Case Note & Summary
The dispute arose from the acquisition of land under an award dated 25 February 2001, which the petitioners challenged under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The petitioners claimed that they had not received any compensation and that the state had not taken possession of their land, leading to the filing of the writ petition in 2015. The High Court initially allowed the petition, declaring the acquisition proceedings lapsed. However, the respondents, claiming allotment of the land, appealed to the Supreme Court, which remanded the case back to the High Court for fresh consideration in light of the Supreme Court's judgment in Indore Development Authority vs. Manoharlal. The petitioners argued that the state had failed to prove that possession was taken or compensation offered, while the state contended that the petition was barred by delay and laches. The court found that the petitioners had a fresh cause of action under Section 24(2) of the 2013 Act, as the Act came into force after the award was made. The court noted that the state had not provided sufficient evidence to support its claims regarding possession and compensation. Ultimately, the court rejected the state's objections and reiterated that the absence of a panchanama or credible evidence of possession meant that the petitioners' claims were valid. The court emphasized that the state must provide cogent evidence to establish that it had taken possession of the land. The matter was reserved for orders after hearing the arguments. The court's decision favored the petitioners, leading to the conclusion that the acquisition proceedings had lapsed.
Headnote
A) Land Acquisition - Lapsing of Acquisition - Non-Payment of Compensation - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Section 24(2) - The court held that the acquisition proceedings lapsed as neither compensation was paid nor possession taken, fulfilling the conditions under Section 24(2) of the 2013 Act. The petitioners were in continuous possession of the properties since the award was made. (Paras 3, 29-30).
Issue of Consideration
Whether the land acquisition proceedings lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 due to non-payment of compensation and non-taking of possession.
Final Decision
The court held that the acquisition proceedings lapsed as neither compensation was paid nor possession taken, fulfilling the conditions under Section 24(2) of the 2013 Act. The petitioners were in continuous possession of the properties since the award was made.
Law Points
- Land Acquisition
- Compensation
- Possession
- Lapsing of Acquisition
- Article 226
- Writ Jurisdiction



