High Court Dismisses Municipal Corporation's Challenge to Arbitral Award Under Section 34 of Arbitration Act. Arbitral Tribunal's Finding on Proof of Minutes and Contractor's Liability Upheld Based on Contractual Certificates.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The Arbitration Petition under Section 34 of the Arbitration and Conciliation Act, 1996 was filed by the Municipal Corporation of Greater Mumbai to challenge an arbitral award dated 24 September 2007. The award directed the Corporation to pay Rs.66,51,987.69 along with interest to Hindustan Construction Company Ltd. for work executed under a construction contract for aerated lagoons at Bhandup and Ghatkopar. The contract was awarded in 1996, and the work was completed in 2001. The Corporation issued a taking over certificate on 14 March 2001 and, after the defects liability period ended on 3 March 2002 and rectification of minor defects, defects liability certificates were issued on 16 April 2002. In June/July 2003, new defects were noticed, leading to a meeting on 15 September 2004. The Corporation retained the amount due, alleging the contractor had agreed to rectify defects at its cost. The contractor invoked arbitration. The arbitral tribunal found that the taking over and defects liability certificates conclusively established satisfactory performance, and the subsequent alleged defects arose long after the liability period. The tribunal allowed the contractor's claim for the balance and dismissed the Corporation's counterclaim. In the Section 34 petition, the Corporation argued that the tribunal erroneously relied on an unproved report of Dr. Katti and wrongly rejected the minutes of the 15 September 2004 meeting as not proved, violating natural justice. The High Court analysed the tribunal's reasoning and held that the foundation of the award was the contractual certificates, not Dr. Katti's report. As for the minutes, the Corporation failed to produce the original or any justification for secondary evidence; the witness admitted non-production and undertook to trace the original but did not. The tribunal's finding that the minutes were not proved was justified. The court also recalled the principle in Bareilly Electricity Supply Co. Ltd. v. The Workmen that while an arbitral tribunal is not bound by strict rules of evidence, it must observe principles of natural justice and cannot act on what is not evidence. Finding no perversity, illegality, or violation of natural justice, the court dismissed the petition and upheld the arbitral award.

Headnote

A) Arbitration - Challenge to Award - Scope of Interference Under Section 34 - Arbitration and Conciliation Act, 1996, Section 34 - The court held that the arbitral tribunal's findings on facts and evidence are not to be reappreciated unless the award is perverse, arbitrary, or illegal. The tribunal's conclusion that the contractor had performed the work satisfactorily based on the taking over and defects liability certificates issued by the employer was a plausible view and not open to interference (Paras 8-9).

B) Evidence - Proof of Documents - Secondary Evidence - Indian Evidence Act, 1872 - The arbitral tribunal found that the employer failed to prove the minutes of the meeting dated 15 September 2004 as the original signed minutes were not produced, and no justification for leading secondary evidence was given. The court upheld this finding, noting that the witness admitted non-production and failed to trace the original (Paras 8, 10).

C) Natural Justice - Reliance on Unproved Documents - Principles of Natural Justice - Arbitration and Conciliation Act, 1996, Section 18 - Relying on Bareilly Electricity Supply Co. Ltd. v. The Workmen, the court held that an arbitral tribunal must observe principles of natural justice, and cannot act on what is not evidence. However, the petitioner's contention that the tribunal relied on an unproved report (Dr. Katti's report) was rejected because the award was based on contractual certificates, not that report (Paras 9).

D) Contract Law - Construction Contracts - Defects Liability Period and Certificates - Conditions of Contract, Clauses 49.2, 62.1 - The taking over certificate and defects liability certificates issued by the employer evidenced that the contractor had completed the work in accordance with the contract and rectified all defects. The tribunal rightly held that the contractor could not be held liable for defects noticed after the expiry of the defects liability period and after unconditional certificates were issued (Paras 4, 8).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award suffered from perversity or illegality in its appreciation of evidence, particularly regarding the proof of the minutes of meeting dated 15 September 2004 and the report of Dr. Katti, warranting interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court found no merit in the challenge and dismissed the arbitration petition. The arbitral award was upheld. The court held that the tribunal was justified in finding the minutes not proved and that the award was based on proper evidence.

