Bombay High Court Grants Interim Stay on Personal Guarantee Enforcement in CDR Failure Case — Deed of Guarantee Held Not Enforceable Due to Conditional Nature and Subsequent Termination Events. The court found that the guarantee was conditional upon CDR sanction and automatically terminated upon CDR failure and the guarantor's resignation, making it unenforceable against the personal guarantor.

High Court: Bombay High Court In Favour of Accused
  • 405
Judgement Image
Font size:
Print

Case Note & Summary

The Plaintiff, Deepen Arun Parekh, filed a suit seeking a declaration that the Deed of Guarantee dated 10 April 2014 executed by him in favour of the Defendant banks and financial institutions is not valid and binding, and alternatively, that it has ceased to have effect and stands automatically terminated. The Plaintiff also sought interim relief restraining the Defendants from acting upon the Deed of Guarantee. The Plaintiff is the brother of late Amitabh Arun Parekh, who was the Chairman and Managing Director of Parekh Aluminex Limited (the Company). After Amitabh's sudden demise in January 2013, the Company owed a liability of Rs.2762.09 Crores to a consortium of lenders led by Indian Overseas Bank (Defendant No.1). The lenders pressured the family to take over management and provide personal guarantees as a pre-requisite for a Corporate Debt Restructuring (CDR) scheme. The Plaintiff was appointed as an independent and non-executive Director on 11 September 2013, with an express understanding that he would not be liable for prior acts of the Company. On 10 April 2014, the Plaintiff executed a Deed of Guarantee, which categorically stated that it was provided to comply with CDR conditions. The CDR package failed, and the CDR Cell informed the Defendants on 23 March 2016 that the Company stood exited from the CDR mechanism as a failure. The Plaintiff resigned on 28 April 2016, which was accepted. Despite this, many Defendants impleaded the Plaintiff in recovery proceedings as a personal guarantor. The Plaintiff contended that the Deed of Guarantee never came into effect as it was conditional upon CDR sanction, and alternatively, it ceased to operate under Clause 12 due to events such as his resignation, CDR failure, and lenders walking out. The Defendants opposed the suit on grounds of limitation, bar of jurisdiction under SARFAESI Act, RDB Act, and IBC, and that the Plaintiff should have raised his grievances before the DRT. The Court, after hearing extensive arguments, found that the Plaintiff had made out a strong prima facie case that the Deed of Guarantee was conditional and never became effective or stood terminated. The balance of convenience was in favour of granting interim relief as the Defendants could still proceed against the Company and other guarantors, and the Plaintiff would suffer irreparable loss if the guarantee was enforced. The Court granted an interim stay on the operation and implementation of the Deed of Guarantee qua the Plaintiff, restraining the Defendants from acting upon it, subject to the Plaintiff not alienating or encumbering his assets except in the ordinary course of business.

Headnote

A) Contract Law - Conditional Guarantee - Deed of Guarantee - The Deed of Guarantee was executed subject to the condition that it would come into force only upon sanction of the CDR plan under the CDR Scheme. Since the CDR failed and the company exited the CDR mechanism, the guarantee never became effective. (Paras 3.5, 3.7)

B) Contract Law - Automatic Termination - Clause 12 of Deed of Guarantee - The Deed of Guarantee contained clauses for automatic cessation upon occurrence of specified events, including the guarantor ceasing to be a director, CDR becoming inoperative, bankruptcy of the company, and lenders walking out of CDR. All these events occurred, terminating the guarantee. (Paras 3.7, 3.8)

C) Civil Procedure - Interim Relief - Prima Facie Case, Balance of Convenience, Irreparable Loss - The Plaintiff made out a strong prima facie case that the Deed of Guarantee never came into force or stood terminated. Balance of convenience was in favour of granting stay as the Defendants could still proceed against the company and other guarantors. Irreparable loss would be caused to the Plaintiff if the guarantee was enforced pending suit. (Paras 12-14)

D) Limitation - Suit for Declaration - The suit for declaration that the Deed of Guarantee is not binding was filed in 2024, but the cause of action arose when the Defendants sought to enforce the guarantee against the Plaintiff, which is a continuing cause. The issue of limitation is a mixed question of fact and law and cannot be decided at the interim stage. (Para 6)

E) Jurisdiction - Bar under SARFAESI, RDB Act, IBC - The bar under Sections 34 and 35 of SARFAESI Act, Section 18 of RDB Act, and Section 180 of IBC applies only to matters which the DRT or NCLT can adjudicate. The validity and enforceability of a personal guarantee is not exclusively within the jurisdiction of those tribunals, and the Civil Court has jurisdiction to decide the same. (Para 7)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Deed of Guarantee dated 10 April 2014 executed by the Plaintiff in favour of the Defendants is valid and binding, and whether the Plaintiff is entitled to interim relief restraining the Defendants from acting upon the said Deed of Guarantee.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Court allowed the Interim Application and granted an interim stay on the operation and implementation of the Deed of Guarantee dated 10 April 2014 qua the Plaintiff, restraining the Defendants from acting upon it, subject to the Plaintiff not alienating or encumbering his assets except in the ordinary course of business.

