Bombay High Court Dismisses Petitioner's Challenge to Work Order in Tender Dispute — Additional Performance Security Furnished Within Time. Court holds that submission of additional performance security on the third working day was within the prescribed period of two working days as per Clause 2.22.0, and minor discrepancies in documents did not warrant disqualification.

High Court: Bombay High Court Bench: NAGPUR In Favour of Accused
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, M/s. V.N.Reddy, a government contractor, challenged the issuance of a work order dated 07.05.2021 by the Executive Engineer, Lower Wardha Project Division, Wardha (respondent no.2) in favor of respondent no.3, M/s. Om Gurusai Construction Company. The dispute arose from a tender notice issued on 18.01.2021 for construction of land development works. Three bidders submitted bids; technical bids were opened on 08.02.2021, and the petitioner and respondent no.3 were found eligible. On 12.03.2021, financial bids were opened, and respondent no.3's bid was the lowest. Clause 2.22.0 required the lowest bidder to furnish additional performance security within two working days. The petitioner alleged that respondent no.3 furnished the security on the third working day, thus should be disqualified. The court examined the timeline: financial bids opened on 12.03.2021 (Friday), the next working day was 15.03.2021 (Monday), and the security was furnished on 16.03.2021 (Tuesday). The court held that the period of two working days commenced from the date of opening, and since the security was furnished on the third working day, it was within time. The court also rejected ancillary grounds regarding document shortcomings, finding them minor. The petition was dismissed, upholding the work order.

Headnote

A) Tender Law - Additional Performance Security - Time Period - Clause 2.22.0 - The issue was whether the third respondent furnished additional performance security within the prescribed period of two working days. The court held that the period of two working days commenced from the date of opening of financial bids, and since the third respondent submitted the security on the third working day, it was within time as the first working day was the date of opening itself. (Paras 4-6)

B) Tender Law - Disqualification - Minor Discrepancies - The petitioner raised ancillary grounds regarding shortcomings in documents submitted by the third respondent. The court found that these were minor discrepancies and did not warrant disqualification, as the tender conditions did not mandate rejection for such minor issues. (Paras 7-8)

C) Tender Law - Judicial Review - Scope - The court reiterated that in tender matters, the scope of judicial review is limited to examining whether the decision-making process is arbitrary, irrational, or mala fide. The court found no such infirmity in the present case. (Para 9)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the third respondent's failure to furnish additional performance security within two working days as per Clause 2.22.0 of the tender conditions warranted his disqualification from the tender process.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The writ petition is dismissed. The work order dated 07.05.2021 issued in favor of the third respondent is upheld. No order as to costs.

Law Points

  • Interpretation of tender conditions
  • Additional performance security
  • Time period computation
  • Working days
  • Disqualification of bidder
  • Judicial review of tender process
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (BOM) (03) 97

WRIT PETITION NO. 1787/2021

2022-03-25

A.S.CHANDURKAR, G.A.SANAP

Shri S.D.Chopde for petitioner; S/Shri S.G.Jagtap with Shri H.D.Marathe for respondent nos. 1 & 2; Shri Tushar Tathod for respondent no.3

M/s. V.N.Reddy, Through its Proprietor – Shri V. Narsimha Reddy

1] The Superintending Engineer, Vidarbha Irrigation Development Corporation, 2] The Executive Engineer, Lower Wardha Project Division, Wardha, 3] Shri Mahesh Reddy, M/s. Om Gurusai Construction Company

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging issuance of work order in a tender process.

Remedy Sought

Petitioner sought quashing of work order dated 07.05.2021 issued in favor of respondent no.3 and direction to award the work to the petitioner.

Filing Reason

Petitioner alleged that respondent no.3 failed to furnish additional performance security within the prescribed two working days as per Clause 2.22.0, and therefore should have been disqualified.

Issues

Whether the third respondent's failure to furnish additional performance security within two working days as per Clause 2.22.0 of the tender conditions warranted his disqualification from the tender process.

Submissions/Arguments

Petitioner argued that the third respondent furnished additional performance security on the third working day, thus violating Clause 2.22.0 and should be debarred. Respondent no.3 contended that the security was furnished within time as the period of two working days commenced from the date of opening of financial bids, and the security was submitted on the third working day, which was within time. Respondent nos. 1 & 2 supported the tender process and submitted that the third respondent complied with the requirements.

Ratio Decidendi

The period of two working days for furnishing additional performance security under Clause 2.22.0 commences from the date of opening of financial bids. Submission of security on the third working day is within time as the first working day is the date of opening itself. Minor discrepancies in documents do not warrant disqualification unless the tender conditions expressly mandate rejection.

Judgment Excerpts

The period of two working days for furnishing additional performance security under Clause 2.22.0 commences from the date of opening of financial bids. Submission of security on the third working day is within time as the first working day is the date of opening itself. Minor discrepancies in documents do not warrant disqualification unless the tender conditions expressly mandate rejection.

Procedural History

The writ petition was filed on 12.01.2022 (amended as per court's order dated 07.01.2022). Arguments were closed on 25.02.2022 and judgment pronounced on 25.03.2022.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes FIR Against Applicant in Defamation Case for Allegations Against Police Officer — Lack of Prima Facie Case Under Section 500 IPC. Court holds that mere publication of news item based on representation without verification ...
Related Judgement
High Court Bombay High Court Dismisses Petitioner's Challenge to Work Order in Tender Dispute — Additional Performance Security Furnished Within Time. Court holds that submission of additional performance security on the third working day was within the presc...