Case Note & Summary
The dispute arose from the auction of leasehold rights on a plot in Nehru Place, Delhi, which was awarded to the appellant for Rs. 8.13 crores in January 1981. The appellant paid 25% of the auction amount but failed to pay the remaining 75% within the stipulated time, citing confusion over ownership and a downturn in the property market. Revised payment terms were communicated in December 1984, requiring the appellant to pay the remaining amount in instalments with interest. The appellant submitted building plans in August 1985, which were forwarded to the Delhi Urban Arts Commission (DUAC) for approval. However, the DUAC sought clarifications, and the appellant claimed deemed sanction for construction due to lack of response within sixty days. In October 1985, the Central Government imposed a ban on multi-storeyed buildings pending a new master plan, which the D.D.A. communicated to the appellant. The D.D.A. later rejected the building plans, leading the appellant to file writ petitions challenging the construction ban and the D.D.A.'s actions. The High Court allowed construction at the appellant's risk but upheld the D.D.A.'s claims for interest and compounding fees. The Supreme Court, upon appeal, clarified that the D.D.A. was entitled to charge simple interest on the instalments but not compound interest. It upheld the legality of the construction ban and the requirement for compounding fees due to lack of a building permit, while ruling that no interest could be charged on the compounding fee. The court modified the High Court's order regarding the timeline for compliance with payment and sanctioning of plans. The appeals were partly allowed, with no costs awarded.
Headnote
A) Administrative Law - High Rise Construction Ban - Legality of Ban - Delhi Development Act, 1947, Sections 9(2), 41 - The Central Government's ban on high rise constructions during the formulation of a new master plan was held to be lawful and not unauthorized. The court found that the ban was necessary for planned development and did not violate any laws. (Paras 475-476). B) Building Bye-Laws - Deemed Sanction - Requirement for Notice - Delhi Development Act, 1947, Bye-law 6.7.4 - The court ruled that the appellant did not fulfill the requirements for deemed sanction as the necessary notice was not properly given. The D.D.A. had already communicated the need for clarifications, thus negating the claim for deemed sanction. (Paras 478-479). C) Interest on Payments - Nature of Interest Charged - Delhi Development Act, 1947 - The D.D.A. was justified in charging simple interest at 18% per annum on the instalments as per the revised agreement. The court clarified that this was not compound interest but simple interest on the principal amount. (Paras 474-475). D) Compounding Fee - Liability for Compounding Fee - Delhi Development Act, 1947 - The court held that the appellants were liable to pay the compounding fee as no building permit was obtained, despite the construction being completed under a stay order. (Paras 479). E) Interest on Compounding Fee - Charging of Interest - The court ruled that the D.D.A. was not entitled to charge interest on the compounding fee, modifying the High Court's order in this respect. (Paras 479).
Issue of Consideration
Whether the Delhi Development Authority was entitled to charge interest and compounding fees under the circumstances of the case.
Final Decision
The Supreme Court partly allowed the appeals, ruling that the D.D.A. was entitled to charge simple interest at 18% per annum on the instalments but not compound interest. The court upheld the legality of the construction ban and the requirement for compounding fees due to lack of a building permit, while ruling that no interest could be charged on the compounding fee. The directions given by the High Court were modified to take effect from the date of the Supreme Court's judgment.
Law Points
- Deemed sanction
- High rise construction ban
- Interest on delayed payments
- Compounding fee
- Building bye-laws compliance

