Case Note & Summary
The dispute arose from a contract for widening and strengthening of a road in West Bengal, awarded to Pam Developments Private Limited (the appellant) by the State of West Bengal (the respondent). The work was completed with a delay of about five months. The appellant raised claims for additional costs due to alleged delays by the respondent. The Arbitrator awarded Rs. 1,37,25,252 with interest, including claims for loss of business (claim 1), uneconomic utilization of plant and machinery (claim 2), labour charges for uneconomical stoppage of work (claim 3), interest on delayed payment of running account bills (claim 4), escalation (claim 5), interest (claim 6), and costs (claim 7). The respondent challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The District Judge set aside claims 1 and 2 but upheld the rest. Both parties appealed under Section 37. The Calcutta High Court set aside claims 1, 3, and 4, restored claim 2, and modified claim 6 to exclude pre-reference interest. The appellant appealed to the Supreme Court, confining submissions to claims 3, 4, and 6. The Supreme Court held that the High Court correctly set aside claim 3 because the contract's Special Terms and Conditions expressly prohibited claims for idle labour, additional establishment, etc. The Arbitrator had ignored these clauses, and the District Court's standard reasoning was insufficient. Regarding claim 4, the Supreme Court found that the contract did not prohibit interest on delayed payments, and the Arbitrator's award of interest on blocked capital was justified. The High Court erred in setting it aside. For claim 6, the Supreme Court restored the Arbitrator's award of interest from the date of invocation of arbitration (12.04.2016) to the date of award at 12% p.a. and post-award interest at 9.25% p.a., as the High Court's modification to exclude pre-reference interest was not warranted. The appeal was partly allowed, restoring claims 4 and 6 as per the Arbitral Award.
Headnote
A) Arbitration Law - Section 37 Appeal - Scope of Interference - Contract Interpretation - The High Court, while exercising appellate jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996, is entitled to examine the contractual provisions and set aside an award that is contrary to the express terms of the contract. The Arbitrator's failure to consider the 'Special Terms and Conditions' prohibiting claims for idle labour, additional establishment, etc., renders the award liable to be set aside. (Paras 7.3-7.5) B) Arbitration Law - Section 34 - Public Policy - Standard Reasoning - A District Court's dismissal of objections under Section 34 using a standard phrase that the award is not 'irrational, insensible or unrealistic' without examining the contractual provisions is insufficient. The court must independently assess whether the award conflicts with the terms of the contract. (Para 7.2) C) Contract Law - Interest on Delayed Payment - Blocked Capital - Claim for interest on delayed payment of running account bills is permissible where the contract does not prohibit such interest. The Arbitrator's award of interest at 12% p.a. on blocked capital was upheld by the Supreme Court, as the High Court erred in setting it aside without considering that the contract did not bar interest on delayed payments. (Paras 8.1-8.5) D) Arbitration Law - Interest - Pre-reference Period - The Arbitrator's award of interest for the pre-reference period is within his discretion, and the High Court's modification to exclude pre-reference interest was not justified. The Supreme Court restored the Arbitrator's award of interest from 12.04.2016 (the date of invocation of arbitration) to the date of award at 12% p.a. and post-award interest at 9.25% p.a. (Paras 9.1-9.3)
Issue of Consideration
Whether the High Court under Section 37 of the Arbitration and Conciliation Act, 1996, was justified in setting aside the Arbitral Award on claims 3 (labour charges for uneconomical stoppage of work) and 4 (interest on delayed payment of running account bills) and modifying claim 6 (interest) while restoring claim 2 (uneconomic utilization of plant and machinery).
Final Decision
The Supreme Court partly allowed the appeal. It upheld the High Court's decision setting aside claim 3 (labour charges for uneconomical stoppage of work). It set aside the High Court's decision on claim 4 (interest on delayed payment of running account bills) and restored the Arbitral Award on that claim. It also set aside the High Court's modification of claim 6 (interest) and restored the Arbitrator's award of interest from 12.04.2016 to the date of award at 12% p.a. and post-award interest at 9.25% p.a.
Law Points
- Arbitration award
- Section 34 of Arbitration and Conciliation Act
- 1996
- Section 37 of Arbitration and Conciliation Act
- Hudson's formula
- contract interpretation
- public policy
- interest on delayed payment
- blocked capital
- idle labour claim
- special terms and conditions




