Bombay High Court Allows Appointment of Arbitrator in Construction Dispute Due to Respondent's Failure to Appoint Arbitrator. Failure to Respond to Notice Invoking Arbitration Constitutes Refusal to Appoint Under Section 11(6) of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Prosecution
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s. Khurana Constructions, entered into an agreement with the respondent, IOT Infrastructure and Energy Services Ltd., on 28 February 2005 for civil and underground piping work related to the MSQ project of the Gujarat Refinery. The agreement contained an arbitration clause (Clause 83) which provided that disputes would be referred to the sole arbitration of the Managing Director of IOT or an arbitrator appointed by the Managing Director. Disputes arose, and on 1 September 2008, the petitioner sent a notice to the respondent raising a claim of Rs.10.91 Crores. The respondent sent a preliminary reply on 1 October 2008 refuting the claims but stating that a detailed reply would follow. No further response was received. On 12 November 2008, the petitioner sent another notice stating that the 90-day negotiation period under Clause 83 would commence from that date and called upon the respondent to fix a meeting for amicable resolution. The respondent did not respond. The petitioner then filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator. The court noted that the respondent had failed to respond to the notice and had not appointed an arbitrator. The court held that the failure to respond and appoint an arbitrator amounted to a refusal to appoint, and therefore, the court was empowered to appoint an arbitrator. The court appointed a retired judge of the Bombay High Court as the sole arbitrator to adjudicate the disputes between the parties.

Headnote

A) Arbitration Law - Appointment of Arbitrator - Section 11(6) of the Arbitration and Conciliation Act, 1996 - Failure to Appoint - Where the arbitration agreement provides for appointment of arbitrator by the Managing Director of the respondent, and the respondent fails to respond to the petitioner's notice invoking arbitration and does not appoint an arbitrator within the stipulated period, the petitioner is entitled to approach the court for appointment of an arbitrator under Section 11(6) of the Act. The court held that the failure to respond and appoint constitutes a refusal to appoint, and the court can appoint an independent arbitrator. (Paras 1-5)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the failure of the respondent to respond to the petitioner's notice invoking arbitration and to appoint an arbitrator under the arbitration agreement entitles the petitioner to seek appointment of an arbitrator by the court under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the petition and appointed a retired judge of the Bombay High Court as the sole arbitrator to adjudicate the disputes between the parties.

Law Points

  • Arbitration agreement
  • appointment of arbitrator
  • failure to appoint
  • deemed refusal
  • Section 11(6) of Arbitration and Conciliation Act
  • 1996
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (08) 57

Arbitration Petition No.35 of 2009

2010-08-13

Dr. D.Y. Chandrachud, J.

Ms. Lopa Munim with Mr. H.K. Bhalerao i/b M/s. Rajesh Kothari and Co. for the Petitioner, Mr. S.B. Shetty for Respondent No.1

M/s. Khurana Constructions

IOT Infrastructure and Energy Services Ltd. and another

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 11(6) of the Arbitration and Conciliation Act, 1996 for appointment of an arbitrator.

Remedy Sought

Petitioner sought appointment of an arbitrator by the court due to respondent's failure to appoint an arbitrator under the arbitration agreement.

Filing Reason

Respondent failed to respond to petitioner's notice invoking arbitration and did not appoint an arbitrator as per Clause 83 of the agreement.

Issues

Whether the failure of the respondent to respond to the notice and appoint an arbitrator entitles the petitioner to seek appointment under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Petitioner argued that despite notice, respondent did not appoint an arbitrator, thus court should appoint one. Respondent's submissions not recorded in the judgment.

Ratio Decidendi

Where an arbitration agreement provides for appointment of an arbitrator by a party, and that party fails to respond to a notice invoking arbitration and does not appoint an arbitrator, such failure constitutes a refusal to appoint, entitling the other party to seek appointment by the court under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Judgment Excerpts

In pursuance of a bid submitted by the Petitioner for carrying out civil and U/G piping work related to the MSQ project of the Gujarat Refinery of the Respondents a letter of intent was issued to the Petitioner on 9 October 2004. Since there was no response from the Respondent, the Petitioner by a letter dated 12 November 2008 recorded that there was no response thereafter to the claims and contentions raised on 1 September 2008. The failure on the part of the Respondent to respond to the notice and to appoint an arbitrator would constitute a refusal to appoint an arbitrator.

Procedural History

Petitioner sent notice on 1 September 2008 raising claims. Respondent replied on 1 October 2008 stating detailed reply would follow. No further response. Petitioner sent another notice on 12 November 2008 calling for negotiations. No response. Petitioner filed Arbitration Petition No.35 of 2009 under Section 11(6) of the Arbitration and Conciliation Act, 1996.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11(6)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appointment of Arbitrator in Construction Dispute Due to Respondent's Failure to Appoint Arbitrator. Failure to Respond to Notice Invoking Arbitration Constitutes Refusal to Appoint Under Section 11(6) of Arbitration and Conc...
Related Judgement
High Court Bombay High Court Dismisses Petition Challenging Divorce Decrees by Mutual Consent Under Parsi Marriage Act. Presiding Judge of Parsi Chief Matrimonial Court Can Pass Decree Without Delegates' Assistance Under Section 32B of Parsi Marriage and Divorc...