The dispute arose from the termination of a conductor's services by the U.P. State Road Transport Corporation (appellant) in 1975. The conductor, Sarada Prasad Misra (respondent), was initially appointed on a temporary basis in 1973 and his services were terminated on September 6, 1975, with one month's salary in lieu of notice. After a significant delay of seven years, he approached the Conciliation Officer under the U.P. Industrial Disputes Act, claiming illegal termination. The Labour Court ruled in his favor, ordering reinstatement and full back wages. The appellant challenged this decision in the High Court, which upheld the Labour Court's findings but modified the back wages to 50%. The Supreme Court, while acknowledging the delay in the workman's application, partly allowed the appeal, ruling that he was not entitled to back wages from 1975 to 1984 but could receive 50% back wages from the date of the award until reinstatement. The court emphasized that the payment of back wages is discretionary and must consider various factors, including the nature of employment and the length of service. The appeal was disposed of without costs.
Headnote
A) Employment Law - Termination of Services - Legal Validity of Termination - U.P. Industrial Disputes Act, 1947, Section 2A - The court held that the workman's termination was illegal as he had completed 240 days of service without retrenchment compensation. The Labour Court's award for reinstatement was upheld, but the entitlement to back wages was limited due to the delay in raising the dispute (Paras 1-6).
Issue of Consideration
Whether the termination of the workman's services was legal and the entitlement to back wages.
Final Decision
The Supreme Court partly allowed the appeal, ruling that the workman was not entitled to back wages from 1975 to 1984 but entitled to 50% back wages from the date of the award until reinstatement.
Law Points
- Industrial Disputes
- Temporary Employment
- Back Wages
- Delay and Laches