Bombay High Court Dismisses Suit for Specific Performance of Property Sale Agreement Due to Plaintiffs' Default and Unauthorized Payments. Plaintiffs Failed to Pay Balance Consideration Within Stipulated 10-Month Period and Dealt with Sole Director Contrary to Board Resolution Requiring Joint Action.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 9
Judgement Image
Font size:
Print

Case Note & Summary

The suit was filed by the plaintiffs, Pankaj Anantrai Bhuwa & others, against the defendant, M/s. Ramkumar Shivchandray & Sons, seeking specific performance of an agreement for sale dated 23.04.1981, a declaration that the agreement was valid, and a direction to convey the suit property at Prabhadevi Road, Mumbai. The defendant company owned the property, and the plaintiffs were tenants of a large portion. Under the agreement, the defendant agreed to sell the property for Rs.20 lakhs, with Rs.50,000 paid as earnest. The balance was to be paid on completion within 10 months. The sale was on 'as is where is' basis, subject to tenancies. The defendant was to obtain an income-tax clearance certificate under Section 230A and permission under Section 27 of the Urban Land Ceiling Act, though the land was fully built. The agreement also provided that the defendant's board had resolved that two directors, Deviprasad Poddar and Bhagwatiprasad Poddar, would jointly settle documents and execute the conveyance. The plaintiffs did not pay the balance consideration within the 10-month period expiring on 23.02.1982. Instead, they dealt with one director, Deviprasad Poddar, and claimed to have made two additional payments of Rs.50,000 each to him and that time was extended to 15.04.1982. The defendant terminated the contract on 24.02.1982, forfeiting the earnest, arguing that the resolution required joint action and that no valid payment was made. The termination was without the 15 days' notice required by the agreement to make time essential. The court examined whether the plaintiffs were ready and willing to perform, whether the defendant validly terminated, and whether specific performance should be granted. It held that the plaintiffs' failure to pay the balance consideration and their dealings with a single director, contrary to the board resolution, showed they were not ready and willing. The company's resolution was known to them, and the directors had to act jointly. Therefore, the extension claimed was not binding. The defendant's termination was procedurally defective for not providing the required notice, but the plaintiffs' own default precluded them from obtaining equitable relief. The court also noted that the ULCRA permission was not necessary, and the Section 230A certificate was not a precondition to sale. Ultimately, the suit was dismissed.

Headnote

A) Contract Law - Specific Performance - Readiness and Willingness - Specific Relief Act, 1963 - Plaintiffs failed to pay balance consideration of Rs.19.50 lakhs within the agreed 10-month period ending 23.02.1982, and payments made to a single director were not binding due to a board resolution requiring joint action; thus, plaintiffs were not ready and willing to perform - Held, not entitled to specific performance (Paras 10-17).

B) Company Law - Authority of Directors - Board Resolution - Where a board resolution authorizes two directors to act jointly for settling and executing documents, any dealings with a single director are not binding on the company; plaintiffs' payments to one director and reliance on his extension of time were therefore invalid (Paras 14-16).

C) Contract Law - Termination of Contract - Notice Requirement - Clause 18(b) of the agreement required the defendant to make time the essence by giving 15 days' notice before termination; defendant's termination without such notice was invalid, but plaintiffs' own default prevented equitable relief (Paras 11, 18-19).

D) Urban Land Ceiling (Regulation) Act, 1976 - Section 27 - Permission for Transfer - Since the suit land was fully built-up with no vacant land, Section 27 permission was not required and was struck down as ultra vires; defendant's failure to obtain it was not a breach (Paras 5-6, 17).

E) Income Tax Act, 1961 - Section 230A - Certificate - The agreement provided that sale would proceed even without the certificate, with a security deposit; thus, non-production of the certificate did not excuse plaintiffs from completing the sale (Paras 3, 5, 17).

