Case Note & Summary
The petitioner, M/s. K. K. Vidyut, a joint venture company, was awarded a contract by the respondents (Union of India and Central Railway officials) for railway infrastructure development. The petitioner submitted performance and mobilization bank guarantees, which were initially verified. Later, the respondents received information that the guarantees were forged and issued show-cause notices to the petitioner. Despite multiple opportunities, the petitioner failed to provide a substantive reply, citing the arrest of its director. The respondents terminated the contract on 30 October 2024. The petitioner challenged the termination and show-cause notices under Article 226, also seeking a declaration that the arbitration clause was void. The court heard arguments from both sides. The petitioner argued that the respondents failed to issue a mandatory notice to rectify defaults under Clause 62, that the 48-hour notice was violated, that substantial work was completed, and that extension of time and termination amounted to double jeopardy. The respondents contended that the petitioner was given ample opportunity but did not respond substantively, and that the allegations of forgery raised serious disputed questions of fact unsuitable for writ jurisdiction. The court held that the respondents complied with natural justice by issuing multiple notices and granting extensions. The court found that the petitioner's failure to provide a substantive reply justified termination. The court also held that the extension of time under Clause 17B and termination under Clause 62 are distinct remedies and do not constitute double jeopardy. The court concluded that the writ petition involved serious disputed questions of fact regarding the genuineness of bank guarantees, which cannot be adjudicated in writ proceedings. Accordingly, the court dismissed the petition, leaving the petitioner to seek alternative remedies such as arbitration or civil suit.
Headnote
A) Constitutional Law - Writ Jurisdiction - Article 226 of the Constitution of India - Disputed Questions of Fact - The court held that where serious disputed questions of fact exist regarding the genuineness of bank guarantees, the writ court should not entertain the petition and relegate the parties to alternative remedies such as arbitration or civil suit. (Paras 19-20) B) Contract Law - Termination of Contract - Clause 62 of General Conditions of Contract - Notice Requirement - The court found that the respondents issued multiple show-cause notices and granted adequate opportunities to the petitioner to respond, thus complying with the principles of natural justice. The petitioner failed to provide a substantive reply. (Paras 5-12) C) Contract Law - Double Jeopardy - Extension of Time and Termination - The court rejected the argument that extension of time under Clause 17B and termination under Clause 62 constitute double jeopardy, as they are distinct contractual remedies for different defaults. (Paras 16-17) D) Contract Law - Forged Bank Guarantees - Serious Allegations - The court noted that the allegation of submission of forged bank guarantees is a serious matter involving fraud, which cannot be adjudicated in writ proceedings without proper evidence. (Paras 19-20)
Issue of Consideration
Whether the termination of the contract by the respondents was arbitrary, illegal, and in violation of principles of natural justice, and whether the writ court should interfere with the termination notice.
Final Decision
The court dismissed the writ petition, holding that the respondents complied with principles of natural justice, and that the writ court is not the appropriate forum to adjudicate serious disputed questions of fact regarding the genuineness of bank guarantees. The petitioner is at liberty to avail alternative remedies.
Law Points
- Principles of natural justice
- Contractual termination
- Writ jurisdiction under Article 226
- Disputed questions of fact
- Clause 62 of General Conditions of Contract
- Double jeopardy
- Extension of time and termination



