Case Note & Summary
The Petitioner, Heritage Lifestyles & Developers Pvt. Ltd., a developer, filed an appeal under Section 37(2)(b) of the Arbitration and Conciliation Act, 1996, challenging an order dated October 14, 2024, passed by a Learned Arbitral Tribunal refusing to grant interim relief under Section 17 of the Act. The dispute arose from a Development Agreement dated March 19, 2014, between Heritage and the Respondent, Madhugiri Co-operative Housing Society Ltd., for redevelopment of the society's buildings. The DA provided for sharing of additional FSI/TDR in a 54:46 ratio. A Supplemental Development Agreement was also executed on the same day but was not registered. Over time, the project stalled, and the society terminated the DA in August 2022. Heritage made revised proposals, including one on March 24, 2023, which the society initially approved but later sought clarifications regarding area entitlements, particularly from road setback area. Heritage filed a Section 17 application seeking interim relief to restrain the society from terminating the agreements and to allow Heritage to proceed with redevelopment. The Arbitral Tribunal refused the relief, holding that no prima facie case was made out as the terms of the alleged concluded contract were unclear. On appeal, the High Court upheld the Tribunal's decision, finding that the acceptance of the March 24, 2023 proposal was conditional, the material terms were not crystallized, and the SDA was unregistered. The court also noted that the balance of convenience did not favor Heritage as the society had not violated the DA, and irreparable injury was not established. The appeal was dismissed.
Headnote
A) Arbitration - Interim Relief under Section 17 - Prima Facie Case - The court examined whether the Petitioner had made out a prima facie case for grant of interim injunction to restrain the Respondent from terminating the Development Agreement and related documents. The court held that the terms of the alleged concluded contract were unclear, especially regarding the sharing of additional FSI/TDR from road setback area, and the Supplemental Development Agreement was unregistered, thus no prima facie case was established (Paras 1-37). B) Contract Law - Formation of Contract - Offer and Acceptance - The court considered whether the exchange of emails and letters between the parties constituted a concluded contract. It held that the acceptance was conditional upon approval by the society and further clarifications, and the material terms regarding area entitlement were not crystallized, thus no binding contract was formed (Paras 20-30). C) Property Law - Development Agreement - Sharing of Additional FSI/TDR - The court analyzed the clauses of the Development Agreement and Supplemental Development Agreement regarding the sharing of additional FSI/TDR. It held that the 54:46 ratio applied only to additional FSI/TDR due to difference in actual plot area, and the road setback area was a separate entitlement that required further agreement between the parties (Paras 10-15).
Issue of Consideration
Whether the Learned Arbitral Tribunal erred in refusing to grant interim relief under Section 17 of the Arbitration and Conciliation Act, 1996, to the Petitioner/Developer, particularly in light of the alleged concluded contract based on the revised proposal dated March 24, 2023.
Final Decision
The High Court dismissed the appeal, upholding the order of the Learned Arbitral Tribunal refusing to grant interim relief under Section 17 of the Arbitration and Conciliation Act, 1996.
Law Points
- Section 37(2)(b) of Arbitration and Conciliation Act
- 1996
- Section 17 of Arbitration and Conciliation Act
- Prima Facie Case
- Balance of Convenience
- Irreparable Injury
- Unregistered Agreement
- Supplemental Agreement
- Development Agreement
- FSI
- TDR
- Road Setback Area
- 54:46 Ratio




