Supreme Court Upholds Rajasthan Electricity Regulatory Commission's Open Access Regulations in Challenge by Industrial Consumers. The Court held that the RERC has jurisdiction to regulate both intra-state and inter-state open access, and the restrictions imposed are reasonable and within the statutory framework of the Electricity Act, 2003.

  • 629
Judgement Image
Font size:
Print

Case Note & Summary

The present appeals challenge two separate orders of the Rajasthan High Court upholding the validity of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016. The appellants, industrial consumers including Hindustan Zinc Limited, are engaged in mining and smelting operations with substantial power requirements. They operate captive power plants (CPPs) and also have agreements with distribution licensees for contracted demand. Prior to 2016, they could simultaneously draw power from open access and contracted demand without reduction. The 2016 Regulations introduced limitations: if a consumer opts for open access, the contracted demand is reduced by the quantum scheduled through open access, and penalties are imposed for overdrawal or under-drawal. The appellants challenged these regulations as arbitrary, unreasonable, and contrary to the Electricity Act, 2003. The Jodhpur Bench of the High Court upheld the regulations, holding that the Commission is empowered to regulate open access for grid stability. The Jaipur Bench similarly upheld the regulations, finding the challenge covered by the Jodhpur judgment. The Supreme Court considered five issues: whether RERC has jurisdiction to regulate inter-state open access; whether penalties for deviation are unreasonable; whether Regulation 26(7) requiring 24-hour advance notice is ultra vires; whether Regulation 21 is discriminatory; and whether the right to open access is foreclosed. The Court heard arguments from both sides. The appellants contended that RERC lacked jurisdiction over inter-state open access, that the penalties and conditions were excessive, and that the regulations discouraged captive power generation. The Court, after hearing the parties, dismissed the appeals, upholding the High Court's decisions. The Court held that RERC has jurisdiction to regulate inter-state open access as the regulations apply to consumers within the state. The penalties and conditions were found to be reasonable measures to ensure grid stability and prevent gaming, and not violative of the right to open access under Section 42 of the Act. The Court concluded that the regulations are within the statutory framework and do not foreclose open access.

Headnote

A) Electricity Law - Open Access - Jurisdiction of State Commission - Inter-State Open Access - Electricity Act, 2003, Sections 42, 181 - The Court held that the RERC has jurisdiction to regulate inter-state open access as the regulations apply to consumers within the state, and the conditions imposed are ancillary to intra-state regulation. The challenge to jurisdiction was rejected. (Paras 11, 14)

B) Electricity Law - Open Access - Reasonable Restrictions - Penalties for Deviation - Electricity Act, 2003, Section 42 - The Court held that the imposition of penalties for variations in drawal from contracted demand is a reasonable restriction to ensure grid stability and prevent gaming, and does not violate the right to open access. (Paras 11, 13)

C) Electricity Law - Open Access - Scheduling Requirements - Advance Notice - Electricity Act, 2003, Section 42 - The Court held that Regulation 26(7) requiring 24-hour advance notice is not ultra vires as it is a procedural requirement to ensure efficient scheduling and does not foreclose open access. (Paras 11, 14)

D) Electricity Law - Captive Power Plants - Discrimination - Regulation 21 - Electricity Act, 2003, Section 42 - The Court held that Regulation 21 is not arbitrary or discriminatory as it applies uniformly to all consumers and is aimed at balancing interests of consumers and distribution licensees. (Paras 11, 13)

E) Electricity Law - Open Access - Foreclosure of Right - Electricity Act, 2003, Section 42 - The Court held that the Regulations of 2016 do not foreclose the right to open access but impose reasonable conditions to ensure grid stability and efficient load distribution. (Paras 11, 13)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Rajasthan Electricity Regulatory Commission (RERC) has jurisdiction to regulate inter-state open access under the Electricity Act, 2003; whether the imposition of penalties for variations in drawal from contracted demand amounts to an unreasonable restriction on the right to open access under Section 42 of the Act; whether Regulation 26(7) requiring advance notice of 24 hours is ultra vires; whether Regulation 21 is arbitrary and discriminatory against captive power plants; and whether the appellants' right to open access is foreclosed by the Regulations of 2016.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeals, upholding the validity of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016. The Court held that the RERC has jurisdiction to regulate inter-state open access, and the restrictions imposed are reasonable and within the statutory framework of the Electricity Act, 2003.

