Bombay High Court Dismisses Petition Challenging Tender Award in Irrigation Project — No Arbitrariness Found in Relaxation of Eligibility Criteria. Court held that tender conditions are not statutory and can be relaxed if not essential, and that the petitioner failed to establish mala fides or arbitrariness.

High Court: Bombay High Court Bench: GOA
  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Kailash Constructions, challenged the award of a tender by the Vidarbha Irrigation Development Corporation (VIDC) to respondent no. 5, M/s Mavin Switchgears and Control, for the design, supply, erection, testing and commissioning of a 132 KV transmission line. The petitioner alleged that respondent no. 5 did not meet the technical qualifying requirement under clause 1.13.2(a) of having successfully completed a similar work of at least 32 km in a single order during the last three years. Additionally, the petitioner contended that respondent no. 5 failed to submit two tender documents in envelope no. 1 as required, and that the department improperly relaxed these conditions to favour respondent no. 5. The petitioner also argued that the security deposit was not deposited within the stipulated time. The respondents, including VIDC and respondent no. 5, defended the award, stating that the conditions were not essential and could be relaxed, and that the decision was taken in a fair and transparent manner. The High Court, after hearing the parties, held that the conditions in question were not essential conditions but technical qualifying requirements, and the department had the discretion to relax them. The court found no arbitrariness or mala fides in the decision, noting that the petitioner had no vested right to the contract. The court dismissed the petition, upholding the tender award to respondent no. 5.

Headnote

A) Tender Law - Judicial Review - Scope of Interference - Court's power to review tender decisions is limited to arbitrariness, mala fides, or bias - The court cannot sit as an appellate authority over technical evaluations or relaxations of conditions unless they are essential and non-waivable - Held that the relaxation of clause 1.13.2(a) and the acceptance of a single set of documents were not arbitrary as the conditions were not essential and the department acted within its discretion (Paras 5-7).

B) Tender Law - Eligibility Criteria - Relaxation - Non-essential conditions can be relaxed by the tendering authority - The condition regarding experience of 32 km line and submission of two tender documents were not essential conditions but technical qualifying requirements - Held that the department's decision to relax these conditions in favour of respondent no. 5 was not arbitrary or mala fide (Paras 5-7).

C) Tender Law - Vested Right - No vested right in tender process - A bidder has no fundamental right to be awarded a contract; only a right to be considered fairly - Held that the petitioner's challenge failed as no arbitrariness or mala fides were established (Para 7).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the acceptance of respondent no. 5's tender by the Vidarbha Irrigation Development Corporation was arbitrary and illegal due to alleged non-compliance with eligibility criteria and tender conditions.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the writ petition, holding that the tender conditions were not statutory and the department's relaxation of non-essential conditions was not arbitrary. The court found no mala fides or arbitrariness in the award of the tender to respondent no. 5.

Law Points

  • Tender conditions are not statutory
  • relaxation of non-essential conditions permissible
  • judicial review limited to arbitrariness and mala fides
  • no vested right in tender process
Subscribe to unlock Law Points Subscribe Now

Case Details

2011 LawText (BOM) (04) 99

Writ Petition No. 3285 of 2010

2011-04-25

D. D. Sinha, A. P. Bhangale

Mr A.S. Mardikar for petitioner, Mr V.G. Palshikar for respondents 1 to 4, Mr D.V. Chauhan for respondent 5

Kailash Constructions, through its authorised signatory and Power of Attorney Atul Rajoria

Vidarbha Irrigation Development Corporation, Nagpur; Chief Engineer (Electrical), Hydro Project, Mumbai; The Superintending Engineer, Vidarbha Hydro Electric and Lift Irrigation Division, Bhandara; The Executive Engineer, Vidarbha Hydro Electric and Lift Irrigation Division, Bhandara; M/s Mavin Switchgears and Control, Aurangabad

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging the acceptance of a tender and issuance of work order by a government corporation.

Remedy Sought

Petitioner sought quashing of the tender acceptance and work order issued to respondent no. 5.

Filing Reason

Petitioner alleged that respondent no. 5's tender did not meet the technical qualifying requirements and that the department improperly relaxed conditions to favour respondent no. 5.

Issues

Whether the acceptance of respondent no. 5's tender was arbitrary and illegal due to non-compliance with clause 1.13.2(a) regarding experience? Whether the department's relaxation of the condition requiring two tender documents in envelope no. 1 was arbitrary? Whether the petitioner has a vested right to challenge the tender award?

Submissions/Arguments

Petitioner argued that respondent no. 5 did not have the required experience of 32 km transmission line and did not submit two tender documents, and the department relaxed conditions arbitrarily. Respondents argued that the conditions were not essential and could be relaxed, and the decision was taken in a fair and transparent manner.

Ratio Decidendi

Tender conditions are not statutory; the tendering authority has discretion to relax non-essential conditions. Judicial review is limited to arbitrariness, mala fides, or bias. A bidder has no vested right to be awarded a contract, only a right to be considered fairly.

Judgment Excerpts

The Technical qualifying requirements of Bidders shall be as below: a) The bidder should have successfully completed the work of supply and installation of 132 KV & above voltage level transmission line having length of not less than 32 Km. In a single order during last three years. Learned counsel for the petitioner has contended that respondent no. 5 did not have experience as required vide clause 1.13.2 (a), nor had submitted two tender documents in envelope no. 1. The action of respondent VIDC in accepting tender and issuing Work Order to respondent no. 5 as well as executing the agreement with respondent no. 5 is arbitrary and cannot be sustained in law.

Procedural History

The petitioner filed a writ petition in the High Court of Bombay at Nagpur challenging the tender award. The court heard the parties and delivered judgment on 25 April 2011.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay at Goa Quashes Chargesheet Against Accused in Immoral Traffic Case Due to Lack of Prima Facie Evidence. Petitioner was arraigned as accused no.8 under Sections 3, 4, 5 of ITP Act and Section 370 IPC without any material connectin...
Related Judgement
High Court Madras High Court Dismisses Writ Petition Seeking Removal of Encroachment on Common Pathway, Holds Dispute Over Patta Land Must Be Resolved by Civil Court. The court found that the pathway was patta land and a civil suit was pending, making the writ ...