The case involved a statutory appeal filed by the Appellant, M/s. Sesa Sterlite Ltd., under Section 125 of the Electricity Act, 2003, challenging the orders of the Odisha Electricity Regulatory Commission and the Appellate Tribunal for Electricity. The Appellant, operating in a Special Economic Zone (SEZ), contended that it was a deemed distribution licensee and therefore not liable to pay Cross Subsidy Surcharge (CSS) to WESCO, the local distribution licensee. The Appellant had entered into a Power Purchase Agreement (PPA) with Sterlite Energy Ltd. for its electricity needs and argued that since it was not drawing power from WESCO, the CSS should not apply. The Appellate Tribunal upheld the State Commission's decision that the Appellant was a consumer of WESCO and thus liable for CSS. The Appellant's arguments included the assertion that the notification under Section 14(b) of the Electricity Act made it a deemed licensee, negating the need for a separate license application. The Respondents countered that the Appellant's status as a deemed licensee did not exempt it from CSS obligations, as it was still consuming electricity within WESCO's area of supply. The court analyzed the definitions of 'consumer' and 'distribution licensee' under the Electricity Act and concluded that the Appellant was indeed a consumer and thus liable for CSS. The court emphasized that the CSS is a mechanism to compensate distribution licensees for losses incurred due to consumers opting for open access from other suppliers. Ultimately, the court upheld the Appellate Tribunal's decision, affirming the Appellant's liability to pay CSS to WESCO.

Headnote

A) Electricity Law - Cross Subsidy Surcharge - Liability of Deemed Distribution Licensee - Electricity Act, 2003, Section 14 - The Appellant, as a deemed distribution licensee, was held liable to pay cross subsidy surcharge to WESCO despite its claim of not drawing electricity from WESCO. The court reasoned that the Appellant qualified as a consumer under the Act and thus was obligated to pay CSS for its electricity consumption (Paras 30-31).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether a developer of a notified Special Economic Zone, deemed by law to be a licensee for distribution of electricity, is required to apply to the Electricity Regulatory Commission for a license.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court upheld the Appellate Tribunal's decision, affirming that the Appellant is liable to pay Cross Subsidy Surcharge to WESCO as it qualifies as a consumer under the Electricity Act.

Law Points

  • Cross Subsidy Surcharge
  • Deemed Distribution Licensee
  • Special Economic Zone
  • Electricity Act
  • 2003
  • Power Purchase Agreement
  • Open Access
Subscribe to unlock Law Points Subscribe Now

Case Details

2014 LawText (SC) (04) 115

Civil Appeal No. 5479 of 2013

2013-05-03

A.K. Sikri

Shyam Diwan, R.K. Mehta, Parag P. Tripathi, Shiv Kumar Suri

M/s. Sesa Sterlite Ltd.

Orissa Electricity Regulatory Commission & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Statutory appeal regarding liability to pay cross subsidy surcharge.

Remedy Sought

Appellant sought to overturn the decision requiring payment of CSS.

Filing Reason

Dispute over the classification of the Appellant as a consumer and its obligation to pay CSS.

Previous Decisions

Orders of the Odisha Electricity Regulatory Commission and the Appellate Tribunal were upheld.

Issues

Whether the Appellant, as a deemed distribution licensee, is required to pay CSS. Whether the Appellant qualifies as a consumer under the Electricity Act.

Submissions/Arguments

Appellant argued that it is a deemed distribution licensee and not a consumer of WESCO. Respondents contended that the Appellant's consumption of electricity within WESCO's area necessitates CSS payment.

Ratio Decidendi

The court held that the Appellant, despite being a deemed distribution licensee, is still liable to pay Cross Subsidy Surcharge as it consumes electricity within the area of supply of WESCO.

Judgment Excerpts

The essence of these orders is that even when the Appellant is a 'Deemed Distribution Licensee' for the purpose of Electricity Act, it is still liable to pay Cross Subsidy Surcharge (CSS) to the Respondent No.8 viz. WESCO. The Appellant, as a deemed distribution licensee, was held liable to pay cross subsidy surcharge to WESCO despite its claim of not drawing electricity from WESCO.

Procedural History

The Appellant filed a statutory appeal under Section 125 of the Electricity Act, 2003 against the orders of the Odisha Electricity Regulatory Commission and the Appellate Tribunal for Electricity, which upheld the Commission's decision.

Acts & Sections

  • Electricity Act, 2003: Section 14, Section 42, Section 125
  • Special Economic Zone Act, 2005: Section 49
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Landlady's Petition in Rent Control Case — Notice Demanding Higher Rent Than Agreed Rent Is Valid Under Section 15 of Maharashtra Rent Control Act, 1999. The Court held that a notice under Section 15 demanding a higher rent...
Related Judgement
Supreme Court Supreme Court Upholds Adjudicating Authority's Decision on Document Disclosure in FEMA Proceedings — Clarifies Natural Justice Principles.