Case Note & Summary
The dispute arose from a contract between a contractor and the Union of India for the construction of a building, which was divided into two phases. The contract commenced on March 10, 1979, with completion dates set for June 9, 1980, and November 9, 1980, respectively. Disagreements emerged regarding the timely handing over of the site, with the contractor claiming that the site was not handed over as agreed, preventing him from commencing work. The Union of India contended that the contractor had abandoned the work and breached the contract. The contract included a clause for arbitration, leading the contractor to seek the appointment of an arbitrator after the dispute escalated. The Supreme Court appointed a former judge as the arbitrator, who examined the evidence and awarded the contractor escalation costs among other claims. The Union of India challenged the award, arguing that the arbitrator exceeded his jurisdiction by awarding escalation costs without a specific clause in the contract. The court analyzed whether the arbitrator had misconducted himself or exceeded his jurisdiction under Section 30 of the Arbitration Act, 1940. It was determined that the arbitrator acted within his jurisdiction, as the issue of escalation costs was a normal consequence of delays in contract execution. The court upheld the award, stating that the arbitrator's findings were reasonable and within the scope of the contract. Consequently, the court directed the Union of India to pay the awarded amounts, including the arbitrator's fees and costs.
Headnote
A) Arbitration Law - Jurisdiction of Arbitrator - Legal Misconduct - An arbitrator can only be set aside under Section 30 of the Arbitration Act if he has misconducted himself or the proceedings. - Arbitration Act, 1940, Section 30 - The court held that adjudicating upon a matter not subject to adjudication constitutes legal misconduct. The arbitrator's award was upheld as he acted within his jurisdiction. (Paras 121C-D, 122C-D). B) Arbitration Law - Escalation Costs - Escalation is a normal incident arising from delays in contract execution. - Arbitration Act, 1940, Section 30 - The court found that the arbitrator reasonably awarded 20% escalation costs due to delays attributed to the respondent, affirming the award's validity. (Paras 121F, 122A).
Issue of Consideration
Whether the arbitrator exceeded his jurisdiction in awarding escalation costs and whether the award can be set aside under the Arbitration Act, 1940.
Final Decision
The Supreme Court upheld the arbitrator's award, affirming that the arbitrator acted within his jurisdiction and that the award was valid. The Union of India was directed to pay the awarded amounts, including Rs. 17,500 as the arbitrator's remuneration and Rs. 10,000 towards advocates' fees and costs.
Law Points
- Arbitration misconduct
- Jurisdiction of arbitrator
- Escalation costs
- Legal misconduct
- Award setting aside



