The dispute arose from the acquisition of land owned by the appellant, Nutakki Sesharatanam, by the Government of Andhra Pradesh for public purposes. A notification under Section 4(1) of the Land Acquisition Act, 1894 was published on February 9, 1976, but the substance of this notification was not published in the locality until April 2, 1978, which was beyond the mandatory 40-day period. The appellant initially consented to the acquisition provided he received lump-sum compensation, but later withdrew this consent before any award was made. The Single Judge of the High Court dismissed the appellant's writ petition, asserting that the consent precluded him from challenging the acquisition. This decision was upheld by the Division Bench of the High Court. The appellant then appealed to the Supreme Court, which found that the High Court erred in its judgment. The Supreme Court held that the appellant's consent constituted an offer that had not been accepted, and thus he was entitled to withdraw it. Furthermore, the Court ruled that the late publication of the notification's substance rendered the acquisition invalid under the Act. Consequently, the Supreme Court allowed the appeal, declared the acquisition invalid, and ordered the return of possession if it had been taken. The appeal was granted with costs throughout.
Headnote
A) Land Acquisition - Notification Publication - Mandatory Requirement - Land Acquisition Act, 1894, Section 4(1) - The substance of the notification must be published within 40 days; failure to do so renders the acquisition invalid. The court held that the acquisition was bad in law due to the late publication of the notification's substance, violating the mandatory requirement of the Act (Paras 116-118). B) Contract Law - Nature of Consent - Land Acquisition Act, 1894 - Consent as Offer - The appellant's consent to acquisition was merely an offer under the Contract Act, which could be withdrawn before acceptance. The court found that the appellant was entitled to withdraw his consent as no contract was formed until acceptance by the Land Acquisition Officer (Paras 115-117).
Issue of Consideration
Whether the acquisition of land was valid given the non-compliance with notification publication requirements and the nature of consent given by the appellant.
Final Decision
The Supreme Court allowed the appeal, declared the acquisition invalid due to non-compliance with the publication requirement, and ordered the return of possession if taken.
Law Points
- Land Acquisition
- Notification Publication
- Consent Withdrawal
- Contract Law