Supreme Court Partially Allows Auroville Foundation's Appeal Against NGT Directions on Environmental Clearance and Master Plan Implementation. NGT's direction to prepare township plan and obtain EC before further construction held to be outside its jurisdiction under the National Green Tribunal Act, 2010.

  • 607
Judgement Image
Font size:
Print

Case Note & Summary

The case involves appeals by The Auroville Foundation against the final judgment and interim order of the National Green Tribunal (NGT), Chennai, in O.A. No. 239/2021 and M.A. No. 6/2022. The NGT had directed the Foundation to prepare a proper township plan for the Auroville project area (either 778 Ha or 1963 Ha) and obtain Environmental Clearance (EC) under Item 8(b) of the EIA Notification, 2006 before proceeding with further construction. Additionally, the NGT permitted the completion of the crown road subject to conditions to minimize tree cutting and protect water bodies, and appointed a Joint Committee for inspection. The Auroville Foundation challenged these directions, arguing that the NGT exceeded its jurisdiction under the NGT Act, 2010, as the preparation of a township plan and requirement of EC were matters within the domain of the Foundation under the Auroville Foundation Act, 1988, and the Master Plan already approved in 2001 and notified in 2010. The Supreme Court, by interim order dated 13.12.2023, stayed the direction in Para 125(i) of the NGT judgment (requiring preparation of township plan and EC) on the prima facie view that it was outside the Tribunal's jurisdiction. The Court noted that the NGT's role is limited to adjudicating disputes relating to environmental issues and cannot assume planning functions. The appeals were disposed of with the observation that the NGT's directions regarding the crown road and tree cutting were not interfered with, but the direction to prepare a township plan and obtain EC was set aside as being ultra vires the NGT Act.

Headnote

A) Environmental Law - Jurisdiction of National Green Tribunal - Environmental Clearance - NGT Act, 2010, Sections 14, 15, 20 - The Tribunal directed the Auroville Foundation to prepare a township plan and obtain Environmental Clearance under Item 8(b) of EIA Notification, 2006 before further construction. The Supreme Court held that such directions were outside the jurisdiction of the Tribunal as they amounted to assuming planning and regulatory functions not conferred by the NGT Act. The Tribunal cannot substitute its own planning decisions for those of statutory authorities under the Auroville Foundation Act, 1988. (Paras 1-2, 5-6)

B) Environmental Law - Interim Directions - Tree Cutting and Crown Road Construction - NGT Act, 2010 - The Tribunal permitted completion of the crown road subject to conditions to minimize tree cutting and protect water bodies. The Supreme Court did not interfere with these interim directions, allowing the Joint Committee to proceed. (Paras 1, 5-6)

C) Administrative Law - Master Plan - Auroville Foundation Act, 1988, Sections 17(e), 19(2)(c) - The Master Plan for Auroville was approved by the Governing Board and Residents' Assembly in 1999, further approved by TCPO in 2001, and notified in 2010. The Tribunal's direction to prepare a new township plan was held to be beyond its jurisdiction as it encroached upon the statutory functions of the Foundation. (Paras 3-4)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the National Green Tribunal had the jurisdiction to direct the Auroville Foundation to prepare a township plan and obtain Environmental Clearance before proceeding with further construction, and whether such directions were within the scope of the NGT Act, 2010.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court, by interim order dated 13.12.2023, stayed the direction in Para 125(i) of the NGT judgment (requiring preparation of township plan and EC) on the prima facie view that it was outside the Tribunal's jurisdiction. The appeals were disposed of with the observation that the NGT's directions regarding the crown road and tree cutting were not interfered with, but the direction to prepare a township plan and obtain EC was set aside as being ultra vires the NGT Act.

Law Points

  • Jurisdiction of National Green Tribunal
  • Environmental Clearance under EIA Notification 2006
  • Master Plan under Auroville Foundation Act 1988
  • Doctrine of ultra vires
  • Separation of powers
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (SC) (03) 292

Civil Appeal No(s). 5781-5782 of 2022

2025-03-17

Bela M. Trivedi

2025 INSC 347

The Auroville Foundation

Navroz Kersasp Mody & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeals against final judgment and interim order of National Green Tribunal, Chennai, in environmental application concerning Auroville township development.

Remedy Sought

The appellant (Auroville Foundation) sought setting aside of NGT directions to prepare a township plan and obtain Environmental Clearance before further construction, and to allow completion of crown road without such conditions.

Filing Reason

The NGT directed the Foundation to prepare a township plan and obtain EC, which the Foundation contended was beyond NGT's jurisdiction and contrary to the existing approved Master Plan under the Auroville Foundation Act.

Previous Decisions

NGT final judgment dated 28.04.2022 in O.A. No. 239/2021 allowed the application in part, directing preparation of township plan and EC, and permitting crown road construction subject to conditions. NGT interim order dated 27.07.2022 in M.A. No. 6/2022 directed the Joint Committee to file a report.

Issues

Whether the National Green Tribunal had jurisdiction to direct the Auroville Foundation to prepare a township plan and obtain Environmental Clearance before further construction. Whether the NGT's directions regarding the crown road and tree cutting were valid.

Submissions/Arguments

The appellant argued that the NGT exceeded its jurisdiction under the NGT Act, 2010, as the preparation of a township plan and requirement of EC are matters within the domain of the Foundation under the Auroville Foundation Act, 1988, and the Master Plan already approved. The respondents supported the NGT's directions, arguing that environmental protection required such measures.

Ratio Decidendi

The National Green Tribunal cannot assume planning and regulatory functions that are statutorily vested in other authorities under specific Acts. The direction to prepare a township plan and obtain Environmental Clearance was outside the jurisdiction of the NGT under the NGT Act, 2010, as it encroached upon the powers of the Auroville Foundation under the Auroville Foundation Act, 1988.

Judgment Excerpts

Having regard to the said prayer which was sought by the Respondent No.1 (original applicant) and having regard to the final directions given by the Tribunal in the impugned order, we are of the prima facie opinion that the direction contained in Para 125(i) being outside the jurisdiction of the Tribunal, the same is required to be stayed till further orders, and is ordered accordingly. The Tribunal directed the 1st Respondent to prepare a proper township plan... and then apply for Environmental Clearance (EC) as it will fall under Item 8 (b) of the EIA Notification, 2006 as amended from time to time. Till then they are directed not to proceed with further construction in the project area.

Procedural History

The National Green Tribunal, Chennai, passed final judgment on 28.04.2022 in O.A. No. 239/2021, allowing the application in part with directions. An interim order was passed on 27.07.2022 in M.A. No. 6/2022. The Auroville Foundation filed Civil Appeal No(s). 5781-5782 of 2022 before the Supreme Court. The Supreme Court passed an interim order on 13.12.2023 staying the direction in Para 125(i) of the NGT judgment.

Acts & Sections

  • National Green Tribunal Act, 2010: Sections 14, 15, 20
  • Auroville Foundation Act, 1988: Sections 11(3), 17(e), 19(2)(c)
  • Environment Impact Assessment Notification, 2006: Item 8(b)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Petitioners in National Pension Scheme Salary Withholding Case; Teachers' Salaries Cannot Be Withheld for Refusing NPS Switch. Withholding Salaries of Government School Teachers for Not Opening NPS Accounts Violates Right to ...
Related Judgement
High Court Bombay High Court Dismisses Step-Mother's Maintenance Revision Due to Invalid Marriage and Self-Created Incapacity. Step-mother's claim for maintenance under Section 125 CrPC rejected as her marriage to father was void under Sections 5 and 11 of Hind...