Case Note & Summary
The High Court of Judicature at Bombay heard a writ petition filed by a private limited company engaged in road construction, challenging an order dated 5 December 2013 passed by the Standing Empowered Committee. The dispute arose out of a road construction contract awarded pursuant to a notice inviting tender dated 2 January 2008 for upgradation/construction of MDR-42 to Tekpol Road in Taluka Velhe, District Pune. The contract was awarded on 23 June 2008 with an initial completion period of eighteen months, which was extended three times up to 30 April 2012. The petitioner cited remote site conditions, heavy rainfall, farmer protests, and forest department objections as reasons for delay, claiming completion of almost 90% of the work. The respondents, however, contended that the petitioner consistently failed to complete work within stipulated periods despite extensions and assurances. Liquidated damages at 1% of contract value per week (Rs.16,65,000) were imposed from 1 May 2012 pursuant to tender condition Nos.21(a) and 21(b). The respondents terminated the contract by letter dated 17 December 2012 under clause 52, after recovering Rs.35.98 lakhs from the 14th running bill as liquidated damages and miscellaneous deposit. The petitioner sought revocation of termination and approached the Standing Empowered Committee, which by its order dated 5 December 2013 cancelled the termination but imposed a penalty of 10% of the contractual amount, denied price escalation or difference in cost, and directed that quality of post-termination work be verified before final payment. The petitioner then filed the present writ petition seeking quashing of that order and constitution of a fresh Standing Empowered Committee. At the outset, the court noted two preliminary defects: the petition did not mention under what provision of law it was filed, neither under Article 226 nor 227 of the Constitution, and the Standing Empowered Committee whose order was challenged was not impleaded as a party. The court observed that on these two counts alone the petition was liable to be dismissed, but since counsel were heard, it proceeded to examine the merits based on materials on record. Petitioner's counsel argued that under clause 21(b) of the General Conditions of Contract, liquidated damages could be imposed only at 1% of the initial contract price, making the 10% penalty unjust and unfair. He highlighted various obstacles beyond the petitioner's control and contended that the contract was illegally terminated. He further submitted that as per clause 24.2, the Standing Empowered Committee is an appellate forum, and by deciding the dispute at the first instance, the petitioner was deprived of one forum of grievance redressal, rendering the impugned order arbitrary, unreasonable, and without jurisdiction. The learned Assistant Government Pleader relied on the affidavit-in-reply filed by respondents and supported the impugned action as just, reasonable, and proper, emphasizing the petitioner's repeated failures to complete work and compliance with tender conditions and clause 52. The judgment excerpt provided ends during the respondent's arguments, and the final operative decision is not available in the text. Therefore, the final outcome of the writ petition, including whether it was dismissed or allowed, cannot be determined from the available excerpt; however, the court had already indicated that the petition was liable to dismissal on preliminary grounds before proceeding to merits.
Headnote
A) Constitutional Law - Writ Petition Pleadings - Non-Mention of Provision - Constitution of India, 1950, Articles 226 and 227 - The petitioner did not state under which provision the writ petition was filed; the court noted this defect as a ground for dismissal but proceeded to hear merits because parties were heard - Held that petition is liable to be dismissed on this count (Para 4). B) Civil Procedure - Necessary Party - Non-Joinder of Authority - Constitution of India, 1950, Articles 226 and 227 - The Standing Empowered Committee whose order was challenged was not arrayed as respondent; the court held this rendered petition liable to dismissal but decided to examine materials on record - Held that non-joinder of necessary party is fatal (Para 4). C) Contract Law - Liquidated Damages - Limitation Under Tender Clause - General Conditions of Contract, Clause 21(b) - Petitioner contended that maximum liquidated damages under clause 21(b) is 1% of initial contract price; imposition of 10% penalty was therefore unjust and without jurisdiction; court noted this submission but final holding not available in excerpt (Paras 23). D) Contract Law - Appellate Forum - Standing Empowered Committee as Appellate Authority - General Conditions of Contract, Clauses 24 and 24.2 - Petitioner argued that Standing Empowered Committee is appellate forum under clause 24.2, but it decided dispute at first instance, depriving petitioner of appellate remedy; this rendered order arbitrary and without jurisdiction; court's final view not available in provided text (Paras 23-24).
Issue of Consideration
Whether writ petition is maintainable absent specification of Articles 226/227 and absent impleadment of Standing Empowered Committee; whether Standing Empowered Committee had jurisdiction to act as first forum instead of appellate forum; whether imposition of 10% penalty and denial of price escalation is valid; whether termination of contract was illegal
Final Decision
Not mentioned in the provided text; the court observed preliminary defects but final operative order not included in excerpt.
Law Points
- Constitutional requirement to plead specific provision under Articles 226 or 227
- necessary party must be impleaded
- non-mention and non-joinder are grounds for dismissal
- Standing Empowered Committee is appellate forum under clause 24.2
- liquidated damages under clause 21(b) limited to 1% of initial contract price
- penalty of 10% challenged as unjust
- contract termination requires compliance with clause 52



