Case Note & Summary
The case involved a writ petition filed by the petitioner seeking enforcement of a quarry lease for building-lime-stone in Junagadh, granted by the Collector on 31st March 1987. The petitioner applied for the lease on 19th September 1985, but despite the grant, the lease agreement was not executed, and possession was not given. The respondents admitted the grant but stated that the area was later notified for allotment to khaniyas, which prevented the execution of the lease. An interim relief was granted on 28th July 1987, directing the respondents to execute a lease deed for a remaining area of 0.24 are. However, the petitioner did not complain about non-compliance with this order. The court observed that the lease was valid for only five years, which had since expired, leading to the conclusion that the writ petition no longer survived. Consequently, the court dismissed the petition, discharging the rule with no order as to costs.
Headnote
A) Writ Jurisdiction - Quarry Lease - Expiry of Lease Period - Constitution of India, 1950 - The petitioner sought enforcement of a quarry lease granted for five years, but the lease period had expired without possession being granted. The court noted that the petitioner did not raise any grievance regarding compliance with interim relief and thus held that the writ petition did not survive (Paras 3-5).
Issue of Consideration
Whether the writ petition survives given the expiry of the quarry lease period and compliance with interim relief.
Final Decision
The writ petition was dismissed as it did not survive due to the expiry of the lease period and the lack of grievances regarding compliance with interim relief. The rule was discharged with no order as to costs.
Law Points
- Writ jurisdiction
- Quarry lease
- Interim relief
- Compliance with court orders