Case Note & Summary
The appellant, National Agricultural Co-operative Marketing Federation of India Limited (NAFED), and the first respondent, Roj Enterprises (P) Limited (REPL), entered into two Tie-Up Agreements dated 24/03/2004 and 30/04/2004. Under these agreements, NAFED agreed to extend financial assistance to REPL to the extent of 80% of the value of stock procured by REPL, with NAFED procuring the balance 20%. Disputes arose between the parties, and NAFED invoked the arbitration clause on 17/03/2008. The sole arbitrator passed an award on 12/02/2019, dismissing NAFED's claim against REPL, holding the claim against respondents 2 and 3 as not maintainable, and allowing REPL's counterclaim, directing NAFED to pay Rs. 33,97,77,369/- with interest. NAFED challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before the District Judge-2, Pune, who dismissed the application on 22/04/2024. NAFED then appealed under Section 37(1)(c) of the Act. The main legal issues were whether the Tie-Up Agreements were loan/finance agreements or joint venture/partnership agreements, and whether the award of counterclaim and interest was proper. NAFED argued that the agreements were loan agreements, the arbitrator erred in treating them as joint venture, and the counterclaim was allowed without evidence. REPL contended that the scope of interference under Section 37 is limited, the arbitrator's interpretation was plausible, and the award was based on evidence. The Bombay High Court held that the learned District Judge had considered the award within the permissible limits of Section 34 and did not find any patent illegality or perversity. The court noted that the arbitrator's construction of the Tie-Up Agreements as joint venture/partnership was a plausible view based on the terms and conduct of the parties, and the award of interest was within the arbitrator's discretion under Section 31(7)(b). The court dismissed the appeal, upholding the impugned judgment and the arbitral award.
Headnote
A) Arbitration Law - Appeal under Section 37 - Scope of Interference - Section 37(1)(c) of the Arbitration and Conciliation Act, 1996 - The court hearing an appeal under Section 37 has limited jurisdiction and does not sit in appeal over the arbitral award; interference is permissible only if the award is in conflict with public policy of India or suffers from patent illegality, such as perversity or irrationality. (Paras 5-6) B) Arbitration Law - Construction of Contract - Tie-Up Agreement - Joint Venture vs. Loan - Sections 34, 37 of the Arbitration and Conciliation Act, 1996 - The arbitrator's interpretation of the Tie-Up Agreements as joint venture/partnership rather than loan/finance agreements was plausible based on the terms and conduct of parties; the court under Section 34 cannot substitute its own view if the arbitrator's view is a possible one. (Paras 7-9) C) Arbitration Law - Counterclaim - Award of Interest - Section 31(7)(b) of the Arbitration and Conciliation Act, 1996 - The arbitrator has discretion to award interest on the counterclaim, and such award is not interfered with unless it is patently illegal or perverse; the award of interest at 18% per annum was within the arbitrator's discretion. (Paras 10-11)
Issue of Consideration
Whether the learned District Judge erred in dismissing the Section 34 application without considering specific grounds raised by NAFED, and whether the arbitral award suffers from patent illegality or is in conflict with public policy of India.
Final Decision
The Bombay High Court dismissed the Commercial Arbitration Appeal, upholding the impugned judgment dated 22/04/2024 and the arbitral award dated 12/02/2019.
Law Points
- Scope of interference under Section 37 of Arbitration and Conciliation Act
- 1996 is limited
- similar to Section 34
- Patent illegality ground requires perversity or irrationality
- Construction of contract by arbitrator is final if plausible
- Award of interest under Section 31(7)(b) is discretionary.



