Case Note & Summary
The case involved appeals by a contractor against the Union of India regarding arbitration awards related to two contracts for construction work. The contractor was awarded contracts for constructing an aircraft hangar and roads, with disputes arising over delays and compensation claims. The contractor claimed amounts for escalation in materials and labor, loss of profit due to delays, and additional compensation for work done beyond the original contract period. The employer contested these claims, asserting that the contractor was responsible for the delays and that the contract prohibited claims for compensation arising from extensions of time. The Arbitrator ruled in favor of the contractor, awarding amounts for the disputed claims. However, the High Court found that the Arbitrator had exceeded his jurisdiction by making these awards, as they violated clause 11(C) of the contract, which barred compensation claims due to delays for which extensions were granted. The Supreme Court upheld the High Court's decision, affirming that the Arbitrator's awards were unsustainable and constituted legal misconduct. The court dismissed the appeals, stating that the contractor's claims were clearly prohibited by the terms of the contract, and the Arbitrator had acted beyond his authority. The parties were directed to bear their own costs.
Headnote
A) Arbitration - Jurisdiction of Arbitrator - Excess of Jurisdiction - General Conditions of Contract, 1989, Clause 11(C) - The Arbitrator exceeded his jurisdiction by awarding compensation for delays despite the clear prohibition in the contract against such claims arising from extensions of time granted. The court held that the contractor's claims were barred by clause 11(C) which prohibits compensation for delays when extensions are granted. (Paras 9-14).
Issue of Consideration
Whether the claims made by the contractor are unsustainable due to the prohibition in clause 11(C) of the contract and whether the Arbitrator committed legal misconduct.
Final Decision
The Supreme Court dismissed the appeals, affirming the High Court's finding that the Arbitrator exceeded his jurisdiction in awarding damages for delays, which were prohibited by clause 11(C) of the contract.
Law Points
- Arbitration
- Contract Law
- Jurisdiction
- Compensation Claims
- Extension of Time


