Case Note & Summary
The appellant, Sri M. Rajappa, filed a writ appeal before the High Court of Karnataka at Bengaluru challenging an order dated 16.12.2024 passed by a learned Single Judge in W.P.No.6371/2021. The appellant had originally filed the writ petition seeking a declaration that the acquisition of his land measuring 6 guntas in Survey No.15/1B at Kodihalli Village, Bengaluru, under a notification dated 15.07.1971 issued under Section 18(1) of the City of Bangalore Improvement Act, 1945, had lapsed or been abandoned. He also sought a direction restraining the respondents from interfering with his possession. The Single Judge dismissed the writ petition, leading to the present appeal. The facts reveal that the notification was issued in 1971 for the formation of a layout. The appellant claimed that the acquisition had lapsed as the scheme was not completed within a reasonable time and that the authorities had abandoned the acquisition. The respondents, the State of Karnataka and the Bangalore Development Authority, contended that possession of the subject land had been taken and an award had been passed, and therefore the acquisition was complete. The legal issues before the court were whether the acquisition had lapsed under Section 27 of the Bangalore Development Authority Act, 1976, or had been abandoned. The appellant argued that the long delay of over 50 years without completing the scheme indicated abandonment. The respondents argued that possession was taken and the acquisition was valid. The court, in its analysis, noted that the acquisition was under the City of Bangalore Improvement Act, 1945, and that the BDA Act of 1976 had repealed the earlier Act. However, Section 27 of the BDA Act provides that if possession of the acquired land is not taken within five years from the date of the award, the acquisition lapses. In this case, the court found that possession of the subject land had been taken and an award had been passed. Therefore, the acquisition did not lapse. The court also rejected the argument of abandonment, stating that the acquisition was for a public purpose and the scheme was still in progress. The court held that there was no evidence of abandonment. Consequently, the appeal was dismissed, and the order of the Single Judge was upheld. The decision primarily favors the respondents (the State and the BDA).
Headnote
A) Land Acquisition - Lapse of Acquisition - Section 27 of Bangalore Development Authority Act, 1976 - The appellant sought declaration that acquisition of land under Section 18(1) of the City of Bangalore Improvement Act, 1945 had lapsed due to non-completion of the scheme. The Court held that since possession of the subject land was taken and an award was passed, the acquisition did not lapse. The provisions of Section 27 of the BDA Act, which deal with lapse of acquisition if possession is not taken within five years, were not applicable as possession had already been taken. (Paras 1-6) B) Land Acquisition - Abandonment of Acquisition - The appellant argued that the acquisition was abandoned due to inaction for over 50 years. The Court rejected this contention, noting that the acquisition was for a public purpose and the scheme was still in progress. The Court found no evidence of abandonment and held that the acquisition remained valid. (Paras 5-6) C) Writ Jurisdiction - Delay and Laches - The appellant challenged a 1971 notification in 2021. The Court observed that the challenge was highly belated and the appellant had not explained the delay. However, the Court did not base its decision solely on delay but also on merits. (Para 1)
Issue of Consideration
Whether the acquisition of the subject land under the City of Bangalore Improvement Act, 1945 had lapsed or been abandoned due to non-completion of the improvement scheme within a reasonable time.
Final Decision
The appeal is dismissed. The order dated 16.12.2024 passed by the learned Single Judge in W.P.No.6371/2021 is upheld.
Law Points
- Land acquisition lapse
- abandonment of acquisition
- Section 27 Bangalore Development Authority Act
- 1976
- Section 18 City of Bangalore Improvement Act
- 1945
- possession taken
- award passed
- scheme not completed



