Bombay High Court Considers Challenge to Penalty Under Maharashtra Stamp Act for Delayed Payment. Court Analyses Effect of Interim Stay on Demand Date Under Section 31(4).

High Court: Bombay High Court Bench: BOMBAY
  • 4
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, a company incorporated under the Companies Act, 1956, filed a writ petition under Article 226 of the Constitution challenging demand notices dated 23 December 2013 and 31 December 2014 issued under the Maharashtra Stamp Act. The core dispute pertained to penalty levied under Section 31(4) of the Act. Background: A scheme of arrangement/amalgamation was sanctioned by the High Court on 11 April 2008 under Sections 391 to 394 read with Sections 78 and 100 of the Companies Act, 1956. The petitioner lodged the order with the Collector of Stamps for adjudication of stamp duty on 17 May 2008 under Section 31 of the Maharashtra Stamp Act. The authorities sought details on 16 April 2010, but the petitioner did not reply. An interim demand letter was issued on 23 December 2013 for stamp duty of Rs.7,07,27,090 and penalty of Rs.9,76,03,385, the penalty computed from 11 April 2008 to 23 December 2013 at the rate of 2% per month. The petitioner requested a personal hearing and filed written submissions on 7 July 2014 and 19 December 2014, explicitly accepting the stamp duty quantum while disputing the penalty. A final demand notice dated 31 December 2014 confirmed both amounts. The petitioner appealed to the Chief Controlling Revenue Authority on 14 January 2015, challenging only the penalty. The Authority, by interim order dated 25 March 2015 under Section 53(1A), stayed the penalty proceedings on condition that the petitioner deposit the stamp duty. The petitioner deposited the duty on 27 March 2015. The appeal was held not maintainable on 25 April 2017, leading to the present writ petition. The only issue argued was the levy of penalty. The petitioner contended that the interim order of 25 March 2015 should be treated as the demand notice under Section 31(4), and since the stamp duty was paid on 27 March 2015, no default occurred. The respondent argued that the interim order was merely a stay and did not alter the date of demand; the penalty had already accrued because the petitioner failed to pay within 60 days of the original demand notice. In its analysis, the court extracted Section 31(4) and emphasized that penalty is leviable when an instrument is brought for adjudication and the person liable to pay stamp duty under Section 30 fails to pay within 60 days of the notice of demand; penalty is computed from the date of execution of the instrument. The court noted that the petitioner initially conceded that only penalty was in issue and made no submissions on the correctness of the stamp duty quantum, later altering its stand without advancing arguments. The court did not accept the argument that the interim order reset the date of demand; it held that the demand had already been made and liability to penalty arose upon failure to pay within the statutory period. The interim stay merely suspended recovery but did not extinguish the accrued penalty. As the provided text is truncated, the final holding is not explicitly recorded, but the analysis strongly indicates that the petition was dismissed and the penalty upheld.

Headnote

A) Stamp Law - Levy of Penalty - Section 31(4) of the Maharashtra Stamp Act - The petitioner challenged penalty imposed after adjudication of stamp duty on a scheme of arrangement, arguing that the demand notice should be considered from the date of the interim order (25 March 2015) and that payment of stamp duty within two days thereafter meant no default. The court examined Section 31(4) which mandates payment within 60 days of service of the notice of demand; failure attracts penalty from the date of execution of the instrument. The court noted that the petitioner had not challenged the stamp duty quantum, accepted the levy, and paid it only after interim stay. Held that the interim order was merely a stay of penalty recovery pending appeal and did not reset the starting point of demand. The liability for penalty accrued upon failure to pay within 60 days of the original demand notice. (Paras 18-23)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is liable to pay penalty under Section 31(4) of the Maharashtra Stamp Act, and whether the interim order dated 25 March 2015 passed by the Chief Controlling Revenue Authority can be treated as the starting point for computation of penalty.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Decision not clearly stated

Law Points

  • Legal points not extracted
  • Section 31(4) of the Maharashtra Stamp Act provides that if a person fails to pay the adjudicated stamp duty within 60 days from the date of service of the notice of demand
  • penalty at the rate of 2% per month is leviable from the date of execution of the instrument
  • an interim stay on recovery of penalty does not alter the date of demand or the accrual of liability.
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (06) 10

Writ Petition No.2358 of 2018

2025-06-18

Jitendra Jain

Citation not available, 2025:BHC-OS:8984

Mr Aditya Pimple, Mr Ranjit Shetty, Ms Avina Karnad, Ms Jyoti Chavan, Mr Himanshu Takke

IL & FS Financial Services Ltd.

