Supreme Court Dismisses Appeal of Power Developer in Mega Power Policy Customs Duty Exemption Dispute — Press Release Not a Binding Policy Change. The court held that a Press Release reducing the capacity threshold for Mega Power Projects from 1000 MW to 700 MW did not create a binding right to customs duty exemption under Section 25 of the Customs Act, 1962, and the appellant had assumed the risk of policy changes under the RFP.

  • 486
Judgement Image
Font size:
Print

Case Note & Summary

The appeal arose from a judgment of the Appellate Tribunal for Electricity (APTEL) dated 30.06.2014, which dismissed the appeal of Nabha Power Limited and another against an order of the Punjab State Electricity Regulatory Commission. The core dispute concerned the applicability of customs duty exemptions for a Mega Power Project. The appellant, Nabha Power Limited, was a special purpose vehicle set up to develop a thermal power plant at Rajpura, Punjab, pursuant to a Request For Proposal (RFP) issued on 10.06.2009 by the erstwhile Punjab State Electricity Board (now PSPCL). The RFP invited bids for procurement of power on a long-term basis under Section 63 of the Electricity Act, 2003. At the time of the RFP, the Mega Power Policy of 2006 was in force, which required an inter-state thermal power plant to have a capacity of 1000 MW or more to qualify for customs duty exemptions under Customs Notification No. 21/2002 dated 01.03.2002. The appellant's project had a capacity of 700 MW, which did not meet the 1000 MW threshold. However, on 01.10.2009, the Ministry of Power issued a Press Release stating that the capacity threshold for Mega Power Projects would be reduced from 1000 MW to 700 MW. The appellant claimed that based on this Press Release, its project should be considered a Mega Power Project and entitled to customs duty exemptions. The State Commission and APTEL rejected this claim, holding that the Press Release was not a binding policy change and that the appellant had assumed the risk of such changes under the RFP. The Supreme Court dismissed the appeal, affirming that the Press Release did not have the force of law and could not override the existing Customs Notification. The court also noted that the RFP clauses required bidders to make independent inquiries and assume risks, and the appellant could not seek relief based on a non-binding Press Release.

Headnote

A) Customs Law - Mega Power Policy - Binding Effect of Press Release - Section 25 of the Customs Act, 1962 - The court considered whether a Press Release issued by the Ministry of Power on 01.10.2009, reducing the capacity threshold for Mega Power Projects from 1000 MW to 700 MW, could be treated as a binding policy change. The court held that the Press Release was merely an expression of intent and did not have the force of law, as it was not followed by a formal notification or amendment to the Customs Notification No. 21/2002. The appellant's reliance on the Press Release was misplaced, and the benefit of customs duty exemption could not be claimed based on it. (Paras 1-20)

B) Electricity Law - Competitive Bidding - Risk Allocation - Section 63 of the Electricity Act, 2003 - The court examined the terms of the Request For Proposal (RFP) issued on 10.06.2009, which required bidders to make independent inquiries and assume risks regarding changes in law. The court held that the appellant, as a successful bidder, was deemed to have accepted the risk of any policy changes, including the non-extension of customs duty benefits. The RFP clauses 2.7.2.1 and 2.7.2.2 made it clear that the bidder could not seek financial compensation or extension of time due to unsuitability of site or changes in law. (Paras 5-6)

C) Administrative Law - Legitimate Expectation - Press Release - The court considered the doctrine of legitimate expectation in the context of the Press Release. It held that a mere Press Release, without a formal policy change or notification, cannot create a legitimate expectation that can be enforced in court. The appellant's claim that it had a legitimate expectation based on the Press Release was rejected, as the Press Release did not amount to a representation that could be relied upon. (Paras 15-20)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Press Release dated 01.10.2009, which reduced the capacity threshold for Mega Power Projects from 1000 MW to 700 MW, was binding on the respondents and whether the appellant was entitled to customs duty exemption based on that Press Release.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court dismissed the appeal, holding that the Press Release dated 01.10.2009 did not have the force of law and could not be treated as a binding policy change. The court affirmed the judgments of the State Commission and APTEL, and held that the appellant was not entitled to customs duty exemption based on the Press Release.

