Case Note & Summary
The dispute arose from an agreement dated 23.10.1992 between the appellant and respondent No. 1 concerning a Technology Upgrade Project, which included an arbitration clause. Following disputes, respondent No. 1 invoked the arbitration clause on 16.5.2002, prompting the appellant to refuse to appoint an arbitrator, claiming non-compliance with the arbitration rules. Respondent No. 1 then approached the Chief Justice of the High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator. The appellant contested this, asserting that the arbitration clause had not been properly invoked. The designated Judge of the High Court ruled that the arbitration agreement allowed for the appointment of arbitrators by the parties without strict adherence to the Indian Council of Arbitration's rules. The appellant subsequently challenged this decision in the Supreme Court, arguing that the appointment process was flawed. The Supreme Court analyzed the arbitration agreement and concluded that the parties retained the right to appoint their arbitrators, affirming the designated Judge's decision and dismissing the appeal. The court directed the Arbitral Tribunal to proceed without delay and issue its award within nine months.
Headnote
A) Arbitration Law - Appointment of Arbitrators - Validity of Appointment - Arbitration and Conciliation Act, 1996, Section 11(6) - The court held that the arbitration agreement allowed parties to appoint their own arbitrators and did not mandate adherence to the Rules of the Indian Council of Arbitration for such appointments. The designated Judge's interpretation was affirmed, allowing the constituted Arbitral Tribunal to proceed with arbitration (Paras 4-9).
Issue of Consideration
Whether the arbitration clause was properly invoked and whether the appointment of arbitrators was valid under the arbitration agreement.
Final Decision
The Supreme Court dismissed the appeal, affirming the decision of the designated Judge and allowing the Arbitral Tribunal to proceed with arbitration. The court directed the Tribunal to issue its award within nine months.
Law Points
- Arbitration agreement interpretation
- appointment of arbitrators
- arbitration clause compliance
- Indian Arbitration Act
- 1940
- Arbitration and Conciliation Act
- 1996



