Case Note & Summary
The petitioner, a company incorporated under the Companies Act, 1956, filed a writ petition under Article 226 of the Constitution challenging demand notices dated 23 December 2013 and 31 December 2014 issued under the Maharashtra Stamp Act. The core dispute pertained to penalty levied under Section 31(4) of the Act. Background: A scheme of arrangement/amalgamation was sanctioned by the High Court on 11 April 2008 under Sections 391 to 394 read with Sections 78 and 100 of the Companies Act, 1956. The petitioner lodged the order with the Collector of Stamps for adjudication of stamp duty on 17 May 2008 under Section 31 of the Maharashtra Stamp Act. The authorities sought details on 16 April 2010, but the petitioner did not reply. An interim demand letter was issued on 23 December 2013 for stamp duty of Rs.7,07,27,090 and penalty of Rs.9,76,03,385, the penalty computed from 11 April 2008 to 23 December 2013 at the rate of 2% per month. The petitioner requested a personal hearing and filed written submissions on 7 July 2014 and 19 December 2014, explicitly accepting the stamp duty quantum while disputing the penalty. A final demand notice dated 31 December 2014 confirmed both amounts. The petitioner appealed to the Chief Controlling Revenue Authority on 14 January 2015, challenging only the penalty. The Authority, by interim order dated 25 March 2015 under Section 53(1A), stayed the penalty proceedings on condition that the petitioner deposit the stamp duty. The petitioner deposited the duty on 27 March 2015. The appeal was held not maintainable on 25 April 2017, leading to the present writ petition. The only issue argued was the levy of penalty. The petitioner contended that the interim order of 25 March 2015 should be treated as the demand notice under Section 31(4), and since the stamp duty was paid on 27 March 2015, no default occurred. The respondent argued that the interim order was merely a stay and did not alter the date of demand; the penalty had already accrued because the petitioner failed to pay within 60 days of the original demand notice. In its analysis, the court extracted Section 31(4) and emphasized that penalty is leviable when an instrument is brought for adjudication and the person liable to pay stamp duty under Section 30 fails to pay within 60 days of the notice of demand; penalty is computed from the date of execution of the instrument. The court noted that the petitioner initially conceded that only penalty was in issue and made no submissions on the correctness of the stamp duty quantum, later altering its stand without advancing arguments. The court did not accept the argument that the interim order reset the date of demand; it held that the demand had already been made and liability to penalty arose upon failure to pay within the statutory period. The interim stay merely suspended recovery but did not extinguish the accrued penalty. As the provided text is truncated, the final holding is not explicitly recorded, but the analysis strongly indicates that the petition was dismissed and the penalty upheld.
Headnote
A) Stamp Law - Levy of Penalty - Section 31(4) of the Maharashtra Stamp Act - The petitioner challenged penalty imposed after adjudication of stamp duty on a scheme of arrangement, arguing that the demand notice should be considered from the date of the interim order (25 March 2015) and that payment of stamp duty within two days thereafter meant no default. The court examined Section 31(4) which mandates payment within 60 days of service of the notice of demand; failure attracts penalty from the date of execution of the instrument. The court noted that the petitioner had not challenged the stamp duty quantum, accepted the levy, and paid it only after interim stay. Held that the interim order was merely a stay of penalty recovery pending appeal and did not reset the starting point of demand. The liability for penalty accrued upon failure to pay within 60 days of the original demand notice. (Paras 18-23)
Issue of Consideration
Whether the petitioner is liable to pay penalty under Section 31(4) of the Maharashtra Stamp Act, and whether the interim order dated 25 March 2015 passed by the Chief Controlling Revenue Authority can be treated as the starting point for computation of penalty.
Final Decision
Decision not clearly stated
Law Points
- Legal points not extracted
- Section 31(4) of the Maharashtra Stamp Act provides that if a person fails to pay the adjudicated stamp duty within 60 days from the date of service of the notice of demand
- penalty at the rate of 2% per month is leviable from the date of execution of the instrument
- an interim stay on recovery of penalty does not alter the date of demand or the accrual of liability.



