The civil appeals arose from a judgment of the High Court of Allahabad, which partially allowed writ petitions filed by M/s Gaursons India Pvt. Ltd., setting aside an order from the Chief Secretary of Uttar Pradesh and a demand notice from the Housing Board. The dispute centered on land acquired under the Vasundhara Scheme, which was to be used for water purification but was later subject to conflicting claims regarding its use. The Housing Board had executed a 2004 Exchange Deed with the predecessors-in-interest of the first respondent, which failed due to the Board's unlawful allotment of land that was already designated for a bird sanctuary. The first respondent subsequently purchased the land in question and sought alternative allotment after the Board's refusal to comply with the High Court's orders. The High Court ruled in favor of the first respondent, leading to the appeals by the State and Housing Board. The Supreme Court upheld the High Court's decision, finding no merit in the appeals and confirming that the Housing Board had failed to fulfill its obligations under the exchange deed. The court emphasized that the 2016 Exchange Deed was a fresh instrument that allowed residential construction and did not carry over the restrictions from the earlier deed. The court extended the timeline for the allotment of flats to the first respondent, dismissing the appeals and ordering that parties bear their own costs.
Headnote
A) Land Law - Exchange Deed Validity - Failure to Allot Alternative Land - Uttar Pradesh Awas Evam Vikas Parishad Adhiniyam, 1965 - The Housing Board failed to exercise due diligence in allotting land under the 2004 Exchange Deed, leading to the conclusion that the deed did not bind the first respondent. The court upheld the High Court's decision that the Housing Board was obligated to make an alternative land arrangement due to its failure (Paras 24-26). B) Land Law - Sale Deed Validity - Right to Transfer Property - Not Applicable - The court affirmed that the predecessors-in-interest had the right to transfer the land to the first respondent, as the alternative land was in lieu of their own acquired land. The court held that the sale deed was valid and the first respondent had the right to the land (Paras 26-28). C) Land Law - 2016 Exchange Deed - Fresh Instrument - Not Binding - The court ruled that the stipulations of the 2004 Exchange Deed did not apply to the 2016 Exchange Deed, which was executed with the State's no-objection and allowed residential construction. The court found that the Housing Board's failure to adhere to the original terms did not bind the first respondent (Paras 30-31).
Issue of Consideration
Whether the High Court correctly set aside the Chief Secretary's order and the demand notice issued by the Housing Board.
Final Decision
The Supreme Court dismissed the appeals filed by the Uttar Pradesh Avas Evam Vikas Parishad and upheld the High Court's judgment, confirming that the Housing Board had failed to fulfill its obligations under the 2004 Exchange Deed. The court extended the timeline for the allotment of 450 EWS/LIG flats by three months.
Law Points
- Land acquisition
- Exchange deed validity
- Writ jurisdiction
- Public interest litigation