Case Note & Summary
The dispute arose from a land acquisition matter where the Land and Building Department and Land Acquisition Collector appealed against a High Court judgment that declared the acquisition of land deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The High Court had allowed a writ petition, relying on the precedent set in Pune Municipal Corporation v. Harakchand Misirimal Solanki, which held that non-payment of compensation led to lapse, despite the appellants' claim that possession of the land was taken on 28.03.2007. The core legal issue was whether the High Court correctly applied Section 24(2) to deem the acquisition lapsed, particularly in light of the subsequent overruling of the Pune Municipal Corporation decision by the Constitution Bench in Indore Development Authority v. Manoharlal. The appellants argued that possession had been taken, which should preclude lapse under the corrected interpretation of Section 24(2). The Supreme Court analyzed the Constitution Bench's ruling, which clarified that for a deemed lapse under Section 24(2), both possession must not have been taken and compensation must not have been paid; the word 'or' in the provision should be read as 'nor' or 'and'. Since the appellants asserted possession was taken in 2007, the Court found that even if compensation was unpaid, no lapse occurred. The Court held that the High Court's reliance on the overruled Pune Municipal Corporation case rendered its judgment unsustainable. Consequently, the Supreme Court allowed the appeal, quashed the High Court's order, and set aside the declaration of lapse, with no costs awarded.
Headnote
A) Land Acquisition Law - Deemed Lapse of Proceedings - Section 24(2) Interpretation - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Section 24(2) - High Court allowed writ petition declaring acquisition lapsed under Section 24(2) due to non-payment of compensation, relying on overruled Pune Municipal Corporation case - Supreme Court applied Indore Development Authority Constitution Bench ruling that lapse requires both possession not taken and compensation not paid, and since possession was taken on 28.03.2007, no lapse occurred - Held that impugned judgment unsustainable and quashed, with no deemed lapse under Section 24(2) (Paras 1-4). B) Land Acquisition Law - Precedent Overruling - Binding Authority - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - High Court relied on Pune Municipal Corporation decision which was overruled by Indore Development Authority Constitution Bench - Supreme Court noted that Pune Municipal Corporation and following decisions were overruled, making them not good law - Held that application of overruled precedent rendered High Court judgment erroneous (Paras 2-3). C) Land Acquisition Law - Possession and Compensation - Conjunctive Requirement - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Section 24(2) - Constitution Bench interpreted 'or' in Section 24(2) as 'nor' or 'and', meaning lapse requires both possession not taken and compensation not paid - Since appellant claimed possession taken on 28.03.2007, even if compensation not paid, no lapse under Section 24(2) - Held that acquisition proceedings did not lapse as possession was taken (Paras 3-4).
Issue of Consideration
Whether the High Court correctly declared the land acquisition as deemed to have lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, based on non-payment of compensation, despite possession having been taken
Final Decision
Supreme Court allowed the appeal, quashed and set aside the impugned High Court judgment and order, declared no deemed lapse under Section 24(2) of the 2013 Act, with no costs
Law Points
- Interpretation of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition
- Rehabilitation and Resettlement Act
- 2013
- deemed lapse of land acquisition proceedings
- overruling of Pune Municipal Corporation precedent
- application of Indore Development Authority Constitution Bench decision
- possession and compensation requirements for lapse





