Case Note & Summary
The dispute arose from a contract between the appellants and the respondent for works related to the Tehri Hydro Dam Project, executed on 29th March 1978, with completion on 31st December 1985. Following the completion, the respondent claimed unpaid amounts and sought arbitration due to the non-preparation of the final bill and the retention of security money. An arbitration award on 29th January 1996 granted the respondent Rs.10,17,461/- but left the claim for Rs.12.50 lakhs unresolved, suggesting amicable settlement or civil suit. The trial court upheld the award but erroneously decreed the Rs.12.50 lakhs claim. The High Court modified the decree, maintaining the Rs.10,17,461/- award but remanding the Rs.12.50 lakhs claim for arbitration. The appellants contended that the claims were previously adjudicated and that the trial court lacked authority to grant the Rs.12.50 lakhs claim. The respondent argued that the appellants participated in arbitration and could not challenge its jurisdiction. The court analyzed the contract clauses regarding interest, concluding that the explicit prohibition against interest rendered the award of pendente lite interest unjustified, while upholding post-award interest at 12% per annum. The appeal was partially allowed, modifying the High Court's order accordingly.
Headnote
A) Arbitration Law - Jurisdiction of Arbitrators - Authority to Adjudicate Claims - Arbitration Act, 1940, Section Not Mentioned - The court held that the claims of the respondent-contractor were validly referred to arbitration, and the trial court's decree regarding the claim of Rs.10,17,461/- was upheld, while the claim of Rs.12.50 lakhs was remanded for proper adjudication. Held that the earlier arbitration did not bar the subsequent claims (Paras 9-10). B) Contract Law - Interest on Amounts Due - Clauses of Contract - Arbitration Act, 1940, Section Not Mentioned - The court found that the contract clauses explicitly barred the grant of interest on delayed payments, thus the award of pendente lite interest was not justified. Held that the grant of interest for the post-award period was upheld at 12% per annum (Paras 17-18).
Issue of Consideration
Whether the High Court correctly modified the trial court's decree regarding the arbitration award and the entitlement to interest.
Final Decision
The Supreme Court partially allowed the appeal, modifying the High Court's order regarding the claims and interest. The court upheld the award of Rs.10,17,461/- and clarified that the claim for Rs.12.50 lakhs should not be adjudicated by the High Court's appointed arbitrator but left for determination according to the agreed procedure. The court also ruled that the grant of pendente lite interest was not justified due to the explicit prohibition in the contract, while upholding post-award interest at 12% per annum.
Law Points
- Arbitration
- Interest
- Contractual Clauses
- Jurisdiction of Arbitrators
- Modification of Awards



