Case Note & Summary
The present appeals challenge two separate orders of the Rajasthan High Court upholding the validity of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016. The appellants, industrial consumers including Hindustan Zinc Limited, are engaged in mining and smelting operations with substantial power requirements. They operate captive power plants (CPPs) and also have agreements with distribution licensees for contracted demand. Prior to 2016, they could simultaneously draw power from open access and contracted demand without reduction. The 2016 Regulations introduced limitations: if a consumer opts for open access, the contracted demand is reduced by the quantum scheduled through open access, and penalties are imposed for overdrawal or under-drawal. The appellants challenged these regulations as arbitrary, unreasonable, and contrary to the Electricity Act, 2003. The Jodhpur Bench of the High Court upheld the regulations, holding that the Commission is empowered to regulate open access for grid stability. The Jaipur Bench similarly upheld the regulations, finding the challenge covered by the Jodhpur judgment. The Supreme Court considered five issues: whether RERC has jurisdiction to regulate inter-state open access; whether penalties for deviation are unreasonable; whether Regulation 26(7) requiring 24-hour advance notice is ultra vires; whether Regulation 21 is discriminatory; and whether the right to open access is foreclosed. The Court heard arguments from both sides. The appellants contended that RERC lacked jurisdiction over inter-state open access, that the penalties and conditions were excessive, and that the regulations discouraged captive power generation. The Court, after hearing the parties, dismissed the appeals, upholding the High Court's decisions. The Court held that RERC has jurisdiction to regulate inter-state open access as the regulations apply to consumers within the state. The penalties and conditions were found to be reasonable measures to ensure grid stability and prevent gaming, and not violative of the right to open access under Section 42 of the Act. The Court concluded that the regulations are within the statutory framework and do not foreclose open access.
Headnote
A) Electricity Law - Open Access - Jurisdiction of State Commission - Inter-State Open Access - Electricity Act, 2003, Sections 42, 181 - The Court held that the RERC has jurisdiction to regulate inter-state open access as the regulations apply to consumers within the state, and the conditions imposed are ancillary to intra-state regulation. The challenge to jurisdiction was rejected. (Paras 11, 14) B) Electricity Law - Open Access - Reasonable Restrictions - Penalties for Deviation - Electricity Act, 2003, Section 42 - The Court held that the imposition of penalties for variations in drawal from contracted demand is a reasonable restriction to ensure grid stability and prevent gaming, and does not violate the right to open access. (Paras 11, 13) C) Electricity Law - Open Access - Scheduling Requirements - Advance Notice - Electricity Act, 2003, Section 42 - The Court held that Regulation 26(7) requiring 24-hour advance notice is not ultra vires as it is a procedural requirement to ensure efficient scheduling and does not foreclose open access. (Paras 11, 14) D) Electricity Law - Captive Power Plants - Discrimination - Regulation 21 - Electricity Act, 2003, Section 42 - The Court held that Regulation 21 is not arbitrary or discriminatory as it applies uniformly to all consumers and is aimed at balancing interests of consumers and distribution licensees. (Paras 11, 13) E) Electricity Law - Open Access - Foreclosure of Right - Electricity Act, 2003, Section 42 - The Court held that the Regulations of 2016 do not foreclose the right to open access but impose reasonable conditions to ensure grid stability and efficient load distribution. (Paras 11, 13)
Issue of Consideration
Whether the Rajasthan Electricity Regulatory Commission (RERC) has jurisdiction to regulate inter-state open access under the Electricity Act, 2003; whether the imposition of penalties for variations in drawal from contracted demand amounts to an unreasonable restriction on the right to open access under Section 42 of the Act; whether Regulation 26(7) requiring advance notice of 24 hours is ultra vires; whether Regulation 21 is arbitrary and discriminatory against captive power plants; and whether the appellants' right to open access is foreclosed by the Regulations of 2016.
Final Decision
The Supreme Court dismissed the appeals, upholding the validity of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016. The Court held that the RERC has jurisdiction to regulate inter-state open access, and the restrictions imposed are reasonable and within the statutory framework of the Electricity Act, 2003.
Law Points
- Open access regulation
- jurisdiction of state electricity regulatory commission
- inter-state open access
- captive power plants
- contracted demand
- penalties for deviation
- scheduling requirements
- reasonableness of regulatory conditions



