Case Note & Summary
The dispute arose from a construction contract for the Kharkhai Irrigation Project, where the appellant was tasked with completing the balance work of an earth dam. The work was initially scheduled to be completed by July 31, 1976, but was delayed until July 1978 due to design changes, leading the appellant to claim financial losses and additional payments for extra work and royalty refunds. After the respondents failed to address these claims, the appellant sought arbitration, which was granted by a court order in 1981. The arbitral tribunal ruled in favor of the appellant on several claims, including price escalation and royalty refunds. The respondents contested the arbitral award on grounds of limitation and the appropriateness of arbitration after the final bill was accepted. The Civil Judge upheld the appellant's claims, but the High Court later ruled that the appellant could not pursue arbitration due to the acceptance of the final bill. The Supreme Court, however, found that the High Court erred in its judgment, emphasizing that the arbitration clause allowed for claims to be raised even after the final bill acceptance, provided no explicit waiver was made. The Court upheld the Civil Judge's ruling and directed the respondents to pay the awarded amount, allowing the appellant to recover through court if necessary.
Headnote
A) Arbitration Law - Reference of Disputes - Validity of Arbitration Post Final Bill Acceptance - Arbitration Act, 1940, Sections 30, 33 - Court held that acceptance of the final bill does not preclude a party from raising further claims unless explicitly stated. The appellant was entitled to seek arbitration despite having received payment, as the arbitration clause allowed for disputes arising post-completion of work (Paras 8-9).
Issue of Consideration
Whether the disputes/claims raised by the appellant could have been referred for arbitration after the appellant had received payment after the preparation of the final bill, without raising any objections.
Final Decision
The Supreme Court set aside the High Court's judgment, upheld the Civil Judge's order, and directed the respondents to pay the awarded amount to the appellant, allowing recovery through court if necessary.
Law Points
- Arbitration
- Limitation
- Contractual Disputes
- Final Bill Acceptance
- Price Escalation
- Royalty Refund



