Case Note & Summary
The dispute arose from an arbitration award dated 29.9.1997 concerning civil construction work awarded to a contractor by the State of Rajasthan. The sole Arbitrator, S.S. Mathur, awarded a sum of Rs.6,68,058.16 with interest at 18% per annum. The State filed objections under Section 30 of the Arbitration Act, 1940, which were rejected by the District Judge, who made the award rule of the court. The contractor later sought rectification of the decree to include interest, which was granted at 12% per annum. The State challenged the validity of the arbitration clause, arguing that Clause 23 of the Agreement did not constitute an arbitration clause, citing several precedents. The court found that the State had participated in the arbitration proceedings without objection, thus waiving its right to contest the arbitrator's competence. The court also addressed the issue of interest, affirming the civil court's decision to award 12% interest as reasonable. The State's appeals against the High Court's decisions were dismissed, including a revision petition that was barred by limitation due to vague claims regarding a strike. Ultimately, all appeals by the State and the contractor's application were dismissed, with parties bearing their own costs.
Headnote
A) Arbitration Law - Validity of Arbitration Clause - Clause 23 of the Agreement not constituting an arbitration clause - Arbitration Act, 1940, Section 30 - The court held that the clause did not provide for arbitration as per precedents, thus the award was challenged on this ground. However, the State's participation in the proceedings estopped it from raising objections later. (Paras 1-10). B) Interest on Awarded Sum - Rate of Future Interest - Arbitration Act, 1940, Section 29 - The court upheld the civil court's decision to award interest at 12% per annum, finding it reasonable and not interfering with the arbitrator's award of 18% interest. (Paras 11-20). C) Limitation in Civil Appeals - Dismissal of Revision Petition - Limitation Act - The High Court dismissed the State's revision petition as barred by limitation, finding no sufficient cause for delay due to vague claims of a strike. (Paras 21-30).
Issue of Consideration
Whether the arbitration award and decree were valid given the nature of the arbitration clause and the objections raised by the State.
Final Decision
The Supreme Court dismissed all appeals by the State and the contractor's application, affirming the decisions of the lower courts regarding the arbitration award and interest rates.
Law Points
- Arbitration proceedings
- Interest on awarded sum
- Substitution of arbitrator
- Waiver and estoppel
- Limitation in civil appeals



