Supreme Court Dismisses Appeals in Land Acquisition Delay Case. Court Held That Challenge to Acquisition Notifications Under Sections 4 and 6 of Rajasthan Land Acquisition Act, 1953 Must Be Made Within Reasonable Time and Writ Petitions Filed After Nine Years and After Award Were Barred by Laches.

In Favour of Prosecution
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose from land acquisition proceedings initiated by the State of Rajasthan for the planned development of the city of Jaipur under the Rajasthan Land Acquisition Act, 1953. The appellants were a cooperative housing society and others whose lands were sought to be acquired. The State issued a notification under Section 4 of the Act on 13 May 1960, published in the Rajasthan Gazette on 9 June 1960. No objections were filed under Section 5A of the Act. A declaration under Section 6 was published on 11 May 1961, and notices under Section 9 were issued on 18 July 1961. Claims were filed by 63 persons, including the predecessor-in-title of the appellant in Civil Appeal No. 943 of 1973. An award was made on 9 January 1964 and amended on 9 July 1964 due to certain sale transactions. The appellants filed writ petitions on 23 January 1970, challenging the validity of the notifications dated 13 May 1960 and 11 May 1961 under Sections 4 and 6, and the notices dated 18 July 1961 under Section 9 of the Act. The grounds of challenge included discrimination and the allegation that land was being acquired at negligible price and would be sold at exorbitant price by the Improvement Trust to the public. The Rajasthan High Court dismissed the writ petitions primarily on the ground of inordinate delay, and also rejected the challenges on merits. The appellants then approached the Supreme Court by special leave. The Attorney General argued at the threshold that if the appellants failed on the ground of delay, it was not necessary to go into the other contentions. The Supreme Court relied on its recent decision in Aflatoon & Ors. v. Lt. Governor of Delhi & Ors., (1975) 1 SCR 802, which held that if persons allow the Government to complete acquisition proceedings on the basis that the notification under Section 4 and the declaration under Section 6 are valid and then attack the notification on grounds available to them earlier, it would be putting a premium on dilatory tactics. The Court observed that land acquisition proceedings commence with a notification under Section 4, objections are invited under Section 5A, and thereafter a declaration under Section 6 is made. Any challenge to a notification under Section 4 and a declaration under Section 6 should be made within a reasonable time thereafter. The length of the delay is an important circumstance because of the nature of acts done during the interval on the basis of the notification and declaration. In the present case, the appellants came to Court nine years after the declaration under Section 6. The Supreme Court held that the High Court rightly dismissed the applications on the ground of delay. Accordingly, the appeals were dismissed with costs.

Headnote

A) Land Acquisition - Delay and Laches - Challenge to Notification under Sections 4 and 6 - Rajasthan Land Acquisition Act, 1953, Sections 4,5A,6,9 - The State issued a notification under Section 4 on 13 May 1960 and a declaration under Section 6 on 11 May 1961; writ petitions were filed on 23 January 1970, nine years after declaration and after award. The High Court dismissed the petitions for inordinate delay. The Supreme Court held that any challenge to a notification under Section 4 and a declaration under Section 6 of the Act should be made within a reasonable time thereafter; if persons allow the Government to complete acquisition proceedings on the basis that the notifications are valid and then attack them on grounds available earlier, it would be putting a premium on dilatory tactics. Held that the appeals are dismissed with costs (Paras 1-3).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether writ petitions challenging land acquisition notifications under Sections 4, 6 and 9 of the Rajasthan Land Acquisition Act, 1953 filed nine years after the declaration under Section 6 and after the award should be dismissed on the ground of inordinate delay and laches.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeals were dismissed with costs. The Supreme Court held that the High Court rightly dismissed the writ petitions on the ground of inordinate delay. Any challenge to a notification under Section 4 and a declaration under Section 6 of the Rajasthan Land Acquisition Act, 1953 should be made within a reasonable time thereafter. Parties who allowed the Government to complete acquisition proceedings on the basis that the notifications were valid and then attacked them on grounds available earlier would be putting a premium on dilatory tactics.

