Bombay High Court Allows Writ Petition Challenging Rejection of Technical Bid in Railway Tender — Interpretation of 'Present Contract Value' Found Arbitrary and Irrational. The court held that the expression 'present contract value' in Clause 2.2.2.1(ii) of the RFP means the value of the present contract (Rs.696 crores) and not the qualifying contract value, and directed reconsideration of the petitioner's technical bid.

High Court: Bombay High Court In Favour of Accused
  • 708
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Konkan Railway Corporation Ltd., a public sector undertaking under the Ministry of Railways, challenged the rejection of its technical bid in a tender for construction works related to gauge conversion from Pachora-Jamner, with an estimated project cost of Rs.696,23,59,867.32. The respondent, Union of India, through the Chief Administrative Officer of Central Railways, had issued a Request for Proposal (RFP) in a two-packet system. The petitioner submitted its bid on 4 September 2024, but after five months, on 22 January 2025, the respondent rejected the bid as 'technically not eligible'. The petitioner filed a writ petition, and in compliance with an order for reconsideration, the respondent passed a speaking order on 27 January 2025, rejecting the bid on the ground that the petitioner had not received 75% of the amount in the qualifying contract, interpreting 'present contract value' in Clause 2.2.2.1(ii) as the value of the qualifying contract (Rs.17,500 crores) rather than the present contract value (Rs.696 crores). The petitioner argued that this interpretation was arbitrary and irrational, as it had received Rs.522.17 crores, which is 75% of the present contract value, and that the respondent had accepted similar bids in other tenders. The respondent contended that the petitioner, being a corporate entity, could not invoke Article 19, and that the interpretation was within the author's domain. The court, after considering submissions and relevant clauses, held that the interpretation by the respondent was arbitrary and irrational, as it disqualified a contractor with vast experience and offended common sense. The court allowed the petition, quashed the impugned order, and directed the respondent to consider the petitioner's technical bid afresh in accordance with the correct interpretation of Clause 2.2.2.1(ii).

Headnote

A) Constitutional Law - Article 14 - Arbitrary State Action - Tender Interpretation - A corporate entity, though not entitled to invoke Article 19 of the Constitution, can challenge state action under Article 14 if it is arbitrary or irrational. The court held that the interpretation of tender conditions by the respondent must be tested on the anvil of Article 14. (Paras 9-10)

B) Contract Law - Interpretation of Tender Documents - 'Present Contract Value' - Clause 2.2.2.1(ii) of RFP - The expression 'present contract value' in Clause 2.2.2.1(ii) means the value of the present contract (Rs.696 crores) and not the value of the qualifying contract (Rs.17,500 crores). The respondent's interpretation was held to be arbitrary and irrational, as it disqualified a contractor with vast experience and offended common sense. (Paras 7-8, 12-13)

C) Administrative Law - Judicial Review - Tender Matters - Scope - The court can interfere with the interpretation of tender conditions by the author if the interpretation is arbitrary, irrational, or perverse. The court relied on Galaxy Transport Agencies v. New J.K. Roadways and Mahalsa Services v. Directorate of Health Services to hold that the interpretation must be reasonable and not commercially absurd. (Paras 8, 11)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the interpretation of Clause 2.2.2.1(ii) of the RFP by the respondent, rejecting the petitioner's technical bid on the ground that the petitioner had not received 75% of the value of the qualifying contract (Rs.17,500 crores) instead of the present contract value (Rs.696 crores), is arbitrary and irrational.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the writ petition, quashed the impugned order dated 27 January 2025, and directed the respondent to consider the petitioner's technical bid afresh in accordance with the correct interpretation of Clause 2.2.2.1(ii) of the RFP, i.e., treating 'present contract value' as the value of the present contract (Rs.696 crores).

Law Points

  • Judicial review in tender matters
  • interpretation of tender documents
  • Article 14 of the Constitution of India
  • corporate entity not entitled to Article 19 but can invoke Article 14
  • principle against arbitrary and irrational interpretation by tender author
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (3) 130

Writ Petition (L) No.2694 of 2025

2025-03-13

Alok Aradhe, CJ., Bharati Dangre, J.

