Case Note & Summary
The dispute arose from two agreements between a contractor and the State of Andhra Pradesh for road repair works. The contractor claimed losses due to delays and escalations, leading to an arbitration award of Rs. 99 lacs. However, the Civil Court set aside the award, and the High Court later allowed a claim of Rs. 16 lacs with interest. In execution proceedings, the State claimed a set off of Rs. 22 lacs against the contractor's claim, which the Executing Court allowed. The contractor contested this, arguing that the State was not entitled to set off in execution proceedings. The High Court upheld the State's claim for the first amount under clause 68 of the contract but required the second claim to await arbitration. The Supreme Court, while allowing the appeal in part, confirmed the High Court's decision regarding the first claim but rejected the second claim for lack of evidence supporting an equitable set off. The court emphasized that adjustments must be based on ascertained sums and that the claims must arise from the same transaction to qualify for equitable set off. The appeal was allowed in part, maintaining the adjustment for the final bill but setting aside the adjustment for the second claim, with parties bearing their own costs.
Headnote
A) Civil Procedure - Set Off Claims - Court's Power to Allow Set Off - Civil Procedure Code, 1908, Order 21, Rule 18 - The court has the power to allow a set off in certain circumstances even if it does not strictly fall within the terms of Order 21, Rule 18. The High Court's decision to allow set off based on the contract terms was upheld, indicating the court's discretion in equitable set off matters (Paras 112B-112C). B) Contract Law - Adjustment of Claims - Clause 68 and 71 of the Contract - The claim for adjustment based on the final bill was justified under clause 68, while the claim under another contract was not supported by evidence for equitable set off. The court clarified that adjustments must be based on ascertained sums (Paras 112F-113A).
Issue of Consideration
Whether the respondent State was entitled to set off amounts against the decretal amount in execution proceedings.
Final Decision
The Supreme Court allowed the appeal in part, maintaining the adjustment for the final bill but setting aside the adjustment for the claim under the other contract, with parties bearing their own costs.
Law Points
- Equitable set off
- adjustment of claims
- execution proceedings
- contractual obligations
- Civil Procedure Code interpretation