Law Points

  • Challenge to notification under Section 4 and declaration under Section 6 of Rajasthan Land Acquisition Act
  • 1953 must be made within a reasonable time
  • persons who allow government to complete acquisition proceedings on basis that notifications are valid and later attack on grounds available earlier engage in dilatory tactics
  • length of delay is important because of acts done during interval on basis of notification and declaration
Subscribe to unlock Law Points Subscribe Now

Case Details

1974 LawText (SC) (09) 6

Civil Appeals Nos. 943 and 980 to 989 of 1973

1974-09-17

Ray, A.N. (CJ), Mathew, K.K., Chandrachud, Y.V., Alagiriswami, A., Gupta, A.C.

1974 AIR 2085, 1975 SCR (2) 68, 1975 SCC (4) 296

A.K. Sen, M.M. Kshatriya, Niren De, L.M. Singhvi, S.M. Jain, S.K. Tewari

Indrapuri Griha Nirman Sahakari Samiti Ltd.

The State of Rajasthan & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petitions filed under Article 226 challenging the validity of land acquisition notifications under the Rajasthan Land Acquisition Act, 1953, dismissed by the High Court on the ground of inordinate delay, and appealed to the Supreme Court by special leave.

Remedy Sought

Appellants sought quashing of notifications dated 13 May 1960 and 11 May 1961 under Sections 4 and 6, and notices dated 18 July 1961 under Section 9 of the Rajasthan Land Acquisition Act, 1953.

Filing Reason

The State proposed to acquire land for planned development of Jaipur; the appellants challenged the acquisition on grounds of discrimination and alleged acquisition at negligible price with intended resale at exorbitant price by the Improvement Trust.

Previous Decisions

The Rajasthan High Court dismissed the writ petitions on 12 April 1973 on the ground of inordinate delay and also rejected the challenges on merits.

Issues

Whether writ petitions challenging land acquisition notifications under Sections 4, 6 and 9 of the Rajasthan Land Acquisition Act, 1953 filed nine years after the declaration under Section 6 and after the award should be dismissed on the ground of inordinate delay and laches.

Submissions/Arguments

Appellants contended that the acquisition notifications were invalid on grounds of discrimination and that land was being acquired at negligible price and would be sold at exorbitant price by the Improvement Trust to the public. Attorney General submitted that if the appellants failed on the ground of delay, it was not necessary to go into the rest of the contentions in the judgment.

Ratio Decidendi

A challenge to a notification under Section 4 and a declaration under Section 6 of the Rajasthan Land Acquisition Act, 1953 must be made within a reasonable time after such notification or declaration. If persons allow the Government to complete acquisition proceedings on the basis that the notifications are valid and then attack them on grounds available earlier, it amounts to putting a premium on dilatory tactics. The length of the delay is an important circumstance because of the nature of acts done during the interval on the basis of the notification and declaration.

Judgment Excerpts

If persons allowed the Government to complete the acquisition proceedings on the basis that the notification under section 4 and the declaration under 6 were valid and then attacked the notification on grounds which were available to them at the time when the notification was published it would be putting a premium on dilatory tactics. Any challenge to a notification under section 4 and a declaration under section 6 of the Act should be made within a reasonable time there-after.

Procedural History

The State of Rajasthan proposed to acquire land for the planned development of Jaipur. On 13 May 1960, a notice under Section 4 of the Rajasthan Land Acquisition Act, 1953 was issued and published in the Rajasthan Gazette on 9 June 1960. No objection was made under Section 5A. A notice under Section 6 was published on 11 May 1961. On 18 July 1961, notices under Section 9 were issued. 63 persons including the predecessor-in-title of the appellant in Civil Appeal No. 943 of 1973 filed claims. An award was made on 9 January 1964 and amended on 9 July 1964. Writ petitions were filed on 23 January 1970. The Rajasthan High Court dismissed the writ petitions on 12 April 1973 on the ground of inordinate delay. Appeals by special leave were filed before the Supreme Court and dismissed on 17 September 1974.

Acts & Sections

  • Rajasthan Land Acquisition Act, 1953: 4, 5A, 6, 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes MHADA Order in Redevelopment Dispute — Upholds Developer's Right to Fair Hearing. Section 95A of MHADA Act, 1976 Requires Compliance with Natural Justice Before Revoking Development Rights.
Related Judgement
Supreme Court Supreme Court Upholds Validity of Hindu Adoption Under Section 11(vi) of Hindu Adoptions and Maintenance Act, 1956. Ceremony of Giving and Taking Held Conclusive of Intent to Transfer Child from Birth Family to Adoptive Family, Overruling Division Be...