State of Maharashtra, The Collector of Stamps (Enforcement-1), The Collector of Stamps (Enforcement-2), The Chief Controlling Revenue Authority

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 challenging demand notices levying penalty under Maharashtra Stamp Act.

Remedy Sought

Petitioner sought quashing of penalty imposed by demand notices dated 23.12.2013 and 31.12.2014, and argued only that penalty was invalid under Section 31(4).

Filing Reason

The appeal before the Chief Controlling Revenue Authority against the penalty was held not maintainable, and the petitioner challenged the penalty on the ground that no default occurred because payment of stamp duty was made within 2 days of the interim order which, according to petitioner, constituted the demand notice.

Previous Decisions

Interim order dated 25.3.2015 by Chief Controlling Revenue Authority under Section 53(1A) stayed penalty proceedings on deposit of stamp duty. Appeal was held not maintainable on 25.4.2017.

Issues

Whether the petitioner is liable to pay penalty under Section 31(4) of the Maharashtra Stamp Act when it paid the stamp duty within two days of the interim order of the Chief Controlling Revenue Authority but after the expiry of 60 days from the original demand notice.

Submissions/Arguments

Petitioner argued that the interim order dated 25.3.2015 should be considered as the date of demand notice under Section 31(4), and since stamp duty was paid on 27.3.2015, there was no default and thus penalty cannot be levied. Respondent submitted that the interim order was only a stay of recovery of penalty pending appeal and did not alter the date of demand; the petitioner had accepted the stamp duty quantum and had failed to pay within 60 days of the original demand, thus penalty was valid.

Ratio Decidendi

Under Section 31(4) of the Maharashtra Stamp Act, penalty at 2% per month is leviable from the date of execution of the instrument when the person liable fails to pay the adjudicated stamp duty within 60 days from the date of service of the notice of demand. An interim order staying recovery of penalty during appeal does not reset the date of demand or extinguish the accrued penalty.

Judgment Excerpts

(4) When an instrument is brought to the Collector for adjudication,— (i) within one month of the execution or first execution of such instrument in the State; or (ii) if, such instrument is executed or first executed, out of the State, within three months from the date of first receipt of such instrument in this State, the person liable to pay the stamp duty under section 30 shall pay the same within sixty days from the date of service of the notice of demand in respect of the stamp duty adjudicated by the Collector. If such person fails to pay the stamp duty so demanded within the said period, he shall be liable to pay a penalty at the rate of two per cent of the deficient portion of the stamp duty, for every month or part thereof, from the date of execution of such instrument, or as the case may be, date of the first receipt of such instrument in the State: Provided that, in no case, the amount of the penalty shall exceed (four times) the deficient portion of the stamp duty. the only issue involved in the present petition is justification for levy of penalty since the Petitioner has accepted the quantum of stamp duty. the Petitioner has not advanced any argument on any prayers except prayer clause (a).

Procedural History

Scheme of arrangement sanctioned on 11.04.2008. Petitioner lodged order for adjudication on 17.05.2008. Respondents sought details on 16.04.2010, no reply. Interim demand notice issued on 23.12.2013 for stamp duty and penalty. Petitioner requested hearing, filed submissions on 07.07.2014 and 19.12.2014, accepting stamp duty but disputing penalty. Final demand notice issued on 31.12.2014 confirming duty and penalty. Appeal filed before Chief Controlling Revenue Authority on 14.01.2015, challenging only penalty. Interim order on 25.03.2015 under Section 53(1A): stay of penalty on deposit of duty. Petitioner deposited duty on 27.03.2015. Appeal held not maintainable on 25.04.2017. Writ petition filed thereafter. Reserved on 17.06.2025, pronounced on 18.06.2025.

Acts & Sections

  • Maharashtra Stamp Act (formerly Bombay Stamp Act, 1958): 31(4), 31, 30, 53(1A)
  • Companies Act, 1956: 391, 392, 393, 394, 78, 100
  • Constitution of India: 226
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay Allows Section 11 Application for Appointment of Fresh Arbitrator After Termination of Previous Arbitrator's Mandate Due to Expiry of Agreed Six-Month Period. Consent Minutes Separating Arbitration Agreement from Specific Appoint...
Related Judgement
High Court Bombay High Court Considers Challenge to Penalty Under Maharashtra Stamp Act for Delayed Payment. Court Analyses Effect of Interim Stay on Demand Date Under Section 31(4).