Supreme Court Dismisses Appeals by Municipality in Electricity Surcharge Refund Case, Upholding Government Decision as Final and Binding. Second Proviso to Clause 5 of Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, Allowed Any Interested Party to Refer Dispute to Provincial Government, and Government's Communication Dated May 22, 1946 Constituted a Final Decision Barring Refund Claim.

In Favour of Accused
  • 33
Judgement Image
Font size:
Print

Case Note & Summary

The litigation arose from a dispute between the Bhusawal Borough Municipality and the electricity supply company over liability to pay War Costs Surcharge under the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944. The Municipality had entered into agreements for supply of electrical energy and, based on its interpretation of those agreements, paid certain electricity charges under protest. It filed two suits seeking refund of two sums of money paid to the electricity company as surcharge, contending that it was not liable to pay the surcharge under the 1944 Order. The State of Bombay was later added as a defendant. The electricity company defended on the ground that the dispute had been referred to and decided by the Government of Bombay, and that under the second proviso to Clause 5 of the Surcharge Order the decision of the Provincial Government was final and binding on both parties. The trial court decreed both suits in favour of the Municipality, and the District Court affirmed those decrees. In second appeal, the Bombay High Court set aside the decrees and dismissed the suits, after admitting certain documents as additional evidence. The Municipality then appealed to the Supreme Court by special leave. The primary legal issues before the Supreme Court were whether the Government's communication dated May 22, 1946 constituted a final and binding decision under the second proviso to Clause 5; whether the second proviso required that the dispute be referred by both parties or whether a reference by any one interested party sufficed; and whether the High Court could correct the lower courts' misconstruction of the document in second appeal. The Municipality argued that the High Court had no power to admit additional evidence in second appeal under Order XLI Rule 27 of the Code of Civil Procedure and that the provisions could not fill up lacunae in evidence. It further contended that the communication was merely an opinion and not a decision, and that the second proviso made the Government an arbitrator, requiring a joint reference under the Arbitration Act, 1940. The Court did not permit the arbitration argument as it had not been raised earlier, and found it unnecessary to decide the additional evidence question because the appeal could be resolved on the construction of the document. The Supreme Court examined the text of the second proviso and the communication dated May 22, 1946. The communication, signed by the Secretary to the Government of Bombay, stated that the Government had fully considered the case under the second proviso and had decided that the Municipality should pay the surcharge at 15% fixed in a Government Order, unless the electricity company raised its rate for street lighting beyond four annas per unit. The Court observed that both parties had stated their respective cases before the Government, which they would not have done unless they were acting under the second proviso. It rejected the argument that the communication was only an opinion, noting that there was no reason to treat a decision on its face as anything else, and that if any correspondence showed the Municipality did not refer the dispute, it was for the Municipality to produce that correspondence, and its omission to do so must be construed against it. The Court also held that the clear language of the proviso "in the event of dispute by any party interested" permitted a reference by one party alone, and the contention that both parties must refer was untenable. Finally, the Court held that the lower courts had wholly misconstrued the document, which was not merely of evidentiary value but was the basis of the electricity company's claim for surcharge. Misconstruction of such a document was an error of law, and the High Court in second appeal was entitled to correct it. Accordingly, the Supreme Court dismissed the appeals with costs, affirming the High Court's decision that the Municipality was not entitled to refund.

Headnote

A) Electricity Law - War Costs Surcharge - Finality of Government Decision - Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, Clause 5 Second Proviso - The dispute between the Municipality and the Electricity Company regarding liability to pay War Costs Surcharge was considered by the Government of Bombay after both parties stated their cases, and the Government's communication dated May 22, 1946 stated that it had decided the Municipality should pay the surcharge at 15% unless the Company raised its rate for street lighting beyond four annas per unit. The Court held that the communication was a final decision under the second proviso and was binding on both parties, not a mere opinion; there was no reason to treat a decision on its face as anything else. Held that the Municipality was not entitled to refund.

B) Electricity Law - Interpretation of Second Proviso to Clause 5 - Unilateral Reference to Government - Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, Clause 5 Second Proviso - The second proviso provided that "in the event of dispute by any party interested" the decision of the Provincial Government shall be final. The Court rejected the contention that the dispute had to be referred by both parties, holding that the clear language allowed any one interested party to refer the dispute, and there was no requirement of a joint reference. Held that the reference by one party was sufficient.

C) Civil Procedure - Second Appeal - Misconstruction of Document as Error of Law - Code of Civil Procedure, 1908 - The lower courts had wholly misconstrued the Government communication dated May 22, 1946, which was not merely of evidentiary value but was the document upon which the respondent's claim for surcharge was based. The Court held that misconstruction of such a document was an error of law, and the High Court in second appeal was entitled to correct it. Held that the High Court rightly set aside the decrees and dismissed the suits.

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Municipality was entitled to refund of surcharge paid under protest; whether the communication dated May 22, 1946 from the Government of Bombay was a final and binding decision under the second proviso to Clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944; whether the second proviso required a reference of dispute by both parties; and whether the High Court in second appeal could correct the lower courts' misconstruction of a document on which the claim was based.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Supreme Court dismissed the appeals with costs, holding that the Government's communication dated May 22, 1946 was a final and binding decision under the second proviso to Clause 5 of the Surcharge Order, 1944, and the Municipality was not entitled to refund. The lower courts had misconstrued the document, which was an error of law correctable by the High Court in second appeal.