Law Points

  • Conditional guarantee
  • Deed of Guarantee
  • Corporate Debt Restructuring
  • CDR failure
  • automatic termination
  • prima facie case
  • balance of convenience
  • irreparable loss
  • limitation
  • jurisdiction bar under SARFAESI
  • RDB Act
  • IBC
  • Order VII Rule 11 CPC
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (12) 142

Interim Application (L) No.3405 of 2024 in Comm. Suit (L) No.3324 of 2024

2024-12-14

N.J. Jamadar

Mr. Zal Andhyarujina, Senior Advocate with Mr. Simil Purohit, Senior Advocate with Ms. Akansha Agarwal, Mr. Ishvendra Tiwari i/by Sonal Doshi and Co., for Applicant/Plaintiff. Mr. Amrut Joshi with Ms. Kajal Gupta, Ms.Shweta Singh, Mr. Yazad Udwadia, Ms. Purvi Jain, Mr. Bhavesh Wadhwani i/by M.V.Kini and Co., for Defendant Nos.1, 5 and 12. Mr. Anant Bamne i/by M/s. A.R.Bamne and Co., for Defendant No.3. Mrs. Rathina Maravarman (through VC) for Defendant Nos.4 and 6. Mr. Nikhil Rajani with Mr. Sheyansh Desai i/by M/s. V. Deshpande and Co., for Defendant No.9. Mr. Fraser Mario Alexander for Defendant No.10. Mr. Benny Joseph with Ms. Pallavi Kamath, Mr. Sameer Solanki i/by BJ Law Officers LLP for Defendant No.15. Mr. Indrajeet Deshmukh i/by Vidhii Partners, for Defendant No.17.

Deepen Arun Parekh

Indian Overseas Bank and Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil suit seeking declaration that Deed of Guarantee is not valid and binding, and interim relief restraining enforcement of the guarantee.

Remedy Sought

Plaintiff seeks a declaration that the Deed of Guarantee dated 10 April 2014 is not valid and binding, and an interim stay on its enforcement.

Filing Reason

The Plaintiff executed a Deed of Guarantee as a pre-requisite for CDR of the Company, which failed. Despite the guarantee being conditional and allegedly terminated, Defendants impleaded the Plaintiff in recovery proceedings.

Issues

Whether the Deed of Guarantee dated 10 April 2014 is valid and binding on the Plaintiff. Whether the suit is barred by limitation. Whether the Civil Court has jurisdiction in view of the bar under SARFAESI Act, RDB Act, and IBC. Whether the Plaintiff is entitled to interim relief restraining the Defendants from acting upon the Deed of Guarantee.

Submissions/Arguments

Plaintiff argued that the Deed of Guarantee was conditional upon CDR sanction and never came into force, and alternatively, it stood automatically terminated under Clause 12 due to CDR failure, his resignation, and other events. Defendants argued that the suit is barred by limitation, the Civil Court lacks jurisdiction due to SARFAESI, RDB, and IBC provisions, and the Plaintiff should have raised his grievances before the DRT.

Ratio Decidendi

A Deed of Guarantee that is conditional upon the sanction of a CDR plan does not become effective if the CDR fails. Additionally, if the guarantee contains clauses for automatic termination upon specified events such as the guarantor ceasing to be a director, CDR becoming inoperative, or lenders walking out, and those events occur, the guarantee stands terminated. The Civil Court has jurisdiction to decide the validity of a personal guarantee, and the bar under SARFAESI, RDB, and IBC does not oust such jurisdiction. Interim relief can be granted if the plaintiff makes out a prima facie case, balance of convenience is in favour, and irreparable loss would ensue.

Judgment Excerpts

The Deed of Guarantee categorically provided that the Plaintiff was providing guarantee in order to comply with the conditions laid down by the CDR Cell with a view to implement the CDR package in respect of the Company. The events referred to in Clause 12 of the Deed of Guarantee, upon happening of which the Deed of Guarantee was to cease to operate, did happen, namely, the Plaintiff ceased to be a member of the Board of Directors; the CDR became inoperative and/or could not be acted upon; bankruptcy and insolvency of the Company and the Defendants - the lenders of the Company - walked out of the CDR.

Procedural History

The Plaintiff filed the suit in 2024 seeking declaration and interim relief. The Defendants filed affidavits in reply and written submissions opposing the application. The Court heard arguments and reserved judgment on 23 September 2024, pronouncing it on 14 December 2024.

Acts & Sections

  • Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002: 34, 35
  • Recovery of Debts and Bankruptcy Act, 1993: 18
  • Insolvency and Bankruptcy Code, 2016: 180
  • Code of Civil Procedure, 1908: Order VII Rule 11(d)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Writ Petition Seeking Enforcement of RERA Order and Grants Interim Relief of Deposit and Injunction Against Developer. RERA Order Directing Refund of Investment with Interest Must Be Complied With by Revenue Authorities and D...
Related Judgement
High Court Bombay High Court Allows Petition by School Against Refund Order — Fees Charged by Unaided Minority School Not Subject to Prior Approval Under Maharashtra Educational Institutions (Prohibition of Capitation Fee) Act, 1987. The court quashed the Pri...