Law Points

  • Customs duty exemption
  • Mega Power Policy
  • Press Release
  • binding effect
  • legitimate expectation
  • change in policy
  • competitive bidding
  • Request For Proposal
  • Section 25 Customs Act 1962
  • Section 63 Electricity Act 2003
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (SC) (11) 54

Civil Appeal No. 8478 of 2014

2024-11-20

K.V. Viswanathan, J.

2024 INSC 833

Nabha Power Limited & Anr.

Punjab State Power Corporation Limited & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Civil appeal against the judgment of the Appellate Tribunal for Electricity (APTEL) dismissing the appellant's challenge to the order of the Punjab State Electricity Regulatory Commission regarding denial of customs duty exemption for a Mega Power Project.

Remedy Sought

The appellant sought to set aside the APTEL judgment and obtain a declaration that its project was entitled to customs duty exemption based on the Press Release dated 01.10.2009.

Filing Reason

The appellant claimed that the Press Release reducing the capacity threshold for Mega Power Projects from 1000 MW to 700 MW should be applied to its 700 MW project, entitling it to customs duty exemptions under Customs Notification No. 21/2002.

Previous Decisions

The Punjab State Electricity Regulatory Commission, by order dated 12.11.2012, rejected the appellant's claim on issue no. 1 (Mega Power Policy and Press Release). The APTEL, by judgment dated 30.06.2014, dismissed the appeal and confirmed the State Commission's order.

Issues

Whether the Press Release dated 01.10.2009, reducing the capacity threshold for Mega Power Projects from 1000 MW to 700 MW, is binding on the respondents and creates a right to customs duty exemption. Whether the appellant, having participated in the bidding process under the RFP dated 10.06.2009, can claim the benefit of the Press Release issued after the RFP.

Submissions/Arguments

The appellant argued that the Press Release dated 01.10.2009 was a policy decision by the Ministry of Power and should be given effect to, as it reduced the capacity threshold for Mega Power Projects to 700 MW, making its project eligible for customs duty exemptions. The respondents contended that the Press Release was not a binding legal document and did not amend the Customs Notification No. 21/2002. They also argued that the appellant had assumed the risk of any changes in law under the RFP clauses.

Ratio Decidendi

A Press Release issued by a government ministry, without a formal notification or amendment to the relevant statutory instrument, does not have the force of law and cannot create a binding right or legitimate expectation. In competitive bidding processes, bidders are deemed to have assumed the risk of policy changes and cannot seek relief based on non-binding announcements.

Judgment Excerpts

The present appeal arises from the judgment dated 30.06.2014 of the Appellate Tribunal for Electricity (for short the “APTEL”) in Appeal No. 29 of 2013. The Press Release of 01.10.2009 was merely an expression of intent and did not have the force of law.

Procedural History

The Punjab State Electricity Regulatory Commission passed an order on 12.11.2012 rejecting the appellant's claim on issue no. 1. The appellant appealed to the APTEL, which dismissed the appeal on 30.06.2014. The appellant then filed the present civil appeal before the Supreme Court.

Acts & Sections

  • Customs Act, 1962: Section 25
  • Electricity Act, 2003: Section 63
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows Appellants in Land Revenue Consolidation Dispute, Holding Fictitious Khasra Entry Cannot Confer Adhivasi Rights Under U.P. Zamindari Abolition and Land Reforms Act, 1950. The Court ruled that a Patwari's entry motivated by hostil...
Related Judgement
Supreme Court Supreme Court Upholds Classification Based on Educational Qualifications for Supernumerary Appointments in Municipal Service. Kolkata Municipal Corporation's Circular Creating Different Service Periods for Diploma and Degree Holder Sub-Assistant Engi...