Case Note & Summary
The dispute involved M/s Hyderabad Vanaspati Limited, a public limited company engaged in manufacturing, and the Andhra Pradesh State Electricity Board regarding the supply of high tension power. The company entered into agreements with the Board in 1970 and 1973. In 1976, the Board disconnected power supply due to alleged pilferage, leading to a provisional assessment of losses. The company contested the assessment and sought a declaration from the civil court that it was not liable for penal damages. The trial court upheld its jurisdiction but dismissed the suit, a decision later affirmed by the High Court. The High Court found that the agreements did not contravene the Electricity Act or the Supply Act and that the Board had acted within its rights. The appellant then appealed to the Supreme Court after obtaining special leave. The Supreme Court examined the legality of the Board's terms and conditions, particularly Clause 39, which outlined procedures for addressing pilferage. The court concluded that these terms were statutory and necessary for the Board's function of regulating electricity supply. It emphasized that the Board's authority to impose such conditions was valid under Section 49 of the Supply Act, and the terms did not violate Article 14 of the Constitution. The court ultimately upheld the Board's actions and dismissed the appeal, affirming the legality of the Board's procedures for dealing with energy pilferage.
Headnote
A) Electricity Law - Terms and Conditions of Supply - Validity of Clause 39 - Electricity (Supply) Act, 1948, Section 49 - The court held that the terms and conditions of supply, including Clause 39, are statutory in character and do not violate any provisions of the Act. The Board is empowered to impose such terms to prevent pilferage and ensure efficient supply of electricity (Paras 20-34).
Issue of Consideration
Whether the terms and conditions of supply imposed by the Board are ultra vires the provisions of the Electricity Act, 1910 and the Electricity (Supply) Act, 1948.
Final Decision
The Supreme Court upheld the validity of Clause 39 of the Terms and Conditions of Supply, affirming that the Board acted within its statutory authority under the Electricity (Supply) Act, 1948. The court dismissed the appeal, validating the Board's procedures for addressing pilferage and ensuring compliance with statutory obligations.
Law Points
- Electricity supply agreements
- jurisdiction of civil courts
- statutory obligations
- contractual terms
- adjudicatory process
- Article 14 of the Constitution