (08) 64

Appeal from Order No. 233 of 2011 with Civil Application No. 344 of 2011

2011-08-10

J.H. Bhatia, J

2011:BHC-AS:18380

Mr J.C. Patil for Appellants, Ms. Samiksha Mhatre i.b Kiran Kandpile for Respondent No.1

Devdatta Chandrakant Patil and Snehal Devadatta Patil

M/s Thalkar Developers through Prop/Partner Mr. Manohar alias Laxman Shankar Thalkar and The Managing Director, IDBI Home Finance Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit for specific performance of agreement to sell a flat and for loan against builder developer and bank.

Remedy Sought

Plaintiffs sought temporary injunction to restrain defendant no.1 builder from creating any third party interest in the suit flat pending the suit.

Filing Reason

Builder refused to sell the flat and threatened to dispose of it after plaintiffs failed to pay balance consideration due to bank not providing loan.

Previous Decisions

The trial court had rejected the application for temporary injunction under Exhibit 5, holding that plaintiffs had failed to comply with paragraph 7 of the agreement.

Issues

Whether the trial court erred in rejecting the temporary injunction application on misinterpretation of the contract terms regarding payment schedule, and whether the plaintiffs were entitled to an injunction restraining the builder from creating third party interests.

Submissions/Arguments

Appellants contended that the balance payment under the agreement was due only when the builder was ready to hand over possession, and as construction was incomplete the builder could not demand payment; they had deposited the balance amount in court. Respondent No.2 contended that the plaintiffs were not in a position to fulfill the terms of the contract and had failed to make payment on time, and therefore were not entitled to temporary injunction.

Ratio Decidendi

In a suit for specific performance of a construction-linked sale agreement, the obligation to pay the balance consideration arises only when the builder is in a position to deliver possession. The builder cannot demand payment before the construction is complete and possession is ready. Where the plaintiff has deposited the balance amount in court, a temporary injunction to protect the subject matter is appropriate. The trial court's order rejecting injunction on misinterpretation of the agreement's terms is erroneous.

Judgment Excerpts

the Defendant no.1 could demand payment of balance amount of consideration only when the construction would be ready and he would be in a position to deliver possession of the flat. the trial Court clearly committed an error in holding that the Plaintiff had failed to comply with the terms and conditions contained in paragraph 7 of the Agreement.

Procedural History

Plaintiffs filed suit for specific performance and also impleaded bank. Plaintiffs filed application Exhibit 5 seeking temporary injunction against builder. Trial court rejected the application. Plaintiffs filed appeal from order before High Court. During pendency of appeal, plaintiffs deposited balance consideration of Rs.6,50,000/- with trial court.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Petition for Removal of Executors in Testamentary Matter Due to No Evidence of Malfeasance and Adequate Administration. Court Rules That Executors’ Gratuitous Duties Under Section 301 Indian Succession Act, 1925 Cannot B...
Related Judgement
High Court Bombay High Court Upholds Appeal by Purchasers in Specific Performance Suit Against Builder; Grants Temporary Injunction Restraining Creation of Third Party Interest. Builder’s Demand for Full Payment Before Possession Ready Held Unjustified Under ...