F) Evidence - Estoppel - Tenants - Section 116 Indian Evidence Act, 1872 - Plaintiffs, being tenants of the defendant, were estopped from questioning the defendant's title to the suit property (Para 6).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the plaintiffs were entitled to specific performance of the agreement for sale; whether the defendant validly terminated the agreement; whether the plaintiffs were ready and willing to perform their part of the contract; whether payment to one director was valid given the board resolution requiring joint action; whether the defendant breached the agreement by not obtaining necessary permissions.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The suit for specific performance is dismissed. The plaintiffs are not entitled to any relief.

Law Points

  • specific performance requires readiness and willingness
  • company board resolution mandating joint action of directors must be respected
  • payment to single director not binding
  • termination of contract invalid if not preceded by notice making time essence
  • estoppel under Section 116 Indian Evidence Act
  • Section 230A Income Tax Act certificate not a precondition
  • Section 27 Urban Land Ceiling Act permission not required for built-up land
Subscribe to unlock Law Points Subscribe Now

Case Details

2010 LawText (BOM) (05) 40

Suit No.391 of 1982

2010-05-07

SMT.ROSHAN DALVI, J.

Mr.D.S. Parikh, Senior Advocate with Mr.R.M. Tiwari for Plaintiffs; Mr.Uday Bobade with Mr.Pankaj Kawli i/by M/s.Dadhich & Co. for Defendant

Pankaj Anantrai Bhuwa & ors.

M/s.Ramkumar Shivchandray & sons

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Suit for specific performance of an agreement for sale of immovable property, declaration that the agreement is valid and subsisting, and order to convey and hand over possession.

Remedy Sought

Plaintiffs sought specific performance, declaration, and conveyance of suit property to nominated plaintiff.

Filing Reason

Defendant terminated the agreement for sale after the plaintiffs allegedly failed to complete the sale within the stipulated period, and plaintiffs alleged breach by defendant.

Issues

Whether the plaintiffs were entitled to specific performance of the agreement for sale? Whether the defendant validly terminated the agreement? Whether the plaintiffs were ready and willing to perform their part of the contract? Whether payment to one director was valid given the board resolution requiring joint action? Whether the defendant breached the agreement by not obtaining necessary permissions?

Submissions/Arguments

Plaintiffs contended that they had paid part consideration to one of the defendant's directors and that time for completion was mutually extended until 15.04.1982. Defendant argued that the board resolution required two directors to act jointly and that payment to a single director was not binding on the company; thus, plaintiffs were in default and the agreement was validly terminated.

Ratio Decidendi

The plaintiffs were not ready and willing to perform their part of the contract as they failed to pay the balance consideration within the stipulated time and dealt with a single director contrary to the board resolution requiring joint action. Consequently, they are not entitled to specific performance. Although the defendant's termination was procedurally defective for not making time the essence, the plaintiffs' own default bars equitable relief.

Judgment Excerpts

The Plaintiffs did not make payment of the balance consideration and complete the sale within 10-month time specifically prescribed. The Defendant did not fully comply with the terms under the said Agreement relating to the termination of the Agreement by it as contained in Clause 18(b) of the said Agreement. The Defendant did not make time the essence of the contract. The Defendant did not give 15 days notice to complete the transaction. Nevertheless the Plaintiffs dealt with one of the Directors of the Defendant, Deviprasad Poddar. ... The resolution of the Company was made known to the Plaintiffs. The Plaintiffs had to abide by that resolution which was recited in the said Agreement itself.

Procedural History

The suit was filed in 1982. The judgment was reserved on 01.04.2010 and pronounced on 07.05.2010. No prior proceedings mentioned.

Acts & Sections

  • Indian Evidence Act, 1872: Section 116
  • Income-tax Act, 1961: Section 230A
  • Urban Land Ceiling (and Regulations) Act, 1976: Section 27
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Suit for Specific Performance of Property Sale Agreement Due to Plaintiffs' Default and Unauthorized Payments. Plaintiffs Failed to Pay Balance Consideration Within Stipulated 10-Month Period and Dealt with Sole Director C...
Related Judgement
Supreme Court Supreme Court Allows Employer's Appeal Against Reinstatement Order in Industrial Dispute. Section 25(H) of Industrial Disputes Act Held Inapplicable Where Workman Accepted Compensation and Employer Only Regularized Existing Employees.