Mr. Gautam Ankad, Senior Advocate a/w. Mr. Chirag Sancheti, Mr. Asif Lampwala, Mr. Joshua D’Souza and Mr. Mutahhar Khan i/b. Bulwark Solicitors for the petitioner; Mr. Rajshekhar V. Govilkar, Senior Advocate a/w. Mr. N. R. Bubna and Ms. Shaba N. Khan for respondent

Konkan Railway Corporation Ltd.

Union of India

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging rejection of technical bid in a public tender for railway construction works.

Remedy Sought

The petitioner sought quashing of the order dated 27 January 2025 rejecting its technical bid and a direction to the respondent to reconsider the bid in accordance with the correct interpretation of the tender conditions.

Filing Reason

The petitioner's technical bid was rejected on the ground that it had not received 75% of the amount in the qualifying contract, interpreting 'present contract value' as the value of the qualifying contract (Rs.17,500 crores) instead of the present contract value (Rs.696 crores).

Previous Decisions

The petitioner had earlier filed Writ Petition (L) No.2475 of 2025 challenging the initial rejection dated 22 January 2025, and the court directed reconsideration with a speaking order. The respondent then passed the impugned order dated 27 January 2025.

Issues

Whether the interpretation of Clause 2.2.2.1(ii) of the RFP by the respondent, treating 'present contract value' as the qualifying contract value, is arbitrary and irrational. Whether the petitioner, being a corporate entity, can invoke Article 14 of the Constitution of India. Whether the court can interfere with the interpretation of tender conditions by the author.

Submissions/Arguments

Petitioner: The expression 'present contract value' in Clause 2.2.2.1(ii) means the value of the present contract (Rs.696 crores), and the petitioner has received 75% of that amount. The respondent's interpretation is arbitrary, irrational, and commercially absurd. The petitioner's bid was accepted in similar tenders by other railway zones. Respondent: The petitioner, being a corporate entity, cannot invoke Article 19. The expression 'present contract value' means the qualifying contract value (Rs.17,500 crores). The respondent is the author of the tender and its interpretation should be respected. The petitioner did not challenge similar rejections in four earlier tenders.

Ratio Decidendi

The interpretation of tender conditions by the author is subject to judicial review under Article 14 of the Constitution of India. If the interpretation is arbitrary, irrational, or perverse, the court can interfere. In this case, the respondent's interpretation of 'present contract value' in Clause 2.2.2.1(ii) as the qualifying contract value (Rs.17,500 crores) instead of the present contract value (Rs.696 crores) was held to be arbitrary and irrational, as it disqualified a contractor with vast experience and offended common sense.

Judgment Excerpts

The interpretation put-forth by the respondent at the tender conditions offends the common sense and is commercially absurd. The expression 'present contract value' used in Clause 2.2.2 (ii) means the value of present contract as is evident from the scope of tender.

Procedural History

The petitioner submitted its bid on 4 September 2024. On 22 January 2025, the respondent rejected the bid as 'technically not eligible'. The petitioner filed Writ Petition (L) No.2475 of 2025, and the court directed reconsideration with a speaking order. On 27 January 2025, the respondent passed the impugned order rejecting the bid. The petitioner then filed the present writ petition challenging that order.

Acts & Sections

  • Companies Act, 1956:
  • Constitution of India: Article 14, Article 19
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Writ Petition Challenging Rejection of Technical Bid in Railway Tender — Interpretation of 'Present Contract Value' Found Arbitrary and Irrational. The court held that the expression 'present contract value' in Clause 2.2.2...
Related Judgement
Supreme Court Supreme Court Allows Appeal in Property Dispute Over Will Interpretation and Gift Deed Validity. High Court Erred in Interfering with First Appellate Court's Factual Finding on Nature of Bequest Under Section 100 CPC and Wrongly Applied Section 14 Hi...