Bombay High Court Dismisses Writ Petition Against MSME Facilitation Council Award on Maintainability Grounds. Council Has Jurisdiction Over Disputes Arising Before 2006 Act Came Into Effect.

High Court: Bombay High Court Bench: AURANGABAD
  • 5
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Bajaj Auto Limited, challenged an award of the Micro and Small Enterprises Facilitation Council (respondent no. 4) in a writ petition before the Bombay High Court. The dispute involved outstanding payment for parts supplied by respondent no. 3, M/s S. M. Solar Products Ltd., to the petitioner. The court framed two issues: maintainability of the writ petition and the Council's jurisdiction over disputes arising before the Micro, Small and Medium Enterprises Development Act, 2006 came into effect. The court held that the writ petition was not maintainable because the Act provides a statutory remedy of appeal under Section 19, which is an efficacious alternative remedy. On the second issue, the court held that the Council has jurisdiction to decide disputes even if they arose prior to the enactment, as the Act applies to all pending disputes. The petition was dismissed with no order as to costs.

Headnote

A) Writ Jurisdiction - Maintainability - Alternative Remedy - Micro, Small and Medium Enterprises Development Act, 2006, Section 19 - Challenge to award of Facilitation Council - Held that writ petition is not maintainable as the Act provides for a statutory remedy of appeal under Section 19, which is an efficacious alternative remedy (Paras 2, 5-7).

B) Jurisdiction - Retrospective Application - Micro, Small and Medium Enterprises Development Act, 2006, Section 18 - Dispute arising before 2006 Act - Held that the Council has jurisdiction to decide disputes even if they arose prior to the enactment, as the Act applies to all pending disputes (Paras 2, 8-10).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether a writ petition is maintainable against an award of the Micro and Small Enterprises Facilitation Council, and whether the Council has jurisdiction to decide a dispute arising before the coming into effect of the Micro, Small and Medium Enterprises Development Act, 2006.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Writ petition dismissed. No order as to costs.

Law Points

  • Maintainability of writ petition against MSME Facilitation Council award
  • Jurisdiction of Council over pre-2006 disputes
  • Alternative remedy under Section 19 of MSMED Act
  • 2006
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (BOM) (10) 36

WRIT PETITION NO. 8496 OF 2019

2022-10-20

SANDEEP V. MARNE, J.

Shri L. D. Vakil for Petitioner, Shri K. B. Jadhavar A.G.P. for Respondent Nos. 1 and 2, Shri V. D. Sapkal Senior Advocate i/by Shri Yogesh S. Thorat for Respondent No. 3

Bajaj Auto Limited

The State of Maharashtra, Joint Director of Industries, M/s S. M. Solar Products Ltd., Micro, Small & Medium Enterprises Felicitation Council

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging award of Micro and Small Enterprises Facilitation Council

Remedy Sought

Petitioner sought to quash the award of the Facilitation Council

Filing Reason

Dispute over outstanding payment for parts supplied by respondent no. 3 to petitioner

Previous Decisions

Award passed by the Micro and Small Enterprises Facilitation Council

Issues

Whether a writ petition is maintainable against an award of the Micro and Small Enterprises Facilitation Council? Whether the Council has jurisdiction to decide a dispute arising before the coming into effect of the Micro, Small and Medium Enterprises Development Act, 2006?

Submissions/Arguments

Petitioner argued that the award is without jurisdiction as the dispute arose before the 2006 Act came into effect. Respondents argued that the writ petition is not maintainable due to alternative remedy under Section 19 of the Act.

Ratio Decidendi

A writ petition challenging an award of the Micro and Small Enterprises Facilitation Council is not maintainable because the Micro, Small and Medium Enterprises Development Act, 2006 provides a statutory remedy of appeal under Section 19, which is an efficacious alternative remedy. Additionally, the Council has jurisdiction to decide disputes even if they arose prior to the enactment of the Act.

Judgment Excerpts

Maintainability of writ petition challenging the award of the Micro and Small Enterprises Facilitation Council and jurisdiction of the Council to decide a dispute arising before coming into effect of the Micro, Small and Medium Enterprises Development Act, 2006 are the two issues that need to be determined in the present petition. Considering the broad two legal issues to be decided in the petition, it is not necessary to narrate the entire factual background under which the dispute between the parties has arisen.

Procedural History

The petitioner filed a writ petition challenging an award of the Micro and Small Enterprises Facilitation Council. The court heard the parties and closed the judgment on 17.10.2022, pronouncing it on 20.10.2022.

Acts & Sections

  • Micro, Small and Medium Enterprises Development Act, 2006: Section 18, Section 19
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Writ Petition Against MSME Facilitation Council Award on Maintainability Grounds. Council Has Jurisdiction Over Disputes Arising Before 2006 Act Came Into Effect.
Related Judgement
High Court Bombay High Court Allows Petition to Correct Illegal Sentence in NDPS Case Due to Non-Retrospective Amendment. Petitioner Convicted for Ganja Possession Under Section 20(b)(i) of NDPS Act, 1985 Sentenced to 10 Years Under Amended Provision, But Offen...