Case Note & Summary
The case involved two appeals arising from a judgment by the High Court of Kerala concerning an arbitration award related to a contract for road work awarded to M/s. Som Datt Builders Ltd. by the State of Kerala. The contractor was unable to complete the work within the stipulated time, leading to claims for additional costs due to delays not attributable to them. An arbitral tribunal was constituted, which awarded the contractor various sums for their claims. The State of Kerala challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, arguing that it was not a reasoned award. The District Judge dismissed the petition, but the High Court partially allowed the appeal, setting aside the award for claims 1 and 4B due to lack of supporting reasons. Both parties appealed to the Supreme Court, with the contractor contesting the setting aside of claims 1 and 4B, while the State sought to challenge claims 5 and 6. The Supreme Court found that the arbitral tribunal did not provide adequate reasons for its decisions, which is a requirement under Section 31(3) of the Act. The Court held that while the High Court was correct in its observation, it should have remitted the matter back to the tribunal for the necessary reasons. The Supreme Court set aside the High Court's judgment and restored the petition for fresh hearing, directing the tribunal to provide reasons for claims 1 and 4B before proceeding with the objections (Paras 1-28).
Headnote
A) Arbitration - Requirement of Reasons - Obligation to Provide Reasons for Award - Arbitration and Conciliation Act, 1996, Sections 31(3), 34 - The arbitral tribunal failed to provide reasons for its award on claims 1 and 4B, violating the statutory requirement. The High Court's decision to set aside the award was justified, but it should have remitted the matter back to the tribunal for reasons as per Section 34(4) (Paras 21-25).
Issue of Consideration
Whether the arbitral tribunal provided sufficient reasons for its award concerning claims made by the contractor.
Final Decision
The Supreme Court set aside the High Court's judgment and restored the petition for fresh hearing, directing the arbitral tribunal to provide reasons for claims 1 and 4B before proceeding with the objections.
Law Points
- Arbitration
- Reasoned Award
- Section 34
- Section 31
- Section 28
- Section 67
- UNCITRAL Model Law


