The dispute arose between the parties regarding the appointment of an arbitrator under the Arbitration and Conciliation Act, 1996. The appellant, M/s. Larsen & Toubro Ltd., contested the High Court's order appointing an arbitrator on behalf of the appellant, arguing that the arbitration clause had been modified by supplementary agreements. The original agreement dated 29.2.1988 was for construction work, with a sub-contract awarded to the respondent, M/s. Mohan Lal Harbans Lal Bhayana. The contract stipulated that payments to the respondent were contingent upon the appellant receiving payments from the principal, SCOPE. The arbitration clause in the original agreement provided for arbitration for disputes, but subsequent supplementary agreements modified this process, requiring joint claims to be raised with SCOPE. The respondent's claims were to be pursued collaboratively, and arbitration between the parties was not permitted until after claims were settled with SCOPE. The respondent's application under Section 11 sought to appoint an arbitrator, which the High Court granted, asserting that the original arbitration clause remained valid. The Supreme Court found that the High Court's interpretation overlooked the significant modifications made by the supplementary agreements. The Court directed that the final bill be settled by SCOPE within two months and outlined procedures for arbitration if disputes remained post-settlement. The appeal was allowed, and the High Court's order was set aside.
Headnote
A) Arbitration Law - Appointment of Arbitrator - High Court's Authority - Arbitration and Conciliation Act, 1996, Section 11 - The High Court appointed an arbitrator for the appellant despite modifications in the arbitration clause through supplementary agreements, which altered the arbitration process. The Supreme Court held that the original arbitration clause was significantly modified, and thus the High Court's order was incorrect (Paras 15-19).
Issue of Consideration
Whether the High Court erred in appointing an arbitrator despite modifications to the arbitration clause in supplementary agreements.
Final Decision
The Supreme Court allowed the appeal, set aside the High Court's order, and directed that the final bill be settled by SCOPE within two months. If disputes remained post-settlement, they would be taken up for arbitration as per the modified agreements.
Law Points
- Arbitration agreement interpretation
- Modification of contract clauses
- Joint claims in arbitration
- Role of supplementary agreements