Law Points

  • Second proviso to Clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order
  • 1944 made the decision of the Provincial Government final and binding
  • Dispute could be referred by any party interested and not necessarily by both parties
  • Communication dated May 22
  • 1946 constituted a final decision and not a mere opinion
  • Misconstruction of a document upon which a claim is based is an error of law correctable in second appeal
  • Burden on party objecting to the document to produce correspondence showing otherwise
Subscribe to unlock Law Points Subscribe Now

Case Details

1963 LawText (SC) (12) 7

Civil Appeals Nos. 47 and 48 of 1961

1963-12-10

Mudholkar, J.R., Sinha, Bhuvneshwar P. (CJ), Dayal, Raghubar, Ayyangar, N. Rajagopala

1966 AIR 1652, 1964 SCR (5) 905

G.S. Pathak, Naunit Lal, I.N. Shroff, M.S.K. Sastri, R.H. Dhebar

Bhusawal Borough Municipality

Amalgamated Electricity Co. Ltd. & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suits for refund of electricity surcharge paid under protest, arising from a dispute over liability under the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944.

Remedy Sought

Appellant Municipality sought refund of two sums of money paid under protest to respondent No.1 as electricity charges, claiming it was not liable to pay surcharge under the Surcharge Order, 1944.

Filing Reason

Municipality disputed its liability to pay War Costs Surcharge under the 1944 Order based on its interpretation of agreements regarding payment of electric charges; it paid the surcharge under protest and filed two suits for refund.

Previous Decisions

Trial court and District Court decreed in favour of Municipality; Bombay High Court in second appeal set aside the decrees and dismissed the suits, after admitting additional evidence, holding that the Government decision was final and binding.

Issues

Whether the Municipality was entitled to refund of surcharge paid under protest. Whether the communication dated May 22, 1946 from the Government of Bombay was a final and binding decision under the second proviso to Clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944. Whether the second proviso required a reference of dispute by both parties or whether a reference by any one interested party sufficed. Whether the High Court in second appeal could correct the lower courts' misconstruction of a document on which the claim was based.

Submissions/Arguments

Appellant contended that the High Court was incompetent in second appeal to admit additional evidence on record because Order XLI Rule 27 of the Code of Civil Procedure was inapplicable to a second appeal and could not be used to fill up lacunae in evidence. Appellant argued that it was not established that the dispute had been referred to the Government and that the communication dated May 22, 1946 contained nothing but the opinion of the Government. Appellant further urged that the second proviso constituted the Government into an arbitrator, requiring a reference by both parties under the Arbitration Act, 1940 (this argument was not permitted as it had not been raised earlier). Respondent No.1 defended on the ground that the dispute between it and the Municipality had been decided by the Government of Bombay and that under the second proviso to Clause 5 of the Surcharge Order, the decision of the Government was final and binding on both parties.

Ratio Decidendi

The second proviso to Clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, made the decision of the Provincial Government on a dispute by any party interested final and binding. A communication from the Government that on its face states a decision, after considering both parties' cases, is a final decision and not a mere opinion. The proviso does not require a reference by both parties; the phrase 'by any party interested' allows unilateral reference. Misconstruction of a document upon which a claim is based is an error of law, correctable in second appeal by the High Court.

Judgment Excerpts

The communication of May 22, 1946 relied upon by the first respondent runs thus: ... Government has fully considered your case under the second proviso to clause 5 of the Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944, and has decided that you should pay the surcharge to the Bhusawal Electricity Co. Ltd., at the rate of 15 % fixed in Government Order No. 6331/36 (IV) dated the 15th August, 1944, unless the Company raised its rate of supply of energy for street lighting to more than 4 annas per unit. In the event of dispute by any party interested the decision of the Provincial Government shall be final. Misconstruction of such a document would thus be an error of law and the High Court in second appeal would be entitled to correct it.

Procedural History

Appellant Municipality filed two suits for refund of surcharge paid under protest. Trial court decreed in favour of Municipality in both suits. District Court affirmed the decrees. Respondent No.1 filed second appeals before the Bombay High Court. The High Court by order dated April 30, 1958 admitted additional evidence, and by judgment dated August 5, 1957 set aside the decrees and dismissed the suits. Appellant obtained special leave and filed Civil Appeals Nos. 47 and 48 of 1961 before the Supreme Court.

Acts & Sections

  • Bombay Electricity Supply (Licensed Undertakings War Costs) Order, 1944: Clause 5, Second Proviso
  • Code of Civil Procedure, 1908: Order XLI Rule 27
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Madras High Court Quashes Government Orders Declaring Land as Government Tharisu in Land Ceiling Proceedings. Court Directs Reclassification Based on Revised Final Statement Under Sections 14 and 18(1) of Tamil Nadu Land Reforms (Fixation of Ceiling ...
Related Judgement
High Court Bombay High Court Allows Writ Petition Challenging School Tribunal's Rejection of Appeal Regarding Promotion to Junior Clerk Post. Petitioner Cook Held Entitled to Promotion Over Peon Based on Higher Qualifications and Government Resolutions.