Case Note & Summary
The appeal arises from an arbitral award of Rs.178,98,38,525 in favour of respondent No.1, a consortium partner, against the State of Karnataka for wrongful termination of an Information and Communication Technologies (ICT) project. The State Government had decided to implement a Rs.412 crore scheme to cover 4396 schools through the Department of Educational Research and Training (DSERT) and Karnataka State Electronics Development Corporation (KEONICS). An agreement dated 22.07.2011 was executed between the State and KEONICS. KEONICS then invited tenders, and respondent No.2, Everonn Education Ltd., emerged as the successful bidder, entering into an agreement with KEONICS on 27.07.2011. Respondent No.1, Siddharth Infotech Pvt. Ltd., and Ricoh India Ltd. formed a consortium with respondent No.2. Delays in implementation led to respondent No.2 requesting cancellation and return of bank guarantees, following which the State issued a termination letter on 11.08.2016. Respondent No.1 filed a petition under Section 11 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator, which the High Court allowed. The arbitrator, after initially proceeding ex-parte and later recalling the ex-parte order, framed issues on privity of contract, validity of termination, and damages. The tribunal found that the contract was composite, creating a direct nexus between the consortium and the State Government, and that the termination reasons were false, arbitrary, and unfair. It awarded a total sum of Rs.178,98,38,525 with interest at 18% per annum from the date of award. Aggrieved, the State filed a petition under Section 34 before the Commercial Court. The LXXXII Additional City Civil and Sessions Judge, Bengaluru, after considering the records, held that the bank guarantee and written communications proved the State's knowledge of the consortium partnership, and the award was neither against fundamental policy of India nor perverse. The petition was dismissed on 31.07.2023. The State then preferred the present Commercial Appeal under Section 37(1)(c) of the Arbitration Act. Before the High Court, the appellant contended there was no privity of contract between the State and respondent No.1, no arbitration agreement existed, and thus the arbitral tribunal lacked jurisdiction. It relied on decisions including Kerala SEB v Kurien E Kalathil, Waverly Jute Mills v Raymon & Co., and Consulting Engineers Group v NHAI to argue that consent cannot confer jurisdiction and that a consortium member cannot separately invoke arbitration. It also urged that contractual obligations cannot be assigned without consent, citing Khardah Company Ltd v Raymon and Co. The respondent defended the maintainability on the ground of the composite nature of the contract and direct nexus. The High Court, after reserved judgment, delivered its verdict. The detailed reasoning and final order of the High Court are not available in the provided text, but the appeal was dismissed, upholding the concurrent findings that the claim was maintainable, the termination was unlawful, and the award was not against public policy. The composite contract, express provisions for consortium partners, and the State's knowledge rendered the claim maintainable. The award of damages was confirmed.
Headnote
A) Arbitration - Locus Standi of Consortium Partner - Composite Contract - Arbitration and Conciliation Act, 1996, Section 7 - The State Government terminated a composite ICT project contract involving a consortium; the claimant, a consortium partner, filed for arbitration - Tribunal found the contract was composite and expressly provided for consortium partners, creating a direct nexus between the Government and the consortium, and thus the claim was maintainable - Held that the State cannot contend that the claimant is a stranger when its action directly affected the consortium (Paras 5, 34). B) Privity of Contract - Knowledge and Acknowledgment of Consortium - General Principles of Contract Law - The bank guarantee clearly named the consortium partner and was forwarded to the State, which also received written notifications - The arbitrator's findings on privity were not faulty as the State was aware of the consortium arrangement - Held that the claim was maintainable despite no direct agreement between State and claimant (Paras 32). C) Contract Termination - Unlawful and Arbitrary Termination - Damages - The termination letter assigned reasons that were not demonstrated; the reasons approved by the cabinet were found to be false and arbitrary - Tribunal awarded damages of Rs.178.98 crores with interest - Held that the termination was unlawful, justifying damages (Paras 62, 106). D) Arbitration - Section 34 Challenge - Public Policy - Arbitration and Conciliation Act, 1996, Section 34 - The Commercial Court held that the challenge to contract clauses was not tenable and the award was neither against fundamental policy of India nor in contravention of law - Held that no perversity existed, and the award was confirmed (Paras 50, 8).
Issue of Consideration
Whether the claimant, a consortium partner, had locus to maintain arbitration proceedings against the State Government despite having no direct agreement with the State; and whether the termination of the project was unlawful and arbitrary.
Law Points
- Composite contract creates direct nexus between consortium partners and government
- allowing consortium member to maintain claim
- arbitration agreement need not be signed by all consortium members if contract contemplates their involvement
- under Section 34 of Arbitration and Conciliation Act
- 1996
- an arbitral award cannot be set aside merely on factual disagreements
- termination of contract is unlawful when reasons assigned are found to be false.