Law Points

  • Arbitration and Conciliation Act
  • 1996
  • Section 34
  • Scope of interference with arbitral award
  • Arbitral tribunal's appreciation of evidence
  • Principles of natural justice
  • Secondary evidence
  • Proof of documents
  • Contractual obligations under taking over certificate and defects liability certificate
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (12) 53

Arbitration Petition No. 65 of 2008

2010-12-03

Dr. D.Y. Chandrachud, J.

2010:BHC-OS:14207

Mr. R.D. Dhanuka with Mr. H.C. Pimple and Mr. R.Y. Sirsekar i/b. S.H. Ujjainwala & Co. for Petitioner; Mr. Aspi Chinoy, Sr. Advocate with Mr. Kevic Setalwad i/b. M/s. Harish Joshi & Co. for Respondent

Municipal Corporation of Greater Mumbai

Hindustan Construction Company Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award in a construction contract dispute.

Remedy Sought

Petitioner (Municipal Corporation of Greater Mumbai) sought setting aside of the arbitral award dated 24 September 2007 which directed payment of Rs.66,51,987.69 with interest to the Respondent (contractor).

Filing Reason

The petitioner retained the amount due on the ground of defective work, and alleged that the respondent had agreed to rectify defects at a meeting on 15 September 2004.

Previous Decisions

The arbitral tribunal had allowed the respondent's claim and dismissed the petitioner's counter claim.

Issues

Whether the minutes of the meeting dated 15 September 2004 were duly proved and whether the arbitral tribunal erred in rejecting them. Whether the arbitral tribunal's reliance on the report of Dr. Katti was improper and violated principles of natural justice. Whether the arbitral award was liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996 on grounds of perversity or illegality in appreciation of evidence.

Submissions/Arguments

Petitioner: Arbitral tribunal relied on unproved Dr. Katti report and wrongly rejected minutes of 15 September 2004 meeting despite oral proof, violating natural justice. Respondent: Minutes not proved as original not produced; award based on contractual certificates; no reliance on Dr. Katti report; no perversity.

Ratio Decidendi

The arbitral tribunal's appreciation of evidence is not to be interfered with under Section 34 unless the finding is perverse, arbitrary, or illegal. A document not proved in accordance with law (non-production of original, lack of justification for secondary evidence) cannot be relied upon, and a finding rejecting such document does not suffer from perversity. In construction contracts, issuance of taking over certificates and defects liability certificates conclusively indicates satisfactory completion of work and rectification of defects, and bars any subsequent claim for defects noted after the liability period.

Judgment Excerpts

The basis of the award of the arbitral Tribunal is that the Petitioner had duly certified that the work which was executed by the Respondent was in accordance with the specifications of the contract. The Tribunal was entirely justified in coming to the conclusion that the alleged minutes upon which reliance has been placed by the Petitioner were not duly proved. It is no doubt well settled that an arbitral Tribunal is not bound by the strict rules of evidence which govern civil trial. But, equally ever since the judgment of the Supreme Court in Bareilly Electricity Supply Co.Ltd. Vs. The Workmen, it is well settled that the principles of natural justice must be observed even if an adjudicating body is not governed by the strict rules of evidence or procedure.

Procedural History

In April 1995, Petitioner invited tenders for civil work of aerated lagoons. On 5 January 1996, contract awarded to Respondent; formal agreement on 30 April 1996. Work completed and taking over certificate issued on 14 March 2001. Defects liability period from 4 March 2001 to 3 March 2002. On 14 March 2002, general inspection conducted, minor defects noted. On 16 April 2002, defects liability certificates issued. In June/July 2003, new defects noted. On 15 September 2004, meeting held between parties. Petitioner retained Rs.66,51,987.69 due. Arbitration invoked and three-member Tribunal constituted. Award passed on 24 September 2007 allowing Respondent's claim and dismissing counterclaim. Petitioner filed Arbitration Petition No.65 of 2008 under Section 34 of Arbitration and Conciliation Act, 1996 before Bombay High Court.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Upholds Assessee in Tax Refund Interest Dispute: Interest under Section 244A Payable from Date of Tax Payment, Not Central Government Account Credit. Court Clarifies that Payment by Cheque to Authorized Agent Constitutes Payment upo...
Related Judgement
High Court High Court Dismisses Municipal Corporation's Challenge to Arbitral Award Under Section 34 of Arbitration Act. Arbitral Tribunal's Finding on Proof of Minutes and Contractor's Liability Upheld Based on Contractual Certificates.