Case Note & Summary
The dispute involved Joginder Singh H Chhabra and the National Building Construction Corporation Ltd. The parties reached a settlement and filed consent terms with the court. The court noted the amounts to be paid to the respondent, including Rs.6,93,461 towards consideration and Rs.2,39,877 towards interest, both of which were deposited via demand drafts. Additionally, Rs.3000 was allocated for the Legal Aid Committee. The court directed that upon receipt of the amounts, the original defendant-respondent was to execute the necessary documents and hand over possession. The court allowed the appeal, quashed the trial court's order, and directed that a decree in terms of the compromise be drawn. The decision was made by the bench comprising Justice B.C. Patel and Justice H.R. Shelat on 1996-12-05.
Headnote
A) Civil Procedure - Settlement - Allowance of Appeal - Code of Civil Procedure, 1908 - The parties reached a settlement and filed consent terms, leading to the court allowing the appeal and quashing the trial court's order. The court directed the payment of specified amounts to the respondent and the execution of the agreement as per the settlement terms. Held that the appeal was allowed based on the mutual agreement of the parties (Paras Not mentioned).
Issue of Consideration
Whether the appeal should be allowed based on the settlement reached between the parties.
Final Decision
The court allowed the appeal, quashed the trial court's order, and directed the payment of specified amounts to the respondent as per the settlement terms.
Law Points
- Settlement
- Consent Terms
- Payment Directions
- Quashing of Trial Court Order