Law Points

  • Open access regulation
  • jurisdiction of state electricity regulatory commission
  • inter-state open access
  • captive power plants
  • contracted demand
  • penalties for deviation
  • scheduling requirements
  • reasonableness of regulatory conditions
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (SC) (4) 6

Civil Appeal Nos. 7964-7966 of 2019

2025-04-01

Vikram Nath, J.

RAMAYANA ISPAT PVT. LTD. AND ANR.

STATE OF RAJASTHAN & ORS.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to the validity of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016, by industrial consumers.

Remedy Sought

The appellants sought to strike down the Regulations of 2016 as arbitrary, unreasonable, and ultra vires the Electricity Act, 2003.

Filing Reason

The appellants contended that the Regulations of 2016 imposed unreasonable restrictions on the exercise of open access, including reduction of contracted demand, penalties for deviations, and advance scheduling requirements, which were contrary to the statutory scheme.

Previous Decisions

The Jodhpur Bench of the Rajasthan High Court upheld the validity of the Regulations on 29.08.2016, and the Jaipur Bench upheld them on 06.09.2016, holding that the challenge was covered by the Jodhpur judgment.

Issues

Whether the RERC has jurisdiction to regulate inter-state open access under the Electricity Act, 2003? Whether the imposition of penalties for variations in drawal from contracted demand amounts to an unreasonable restriction on the right to open access under Section 42 of the Act? Whether Regulation 26(7) requiring advance notice of 24 hours is ultra vires? Whether Regulation 21 is arbitrary and discriminatory against captive power plants? Whether the appellants' right to open access is foreclosed by the Regulations of 2016?

Submissions/Arguments

The appellants argued that the RERC lacked jurisdiction to regulate inter-state open access, which falls within the exclusive domain of the CERC. The appellants contended that the penalties for deviations and reduction of contracted demand were unreasonable and discriminatory, violating the right to open access under Section 42. The appellants submitted that Regulation 26(7) requiring 24-hour advance notice created an artificial barrier to open access. The appellants argued that Regulation 21 arbitrarily distinguished between CPPs and state distribution companies, discouraging captive power generation.

Ratio Decidendi

The RERC has jurisdiction to regulate inter-state open access as the regulations apply to consumers within the state. The imposition of penalties for deviations and reduction of contracted demand are reasonable restrictions to ensure grid stability and prevent gaming, and do not violate the right to open access under Section 42 of the Electricity Act, 2003. The conditions such as advance scheduling are procedural and not ultra vires.

Judgment Excerpts

The primary grievance of the writ petitioners, appellants herein, before the High Court, and now the appellants before this Court, relates to the restrictions and conditions imposed by the Regulations of 2016 on the exercise of open access for captive power plants and other large consumers of electricity. The key change introduced by the Regulations of 2016 was the imposition of limitations on the simultaneous drawal of power through open access and contracted demand from the distribution licensee. The Jodhpur Bench in the judgment dated 29.08.2016 upheld the validity of the Regulations of 2016, holding that the Commission was empowered to regulate open access to ensure grid stability and efficient load distribution.

Procedural History

The appellants filed writ petitions before the Rajasthan High Court challenging the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016. The Jodhpur Bench dismissed the petition on 29.08.2016, and the Jaipur Bench dismissed on 06.09.2016, holding the regulations valid. The appellants then appealed to the Supreme Court, which heard the appeals and dismissed them.

Acts & Sections

  • Electricity Act, 2003: 42, 181
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appeal and Discharges Appellant in Abetment of Suicide Case — No Active Instigation or Intent to Aid Suicide Found. Loan Recovery Harassment Without Proximate Link to Suicide Does Not Attract Section 306 IPC.
Related Judgement
Supreme Court Supreme Court Seeks Resolution of Dispute Over Unauthorized Colony in Faridabad Through Arbitration and Committee Formation. The Court directs parties to submit responses on land extent, layout, and development charges to facilitate completion of the...