Case Note & Summary
The litigation arose from a dispute between the Bhusawal Borough Municipality and the electricity supply company over liability to pay War Costs Surcharge under the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944. The Municipality had entered into agreements for supply of electrical energy and, based on its interpretation of those agreements, paid certain electricity charges under protest. It filed two suits seeking refund of two sums of money paid to the electricity company as surcharge, contending that it was not liable to pay the surcharge under the 1944 Order. The State of Bombay was later added as a defendant. The electricity company defended on the ground that the dispute had been referred to and decided by the Government of Bombay, and that under the second proviso to Clause 5 of the Surcharge Order the decision of the Provincial Government was final and binding on both parties. The trial court decreed both suits in favour of the Municipality, and the District Court affirmed those decrees. In second appeal, the Bombay High Court set aside the decrees and dismissed the suits, after admitting certain documents as additional evidence. The Municipality then appealed to the Supreme Court by special leave. The primary legal issues before the Supreme Court were whether the Government's communication dated May 22, 1946 constituted a final and binding decision under the second proviso to Clause 5; whether the second proviso required that the dispute be referred by both parties or whether a reference by any one interested party sufficed; and whether the High Court could correct the lower courts' misconstruction of the document in second appeal. The Municipality argued that the High Court had no power to admit additional evidence in second appeal under Order XLI Rule 27 of the Code of Civil Procedure and that the provisions could not fill up lacunae in evidence. It further contended that the communication was merely an opinion and not a decision, and that the second proviso made the Government an arbitrator, requiring a joint reference under the Arbitration Act, 1940. The Court did not permit the arbitration argument as it had not been raised earlier, and found it unnecessary to decide the additional evidence question because the appeal could be resolved on the construction of the document. The Supreme Court examined the text of the second proviso and the communication dated May 22, 1946. The communication, signed by the Secretary to the Government of Bombay, stated that the Government had fully considered the case under the second proviso and had decided that the Municipality should pay the surcharge at 15% fixed in a Government Order, unless the electricity company raised its rate for street lighting beyond four annas per unit. The Court observed that both parties had stated their respective cases before the Government, which they would not have done unless they were acting under the second proviso. It rejected the argument that the communication was only an opinion, noting that there was no reason to treat a decision on its face as anything else, and that if any correspondence showed the Municipality did not refer the dispute, it was for the Municipality to produce that correspondence, and its omission to do so must be construed against it. The Court also held that the clear language of the proviso "in the event of dispute by any party interested" permitted a reference by one party alone, and the contention that both parties must refer was untenable. Finally, the Court held that the lower courts had wholly misconstrued the document, which was not merely of evidentiary value but was the basis of the electricity company's claim for surcharge. Misconstruction of such a document was an error of law, and the High Court in second appeal was entitled to correct it. Accordingly, the Supreme Court dismissed the appeals with costs, affirming the High Court's decision that the Municipality was not entitled to refund.
Headnote
A) Electricity Law - War Costs Surcharge - Finality of Government Decision - Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, Clause 5 Second Proviso - The dispute between the Municipality and the Electricity Company regarding liability to pay War Costs Surcharge was considered by the Government of Bombay after both parties stated their cases, and the Government's communication dated May 22, 1946 stated that it had decided the Municipality should pay the surcharge at 15% unless the Company raised its rate for street lighting beyond four annas per unit. The Court held that the communication was a final decision under the second proviso and was binding on both parties, not a mere opinion; there was no reason to treat a decision on its face as anything else. Held that the Municipality was not entitled to refund. B) Electricity Law - Interpretation of Second Proviso to Clause 5 - Unilateral Reference to Government - Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, Clause 5 Second Proviso - The second proviso provided that "in the event of dispute by any party interested" the decision of the Provincial Government shall be final. The Court rejected the contention that the dispute had to be referred by both parties, holding that the clear language allowed any one interested party to refer the dispute, and there was no requirement of a joint reference. Held that the reference by one party was sufficient. C) Civil Procedure - Second Appeal - Misconstruction of Document as Error of Law - Code of Civil Procedure, 1908 - The lower courts had wholly misconstrued the Government communication dated May 22, 1946, which was not merely of evidentiary value but was the document upon which the respondent's claim for surcharge was based. The Court held that misconstruction of such a document was an error of law, and the High Court in second appeal was entitled to correct it. Held that the High Court rightly set aside the decrees and dismissed the suits.
Issue of Consideration
Whether the Municipality was entitled to refund of surcharge paid under protest; whether the communication dated May 22, 1946 from the Government of Bombay was a final and binding decision under the second proviso to Clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944; whether the second proviso required a reference of dispute by both parties; and whether the High Court in second appeal could correct the lower courts' misconstruction of a document on which the claim was based.
Final Decision
Supreme Court dismissed the appeals with costs, holding that the Government's communication dated May 22, 1946 was a final and binding decision under the second proviso to Clause 5 of the Surcharge Order, 1944, and the Municipality was not entitled to refund. The lower courts had misconstrued the document, which was an error of law correctable by the High Court in second appeal.
Law Points
- Second proviso to Clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order
- 1944 made the decision of the Provincial Government final and binding
- Dispute could be referred by any party interested and not necessarily by both parties
- Communication dated May 22
- 1946 constituted a final decision and not a mere opinion
- Misconstruction of a document upon which a claim is based is an error of law correctable in second appeal
- Burden on party objecting to the document to produce correspondence showing otherwise



